• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


The 8-Phase Guide to Installing LW25-126 High-Voltage Circuit Breakers Correctly

James
James
Field: Electrical Operations
China

1. Pre-Installation Preparations

Before commencing installation work, the following preparatory steps must be completed:

  • Organization and Training: Organize training sessions for all construction personnel on relevant regulations,technical standards, and construction procedures. Special emphasis should be placed on safety protocols.

  • Site Survey: Examine the intended location of the circuit breaker, its foundation, and the layout of  surrounding equipment and wiring to prevent accidental contact with energized equipment during installation.

  • Preparation of Tools and Materials:Position specialized tools and required materials near the work site and   implement protective measures against rain. Maintain a detailed checklist of all tools and materials, including types and quantities.


2. Common Issues During Installation and Corresponding Solutions

Prior to beginning installation, conduct the following additional inspections:

  • Inspect Internal Components: Check that all internal components (e.g., relays) within the operating mechanism are complete and undamaged. Pay particular attention to insulating parts, ensuring their surfaces are free from cracks or damage.

  • Inspect Porcelain Bushings: Examine porcelain bushings for smoothness and absence of cracks. If in doubt, request non-destructive testing (NDT). Also verify the strength and integrity of the bond between the bushing and flange.

  • Inspect Component Materials:Confirm the availability and condition of bolts, sealing gaskets, sealing grease, lubricating grease, and other auxiliary materials.

Support Structure Installation

  • Use cranes for lifting, with one signalman assigned per crane.

  • Crane operators and signalmen must take care to avoid contact  between the crane boom and overhead busbars or electrical equipment in adjacent bays.

  • All other personnel have the responsibility to warn against and  prevent accidental contact.

  • No more than three shims should be used between the support and  foundation, with a total thickness not exceeding 10 mm.

Crossbeam and Operating Mechanism Installation

  • The crossbeam and operating mechanism form a single unit. Use  two lifting slings during hoisting—one attached to the crossbeam and the  other to the operating mechanism—to prevent imbalance.

  • After installation, verify that the crossbeam is level and  meets specified tolerances.

Main Pole Column Installation

  • Ensure the flange surfaces of the three-phase porcelain bushings are aligned on the same horizontal plane.

  • The deviation in center-to-center distance between each pole  column should not exceed 5 mm.

  • Use a torque wrench to tighten the bolts connecting the pole column to the crossbeam, ensuring torque values comply with the manufacturer’s specifications.

Connecting Linkages, Secondary Wiring, Primary Leads, and SF6 Piping

Linkage Connections

  • Sequence: First connect the linkage between the pole column and  the operating mechanism, then connect the linkages between pole columns.

  • Apply a mixture of engine oil and molybdenum disulfide lubricant to the pin joints to ensure smooth operation.

Secondary Control Wiring

  • Ensure correct wiring with no loose or false connections.

  • Each secondary wire must be fitted with a clearly and  accurately labeled wire marker to facilitate future troubleshooting.

Primary Lead Connections

  • Ensure contact surfaces of the terminal clamps are flat and  clean.

  • If oxidation is present, polish the surface with sandpaper. For  silver-plated surfaces, use the backside of the sandpaper to avoid      damaging the plating.

  • Apply a uniform layer of electrical compound grease after  cleaning, with a thickness of no less than 1 mm.

  • When inserting bolts, orient the bolt head downward and the nut  upward (to facilitate detection of loosening).

  • Tighten bolts diagonally in sequence to ensure even pressure  distribution.

SF6 Gas Piping Connections

  • Ensure all joints are tightly sealed. Use PTFE (Teflon) tape as  a secondary sealant on threaded connections if necessary.

Gas Charging Procedure

  • After connecting the charging equipment, slightly open the gas  cylinder valve to purge air from the charging hose for approximately 3  minutes, ensuring the hose is free of contaminants.

  • Wipe the circuit breaker’s gas inlet port with a lint-free  cloth dampened with anhydrous alcohol until completely clean and  dust-free.

  • Charge the gas slowly to prevent frost formation on the  cylinder or piping.

  • Fill to the rated pressure of 0.5 MPa.


3. Testing and Inspection

After installation, perform the following tests to verify work quality:

DC Resistance Test

  • With the circuit breaker in the closed position, perform the   test phase by phase (A, B, C).

  • Requirement: DC resistance of each phase must be less than 40      µΩ.

Mechanical Characteristic Test

The following tests and reference values are required (see Table 1):

Table 1. Reference Values for Mechanical Characteristics of LW25-126 Circuit Breaker

Test Item

Standard Value

Opening   Time

≤   30 ms

Closing   Time

≤   150 ms

Opening   Synchronization

≤   2 ms

Closing   Synchronization

≤   4 ms

Minimum   Voltage for Opening

≥   66 V and ≤ 143 V

Minimum   Voltage for Closing

≥   66 V and ≤ 143 V

Moisture (Micro Water) Test

  • Conduct the test at least 24 hours after gas charging.

  • Requirement: Moisture content in the arc extinguishing chamber  must not exceed 150 µL/L.


Give a tip and encourage the author!
Recommended
Top 5 Critical Process Controls for GIS Installation & Commissioning
Top 5 Critical Process Controls for GIS Installation & Commissioning
This paper briefly outlines the advantages and technical characteristics of GIS (Gas-Insulated Switchgear) equipment, and elaborates on several critical quality control points and process control measures during on-site installation. It emphasizes that on-site withstand voltage tests can only partially reflect the overall quality and installation workmanship of GIS equipment. Only by strengthening comprehensive quality control throughout the entire installation process—especially in key areas su
James
10/29/2025
7 Key Steps to Ensure Safe and Reliable Installation of Large Power Transformers
7 Key Steps to Ensure Safe and Reliable Installation of Large Power Transformers
1. Maintaining and Restoring the Factory Insulation ConditionWhen a transformer undergoes factory acceptance tests, its insulation condition is at its optimal state. Thereafter, the insulation condition tends to deteriorate, and the installation phase may be a critical period for sudden degradation. In extreme cases, the dielectric strength may drop to the point of failure, leading to coil burnout immediately upon energization. Under normal circumstances, poor installation quality leaves behind
Oliver Watts
10/29/2025
Complete Guide to Circuit Breaker Selection and Setting Calculation
Complete Guide to Circuit Breaker Selection and Setting Calculation
How to Select and Set Circuit Breakers1. Types of Circuit Breakers1.1 Air Circuit Breaker (ACB)Also known as a molded frame or universal circuit breaker, all components are mounted within an insulated metal frame. It is typically open-type, allowing easy replacement of contacts and parts, and can be equipped with various accessories. ACBs are commonly used as main power supply switches. Overcurrent trip units include electromagnetic, electronic, and intelligent types. They provide four-stage pro
Echo
10/28/2025
Hydraulic Leak & SF6 Gas Leakage in Circuit Breakers
Hydraulic Leak & SF6 Gas Leakage in Circuit Breakers
Leakage in Hydraulic Operating MechanismsFor hydraulic mechanisms, leakage can cause short-term frequent pump starting or excessively long re-pressurization time. Severe internal oil seepage in valves may lead to pressure loss failure. If hydraulic oil enters the nitrogen side of the accumulator cylinder, it can cause abnormal pressure rise, which affects the safe operation of SF6 circuit breakers.Apart from failures caused by damaged or abnormal pressure detection devices and pressure component
Felix Spark
10/25/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.