• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Evolution of 110 kV Substation Power Supply Side Bus Connection Configurations

Vziman
Vziman
Field: Manufacturing
China

Early 110 kV substations typically adopted the "internal bus connection" configuration on the power supply side, where the power source commonly used the "internal bridge connection" method. This was often observed in certain 220 kV substations supplying 110 kV buses from different transformers in a "same-direction dual-power" arrangement. This setup involved two transformers, with the 10 kV side using a single busbar with sectionalized connection.

Advantages included simple wiring, convenient operation, straightforward automatic transfer switching, and only three switches required on the power side for the two transformers. Additionally, the power-side busbar did not require separate protection—being covered within the transformer differential protection zone—and the overall investment was lower. However, limitations existed: each busbar could accommodate only one transformer, constraining the growth of the 10 kV load capacity. Moreover, when one transformer was in operation, half of the substation had to be de-energized, creating a risk of complete station blackout if the other half experienced equipment failure.

To enhance station capacity and improve supply reliability, an intermediate-stage solution for 110 kV substations adopted the "expanded internal bus connection" method, with the power side mainly using the "expanded bridge connection." This configuration involved three transformers. Power was supplied through two "side busbars" from the same-direction dual-power 110 kV buses of a single 220 kV substation, and one "middle busbar" from a different-direction single-power supply of another 220 kV substation.

The 10 kV side continued to use a single sectionalized busbar, ideally segmenting the middle transformer’s 10 kV output into sections A and B. This approach increased the number of 10 kV outgoing circuits and allowed load redistribution from the middle transformer to the other two in case of outage. However, it introduced greater complexity in operation and automatic switching, along with higher investment.

With urban expansion, increasing land scarcity, and surging electricity demand, there arose a pressing need to further boost substation capacity and reliability. The current design for 110 kV substations primarily employs a single sectionalized busbar on the power side, connecting four transformers—each linked to separate buses, with the two middle transformers cross-connected to the upstream power source. On the 10 kV side, an A/B segmented configuration is used, forming an eight-segment "ring connection" powered by the four transformers.

This design increases the number of 10 kV outgoing circuits and enhances supply reliability. The cross-connection of the two middle transformers to the upstream source ensures uninterrupted power supply to the eight-segment 10 kV busbar even if one 110 kV busbar is de-energized. Drawbacks include the need for dedicated protection on the 110 kV busbar, high initial investment, and increased operational complexity.

Give a tip and encourage the author!
Recommended
PT Fuse Slow Blow: Causes, Detection & Prevention
PT Fuse Slow Blow: Causes, Detection & Prevention
I. Fuse Structure and Root Cause AnalysisSlow Fuse Blowing:From the design principle of fuses, when a large fault current passes through the fuse element, due to the metal effect (certain refractory metals become fusible under specific alloy conditions), the fuse first melts at the soldered tin ball. The arc then rapidly vaporizes the entire fuse element. The resulting arc is quickly extinguished by quartz sand.However, due to harsh operating environments, the fuse element may age under the comb
Edwiin
10/24/2025
Why Fuses Blow: Overload, Short Circuit & Surge Causes
Why Fuses Blow: Overload, Short Circuit & Surge Causes
Common Causes of Fuse BlowingCommon reasons for fuse blowing include voltage fluctuations, short circuits, lightning strikes during storms, and current overloads. These conditions can easily cause the fuse element to melt.A fuse is an electrical device that interrupts the circuit by melting its fusible element due to heat generated when current exceeds a specified value. It operates on the principle that, after an overcurrent persists for a certain period, the heat produced by the current melts
Echo
10/24/2025
Fuse Maintenance & Replacement: Safety and Best Practices
Fuse Maintenance & Replacement: Safety and Best Practices
1. Fuse MaintenanceFuses in service should be regularly inspected. The inspection includes the following items: Load current should be compatible with the rated current of the fuse element. For fuses equipped with a fuse blown indicator, check whether the indicator has actuated. Check the conductors, connection points, and the fuse itself for overheating; ensure connections are tight and making good contact. Inspect the fuse exterior for cracks, contamination, or signs of arcing/discharge. Liste
James
10/24/2025
Maintenance and Repair Items for 10kV High-Voltage Switchgear
Maintenance and Repair Items for 10kV High-Voltage Switchgear
I. Routine Maintenance and Inspection(1) Visual Inspection of Switchgear Enclosure No deformation or physical damage to the enclosure. Protective paint coating shows no severe rust, peeling, or flaking. Cabinet is securely installed, clean on the surface, and free of foreign objects. Nameplates and identification labels are neatly affixed and not falling off.(2) Check of Switchgear Operating Parameters Instruments and meters indicate normal values (comparable to typical operating data, with no s
Edwiin
10/24/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.