I. Fuse Structure and Root Cause Analysis

Slow Fuse Blowing:
From the design principle of fuses, when a large fault current passes through the fuse element, due to the metal effect (certain refractory metals become fusible under specific alloy conditions), the fuse first melts at the soldered tin ball. The arc then rapidly vaporizes the entire fuse element. The resulting arc is quickly extinguished by quartz sand.

However, due to harsh operating environments, the fuse element may age under the combined effects of gravity and thermal accumulation. This can lead to fuse fracture even under normal load current. Since the fuse blows under normal current, the melting process is slow. As the fuse resistance gradually increases, the phase voltage amplitude drops, potentially causing maloperation of associated protection relays.

Impact of PT Slow Fuse Blow:
If the high-voltage side PT fuse does not fully clear within the specified time, the resistance of the fuse tube increases continuously, causing a steady decrease in the secondary output voltage of the voltage transformer (TV).

II. Hazards of PT Slow Fuse Blow

  • Excitation system initiates field forcing, leading to over-excitation and overvoltage protection activation.

  • Maloperation of stator ground fault protection.

  • Generator and turbine overloading, which may cause equipment damage in severe cases.

PT fuse.jpg

III. Root Cause Analysis

  • Different materials used in the primary plug-in contacts of the output voltage transformer cause oxidation layers and poor contact; loose connection bolts increase temperature rise on the fuse.

  • High ambient temperature around the PT fuse. The fuse element is made of low-melting-point metal and is very thin—mechanical vibration alone may cause breakage.

  • Poor-quality PT fuses are prone to degradation or premature failure during operation.

  • Transient overvoltages from sudden breaker closing or intermittent arc grounding may cause ferroresonance, leading to primary and secondary fuse blowing in voltage transformers.

  • Low-frequency saturation current can cause primary and secondary fuse blowing in voltage transformers.

  • Reduced insulation or short circuits in primary/secondary windings of the voltage transformer, or degraded insulation in the harmonic suppressor, may cause fuse blowing.

  • Single-phase-to-ground faults may lead to voltage transformer burnout.

  • Generators are typically grounded via an arc suppression coil at the neutral point. However, this configuration can amplify neutral point displacement voltage, causing one or two phases to sustain voltages significantly above normal for extended periods, leading to PT fuse blowing.

IV. Preventive Measures

  • For oxidation and poor contact at primary plug contacts due to material mismatch, perform contact surface polishing during maintenance and apply conductive grease.

  • To address unstable fuse quality, replace high-voltage primary fuses periodically according to the equipment maintenance schedule. Contact surfaces must be de-oxidized and coated with conductive grease.

  • For systems with high vibration: after pushing the PT trolley to the service position, verify all conductive connections are secure and free of looseness. If necessary, withdraw the trolley and tighten bolts. During unit outages with no work on the generator primary or generator outlet PT circuits, keep the generator outlet PT in standby (do not disconnect it). Only open the secondary circuit breaker. This minimizes frequent insertion/removal, preventing fuse drop, mechanical damage, or poor contact with socket spring clips—reducing the likelihood of high-voltage fuse failure. (Before placing the generator in hot standby, operating personnel must verify the integrity of the primary PT fuse.)

  • During single-phase-to-ground faults, if the generator operates at rated frequency, transient overvoltage on healthy phases can reach up to 2.6 times the rated phase voltage. Therefore, generator outlet voltage transformers must be selected to withstand these overvoltages:

    • Steady-state overvoltage withstand ≥ line voltage

    • Transient overvoltage withstand ≥ 2.6 × rated phase voltage
      PT fuse selection must not only isolate internal transformer short circuits but also protect against overvoltage conditions such as voltage rise and ferroresonance.

Primary harmonic suppression: Install a grounding voltage transformer between the primary neutral point of the VT and ground. This effectively suppresses or eliminates overvoltage in the primary winding and prevents ferroresonance and transformer burnout.

Secondary harmonic suppression: Install a damping device (secondary harmonic suppressor) across the open delta of the VT’s residual winding. Modern microprocessor-based harmonic suppressors detect incipient resonance and instantly connect a damping resistor to eliminate ferroresonance. When the generator neutral is grounded via an arc suppression coil (whose inductance is much smaller than the VT’s magnetizing inductance), ferroresonance overvoltage is effectively prevented. Therefore, ferroresonance need not be considered in PT fuse blow analysis.

