Paunsa ha Korrekto ang Pag-install ug Pagsulay sa Vacuum Circuit Breaker?

James
James
Larangan: Operasyon sa Elektrolyo
China

Pag-install ug Pag-ajust sa Vacuum Circuit Breakers

1. Mga Requisito sa Pag-install

  • Ang tanang bahin ug komponente kinahanglan i-inspect ug i-approve bago ang pag-install.

  • Ang mga fixture ug tools nga gamiton sa pag-install kinahanglan malinis ug naka-meet sa mga requisito sa assembly. Ang mga fixed fasteners kinahanglan i-tighten gamit ang box-end, ring, o socket wrenches. Dili mahimong gamiton ang adjustable (open-end) wrenches sa pag-tighten sa mga screws duol sa arc extinguishing chamber.

  • Ang sequence sa pag-install kinahanglan mofollow ang specified assembly process. Ang mga tipo ug specifications sa fastener kinahanglan mastrictly comply sa design requirements. Partikular, ang length sa bolts nga nag-fix sa stationary contact terminal sa arc extinguishing chamber dili mahimong sayon.

  • Human sa assembly, ang pole-to-pole distance ug ang positional distances sa upper ug lower output terminals kinahanglan mosunod sa drawing specifications.

  • Ang tanang rotating ug sliding components kinahanglan molihok libre human sa assembly. I-apply ang lubricating grease sa friction surfaces.

  • Human sa successful adjustment ug testing, clean ug wipe thoroughly ang tanang parts. Marka ang adjustable connection points pinaagi sa red paint aron ipailustrar ang position, ug coat ang output terminals pinaagi sa petroleum jelly, then wrap gamit ang clean paper alang sa protection.

2. Procedure sa Assembly

Tumong sa ZN39-type vacuum circuit breaker isip ehempiyo, ang assembly kay kasagaran gihatag og tulo ka bahin: front, upper, ug rear.

Front Section Assembly Sequence:
Frame positioning → Support insulators → Horizontal insulators → Support bracket → Lower busbar → Arc extinguishing chamber and parallel insulating rods → Upper busbar → Conductive clamp with flexible connection → Contact spring seat and sleeve → Triangular crank arm.

Upper Section Assembly Sequence:
Main shaft and bearing housing → Oil damper → Insulating push rod.

Rear Section Assembly Sequence:
Operating mechanism → Opening spring → Counter, open/close indicator, grounding mark.

Integration of the Three Sections:

  • Connect the front and upper sections: link the adjustable joint of the insulating push rod to the triangular crank arm with a pin.

  • Connect the rear and upper sections: link the adjustable drive rod of the operating mechanism to the main shaft crank arm with a pin.

Ang assembly process simple, intuitive, ug convenient.

Vacuum circuit breaker..jpg

3. Pag-ajust sa Mechanical Characteristic

3.1 Preliminary Adjustment

Ang preliminary adjustment primarily involves coarse tuning of the contact gap (opening distance) ug contact travel (overtravel) para sa matag pole human sa full assembly.

Manually close the breaker slowly to verify correct installation and connection of all components. Avoid setting excessive contact travel, as this may compress the closing spring fully (spring binding), potentially damaging components. To prevent this, initially set the adjustable joint of the insulating push rod shorter (screwed in). After confirming smooth manual operation, proceed to measure and adjust the opening distance and contact travel.

3.2 Adjustment of Opening Distance and Contact Travel

Ang vacuum circuit breakers can be broadly classified into two types based on the relative position of the moving contact rod axis and the closing spring axis:

  • Type I: Coaxial Structure – Moving contact cup axis coincides with the closing spring axis.

  • Type II: Offset (Non-coaxial) Structure – Moving contact rod axis is separate from the closing spring axis, with the spring mounted on the insulating push rod shaft, nearly perpendicular to the contact rod.

The calculation and adjustment methods differ slightly between these two types.

Mechanical characteristic tables for various vacuum circuit breakers specify nominal values for opening distance and contact travel. After manually performing open and close operations and measuring actual values, adjust as follows to meet technical specifications.

(1) Adjustment for Coaxial Structures

  • Step 1: Adjust Total Travel
    Total travel = Opening distance + Contact travel.
    If total travel is less than the sum of nominal values, the main shaft rotation is insufficient. Lengthen the adjustable connecting rod between the operating mechanism and main shaft crank arm. If too long, shorten the rod. This ensures total travel meets requirements.

