• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Evolution of 110 kV Substation Power Supply Side Bus Connection Configurations

Vziman
Field: Manufacturing
China

Early 110 kV substations typically adopted the "internal bus connection" configuration on the power supply side, where the power source commonly used the "internal bridge connection" method. This was often observed in certain 220 kV substations supplying 110 kV buses from different transformers in a "same-direction dual-power" arrangement. This setup involved two transformers, with the 10 kV side using a single busbar with sectionalized connection.

Advantages included simple wiring, convenient operation, straightforward automatic transfer switching, and only three switches required on the power side for the two transformers. Additionally, the power-side busbar did not require separate protection—being covered within the transformer differential protection zone—and the overall investment was lower. However, limitations existed: each busbar could accommodate only one transformer, constraining the growth of the 10 kV load capacity. Moreover, when one transformer was in operation, half of the substation had to be de-energized, creating a risk of complete station blackout if the other half experienced equipment failure.

To enhance station capacity and improve supply reliability, an intermediate-stage solution for 110 kV substations adopted the "expanded internal bus connection" method, with the power side mainly using the "expanded bridge connection." This configuration involved three transformers. Power was supplied through two "side busbars" from the same-direction dual-power 110 kV buses of a single 220 kV substation, and one "middle busbar" from a different-direction single-power supply of another 220 kV substation.

The 10 kV side continued to use a single sectionalized busbar, ideally segmenting the middle transformer’s 10 kV output into sections A and B. This approach increased the number of 10 kV outgoing circuits and allowed load redistribution from the middle transformer to the other two in case of outage. However, it introduced greater complexity in operation and automatic switching, along with higher investment.

With urban expansion, increasing land scarcity, and surging electricity demand, there arose a pressing need to further boost substation capacity and reliability. The current design for 110 kV substations primarily employs a single sectionalized busbar on the power side, connecting four transformers—each linked to separate buses, with the two middle transformers cross-connected to the upstream power source. On the 10 kV side, an A/B segmented configuration is used, forming an eight-segment "ring connection" powered by the four transformers.

This design increases the number of 10 kV outgoing circuits and enhances supply reliability. The cross-connection of the two middle transformers to the upstream source ensures uninterrupted power supply to the eight-segment 10 kV busbar even if one 110 kV busbar is de-energized. Drawbacks include the need for dedicated protection on the 110 kV busbar, high initial investment, and increased operational complexity.

Give a tip and encourage the author!

Recommended

HECI GCB for Generators – Fast SF6 Circuit Breaker
1.Definition and Function1.1 Role of the Generator Circuit BreakerThe Generator Circuit Breaker (GCB) is a controllable disconnect point located between the generator and the step-up transformer, serving as an interface between the generator and the power grid. Its primary functions include isolating generator-side faults and enabling operational control during generator synchronization and grid connection. The operating principle of a GCB is not significantly different from that of a standard c
01/06/2026
Design Principles for Pole-Mounted Distribution Transformers
Design Principles for Pole-Mounted Distribution Transformers(1) Location and Layout PrinciplesPole-mounted transformer platforms should be located near the load center or close to critical loads, following the principle of “small capacity, multiple locations” to facilitate equipment replacement and maintenance. For residential power supply, three-phase transformers may be installed nearby based on current demand and future growth projections.(2) Capacity Selection for Three-Phase Pole-Mounted Tr
12/25/2025
Transformer Noise Control Solutions for Different Installations
1.Noise Mitigation for Ground-Level Independent Transformer RoomsMitigation Strategy:First, conduct a power-off inspection and maintenance of the transformer, including replacing aged insulating oil, checking and tightening all fasteners, and cleaning dust from the unit.Second, reinforce the transformer foundation or install vibration isolation devices—such as rubber pads or spring isolators—selected based on the severity of vibration.Finally, strengthen sound insulation at weak points of the ro
12/25/2025
Rockwill Passes Single-Phase Ground Fault Test for Smart Feeder Terminal
Rockwill Electric Co., Ltd. has successfully passed the real-scenario single-phase-to-ground fault test conducted by the Wenzhou of China Electric Power Research Institute for its DA-F200-302 hood-type feeder terminal and integrated primary-secondary pole-mounted circuit breakers—ZW20-12/T630-20 and ZW68-12/T630-20—receiving an official qualified test report. This achievement marks Rockwill Electric as a leader in single-phase ground fault detection technology within distribution networks.The DA
12/25/2025
Related Products
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.