Coordinate with the excitation system manufacturer to ensure the excitation regulator includes logic to detect slow blowing of PT primary fuses (considering single-phase, two-phase, and three-phase fuse failure scenarios) and secondary circuit breaks. Upon detecting a PT break, the main excitation channel should automatically switch from AVR mode to FCR mode, or switch to the backup channel. Adjust the threshold settings in the PT break detection logic to reduce false triggering of field forcing due to poor PT circuit contact, thereby improving system sensitivity and reliability.

V. Methods for Detecting PT Slow Fuse Blow

Criterion 1: Introduction of Zero-Sequence and Negative-Sequence Voltage

a) Zero-Sequence Voltage Method
Monitor the open-delta voltage on the PT secondary side. Compare the generator terminal zero-sequence voltage with the neutral point zero-sequence voltage. If the absolute difference exceeds a preset threshold, a PT slow fuse blow is indicated. In this case, the stator negative-sequence current criterion must be blocked.

b) Negative-Sequence Voltage Method
The excitation system only measures generator terminal voltage, not neutral point voltage, making the zero-sequence method inapplicable. Instead, decompose the PT secondary voltage to extract the negative-sequence component. If the negative-sequence voltage exceeds a set threshold, a PT primary fuse slow blow is detected. The stator negative-sequence current criterion must also be blocked.

Criterion 2:
UAB – Uab > 5V
UBC – Ubc > 5V
UCA – Uca > 5V

Key Point: Use zero-sequence, negative-sequence, and voltage comparison methods. Never use positive-sequence voltage (used by protection relays) to detect primary PT fuse failure, because the broken phase still induces voltage (not zero), which may not satisfy positive-sequence criteria.

A primary PT fuse break causes induced imbalance in the secondary EMF, resulting in voltage at the open delta and triggering a zero-sequence alarm. This phenomenon does not occur with a secondary fuse blow—this is the primary distinguishing criterion between primary and secondary fuse failures.

A primary PT fuse break reduces the secondary induced voltage (because the other two phases still produce flux in the core), so the corresponding secondary phase voltage decreases. In contrast, a secondary fuse break removes the winding from the circuit, causing the phase voltage to drop to zero.

Give a tip and encourage the author!
Recommended
Why does a 2-in 4-out 10 kV solid-insulated ring main unit have two incoming feeder cabinets?
Why does a 2-in 4-out 10 kV solid-insulated ring main unit have two incoming feeder cabinets?
A "2-in 4-out 10 kVsolid-insulated ring main unit" refers to a specific type of ring main unit (RMU). The term "2-in 4-out" indicates that this RMU has two incoming feeders and four outgoing feeders.10 kVsolid-insulated ring main unit are equipment used in medium-voltage power distribution systems, primarily installed in substations, distribution stations, and transformer stations to distribute high-voltage power to low-voltage distribution networks. They generally consist of high-voltage incomi
Garca
12/10/2025
Low-Voltage Distribution Lines and Power Distribution Requirements for Construction Sites
Low-Voltage Distribution Lines and Power Distribution Requirements for Construction Sites
Low-voltage distribution lines refer to the circuits that, through a distribution transformer, step down the high voltage of 10 kV to the 380/220 V level—i.e., the low-voltage lines running from the substation to the end-use equipment.Low-voltage distribution lines should be considered during the design phase of substation wiring configurations. In factories, for workshops with relatively high power demand, dedicated workshop substations are often installed, where transformers supply power direc
James
12/09/2025
How to Implement Transformer Gap Protection & Standard Shutdown Steps
How to Implement Transformer Gap Protection & Standard Shutdown Steps
How to Implement Transformer Neutral Grounding Gap Protection Measures?In a certain power grid, when a single-phase ground fault occurs on a power supply line, both the transformer neutral grounding gap protection and the power supply line protection operate simultaneously, causing an outage of an otherwise healthy transformer. The main reason is that during a system single-phase ground fault, the zero-sequence overvoltage causes the transformer neutral grounding gap to break down. The resulting
Noah
12/05/2025
Chinese Protection Relay Earns IEC 61850 Ed2.1 Level-A Certification
Chinese Protection Relay Earns IEC 61850 Ed2.1 Level-A Certification
Recently, the NSR-3611 low-voltage protection and control device and the NSD500M high-voltage measurement and control device—both developed by a Chinese protection and control equipment manufacturer—successfully passed the IEC 61850 Ed2.1 Server Level-A certification test conducted by DNV (Det Norske Veritas). The devices have been awarded the international Level-A certification by the Utilities Communication Architecture International Users Group (UCAIug). This milestone marks the manufacturer
Baker
12/02/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.