  • Step 2: Adjust Distribution Between Opening Distance and Contact Travel
    Adjust the threaded connection at the front end of each pole’s insulating rod.

    Minimum adjustment: half a thread pitch (by turning the joint 180°).
    This threaded joint also adjusts three-phase synchronization. Adjustments must balance travel values and phase synchronization. Repeat manual open/close cycles until both are within tolerance. Never exceed maximum allowable contact travel to avoid spring binding and component damage.

    • Lengthen connection (screw out): Opening distance ↑, Contact travel ↓

    • Shorten connection (screw in): Opening distance ↓, Contact travel ↑

(2) Adjustment for Offset (Non-coaxial) Structures

In this design, the closing spring axis and moving contact axis are not aligned, so total travel has no direct physical meaning. Adjustment methods differ:

  • Opening Distance Adjustment:
    Achieved via an "opening distance adjustment shim" mounted on the frame. The shim’s height is adjusted by adding or removing layers. The top is pressed by the main shaft’s crank arm. Changing the shim height alters the main shaft’s initial angle in the open position, thereby changing the contact opening distance through the insulating push rod.

  • Contact Travel Adjustment:
    The pre-compression height (B1) of the contact spring is fixed by the roller diameter and cannot be changed. The final compression height (B2) after closing is adjusted by:

    During adjustment, simultaneously optimize three-phase synchronization, making repeated fine adjustments until all parameters are within tolerance.

    • Lengthen rod: B2 decreases → Contact travel increases

    • Shorten rod: B2 increases → Contact travel decreases

    • Screw in (shorten rod): B2 increases → Contact travel decreases

    • Screw out (lengthen rod): B2 decreases → Contact travel increases

    • A. Adjusting the threaded joint at the end of the insulating push rod:

    • B. Adjusting the length of the connecting rod between the operating mechanism and the main shaft crank arm:

(3) Auxiliary Switch Interlock Adjustment

After manually adjusting opening distance and contact travel, the auxiliary switch interlock position must be properly set before electric operation—otherwise, electrical components may be damaged.

Adjustment Procedure:

  • Disconnect the pin between the auxiliary switch and the main shaft crank arm linkage.

  • Manually close the breaker while rotating the auxiliary switch to the point just before it trips. Adjust the length of the adjustable rod and bolt so that the pin holes align approximately.

  • Manually open the breaker and rotate the auxiliary switch to its trip point again, ensuring pin holes align.

  • Repeat the process until alignment is achieved in both open and close positions, then insert the pin.

  • Ensure the auxiliary switch contacts open slightly before the main contacts fully close or open.

4. Mechanical Characteristic Testing, Fine Adjustment, and Factory Tests

4.1 Characteristic Testing

After preliminary adjustment of opening distance, contact travel, and auxiliary switch, perform electric open/close operations and measure the following mechanical characteristics:

  • Opening/closing time

  • Speed

  • Phase-to-phase synchronization (out-of-phase)

  • Closing bounce

Testing Instruments:

  • Optical oscillograph – highly accurate and visual

  • Circuit breaker analyzer – simple, fast, and sufficiently accurate for field use

(Specific test methods are not detailed here.)

4.2 Fine Adjustment of Mechanical Characteristics

After testing, perform fine adjustments on any out-of-spec parameters to achieve optimal performance.

(1) Fine Adjustment of Synchronization
Identify the phase with the greatest timing deviation. If one pole closes too early (or late), slightly increase (or decrease) its opening distance by turning the insulating rod’s adjustable joint in (for earlier closure) or out (for later closure) by about half a turn. Typically, this can reduce synchronization error to within 1 ms.

(2) Fine Adjustment of Opening/Closing Speed
Speed is influenced by multiple factors, but key adjustable elements are the opening spring tension and contact travel.

  • Closing speed too high, opening speed too low:
    Increase contact travel or tighten the opening spring.

  • Closing speed acceptable, opening speed too low:
    Increase total travel by 0.1–0.2 mm, which increases contact travel and improves opening speed.

  • Opening speed too high:
    Reduce contact travel by 0.1–0.2 mm to lower speed.

After adjustment, re-measure opening distance and contact travel to ensure they remain within specified ranges.

(3) Elimination of Closing Bounce

Closing bounce may result from:

  • Excessive closing impact rigidity, causing axial rebound of the moving contact.

  • Poor guidance of the moving contact rod, resulting in excessive wobble.

  • Excessive clearance in transmission links, especially between the contact spring and the conductive rod.

  • Poor perpendicularity between the contact surface and the central axis, causing lateral slip upon contact (appears as "bounce" on oscillograms).

Mitigation Measures:

  • Design should avoid excessive mechanical rigidity (not adjustable post-manufacture).

  • Ensure proper guidance clearance for the moving contact rod.

  • In coaxial designs, the contact spring connects directly to the conductive rod—no intermediate links, hence less bounce.

  • In offset designs, a triangular crank arm with three pins introduces three potential clearances, increasing bounce risk.

If bounce is caused by poor perpendicularity of the arc extinguishing chamber contact surface, try rotating the chamber by 90°, 180°, or 270° during assembly to find the optimal alignment. If ineffective, replace the arc extinguishing chamber.
Ensure all screws are fully tightened during adjustment to avoid vibration interference.

(4) Factory Acceptance Tests

After all mechanical characteristics meet specifications, perform 50 operation cycles (open/close and reclose) at maximum, minimum, and rated control voltage as per factory requirements.

After 50 operations, re-measure all mechanical parameters. Results should closely match initial measurements to pass.

Finally, perform:

  • Circuit resistance test

  • Power frequency withstand voltage tests on primary and secondary circuits

Only units passing all tests are approved for shipment.

Maghatag og tip ug pagsalig sa author
Gipareserbado
Paunsa sa Pagdisenyo sa mga Poste sa 10kV Overhead Line
Paunsa sa Pagdisenyo sa mga Poste sa 10kV Overhead Line
Ang maong artikulo nagpadayon sa mga praktikal nga ehasemplo aron mapuli an ang logika sa pagpili para sa 10kV steel tubular poles, nagdiskusyon sa malinaw nga pangkalahatang mga patakaran, proseso sa disenyo, ug partikular nga mga kinahanglanan alang sa paggamit sa 10kV overhead line design ug konstruksyon.Ang espesyal nga kondisyon (tulad sa long spans o heavy ice zones) nangangailigan og daghan pa kaayo nga espesyal nga veripikasyon batas sa kini nga pundasyon aron masiguro ang lami ug reliab
James
10/20/2025
Paunsa sa pagpili og dry-type transformer?
Paunsa sa pagpili og dry-type transformer?
1. Sistema sa Pagkontrol sa TemperaturaAng usa ka sa mga pangunahon nga dahon sa pagkawasak sa transformer mao ang pagkasira sa insulation, ug ang pinakadako nga banta sa insulation mao ang paglangkob sa makatarungan nga limitasyon sa temperatura sa mga winding. Kini nga rason, ang pagmonitor sa temperatura ug ang pag-implementar sa sistema sa alarm para sa mga nagoperasyon nga transformers mahimong dili malipayan. Ang sumusunod mao ang pagpakilala sa sistema sa pagkontrol sa temperatura gamit a
James
10/18/2025
Paunsa ang Tama nga Transformer?
Paunsa ang Tama nga Transformer?
Pamilihan ug Pag-configure sa Transformer1. Importansya sa Pamilihan ug Pag-configure sa TransformerAng mga transformer naglakip og importante nga papel sa sistema sa kuryente. Sila moguba sa nivel sa voltaje aron mapasabot sa lain-lain nga pangangailihan, nahimo ang pagpadala ug pagdistribute sa gikinahanglan nga kuryente mula sa mga planta sa kuryente. Ang dili maayo nga pamilihan o pag-configure sa transformer mahimong magresulta sa serius nga problema. Pwede masulti, kon ang kapasidad dili m
James
10/18/2025
Paunsa ang 10kV Vacuum Circuit Breakers sa Maayong Paraan
Paunsa ang 10kV Vacuum Circuit Breakers sa Maayong Paraan
I. Paghunahon sa Vacuum Circuit Breakers Sa Normal nga Operasyon1. Paghunahon sa Closed (ON) Position Ang operasyon mechanism dapat naa sa closed position; Ang main shaft roller dapat wala naka-engage sa oil damper; Ang opening spring dapat naa sa charged (stretched) energy-stored state; Ang length sa moving contact rod sa vacuum interrupter nga nagpakita sa ilalum sa guide plate dapat mga 4–5 mm; Ang bellows sa sulod sa vacuum interrupter dapat makita (wala niini sa ceramic-tube interrupters);