• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Transmission Tower Erection Methodology

Electrical4u
Field: Basic Electrical
0
China

What Is Transmission Tower Erection Methodology

There are four main methods of the erection of steel transmission towers which are described below:

  1. Build-up method or Piecemeal method.

  2. Section method.

  3. Ground assembly method.

  4. Helicopter method.

Build Up Method of Transmission Tower Erection

This method is most commonly used in India for the erection of 6.6 kV, 132 kV, 220 kV, and 400 kV transmission line towers due to the following advantages :

  1. Tower materials can be supplied to the site in a knocked down conditions which facilitates easier and cheaper transportation.

  2. It does not require any heavy machinery such as cranes etc.

  3. Tower erection activity can be done in any kind of terrain and mostly throughout the year.

  4. Availability of workmen at cheap rates.

This method consists of erecting the towers, member by member. The tower members are kept on the ground serially according to the erection sequence to avoid search or time loss. The erection progresses from the bottom upwards.

The four main corner leg members of the first section of the tower are first erected and guard off. Sometimes more than one contiguous leg section of each corner leg is bolted together at the ground and erected.

The cross braces of the first section which are already assembled on the ground are raised one by one as a unit and bolted to the already erected corner leg angles. First section of the lower thus built and horizontal struts (belt members) if any, are bolted in position. For assembling the second section of the tower, two gin poles are placed one each on the top of diagonally opposite corner legs.

These two poles are used, for raising parts of the second section. The leg members and braces of this section are then hoisted and assembled. The gin poles are then shifted to the corner leg members on the top of the second section to raise the parts of the third section of the lower in position for assembly. Gin poles are thus moved up as the tower grows.

This process is continued until the complete tower is erected. Cross-arm members are assembled on the ground and raised up and fixed to the main body of the tower. For heavier towers, a small boom is rigged on one of the tower legs for hoisting purposes. The members/sections are hoisted either manually or by winch machines operated from the ground.

For smaller base towers/vertical configuration towers one gin pole is used instead of two gin poles. In order to maintain speed and efficiency, a small assembly party goes ahead of the main erection gang and its purpose is to sort out the tower members, keeping the member’s incorrect position on the ground and assembling the panels on the ground which can be erected as a complete unit.

Section Method of Transmission Tower Erection

In the section method, major sections of the tower are assembled on the ground and the same are erected as units. Either a mobile crane or a gin pole is used. The gin pole used is approximately 10 m long and is held in place by means of guys by the side of the tower to be erected.

The two opposite sides of the tower section of the tower are assembled on the ground. Each assembled side is then lifted clear of the ground with the gin or derrick and is lowered into position on bolts to stubs or anchor bolts.

One side is h held in place with props while the other side is being erected. The two opposite sides are then laced together with cross members and diagonals; and the assembled section is lined up, made square to the line. After completing the first section, the gin pole is set on the top of the first section. The gin rests on a strut of the tower immediately below the leg joint. The gin pole then has to be properly guyed into position.

The first face of the second section is raised. To raise the second face of this section it is necessary to slide the foot of the gin on the strut of the opposite face of the tower. After the two opposite faces are raised, the lacing on the other two sides is bolted up. The last lift raises the top of the towers.

After the tower, the top is placed and all side lacing has been bolted up all the guyed are thrown off except one which is used to lower the gin pole. Sometimes whole one face of the tower is assembled on the ground, hoisted, and supported in position. The opposite face is similarly assembled and hoisted and then the bracing angles connecting these two faces are fitted.

Ground Assembly Method of Tower Erection

This method consists of assembling the tower on the ground and erecting it as a complete unit. The complete tower is assembled in a horizontal position on even ground. The tower is assembled along the direction of the line to allow the cross arms to be fitted. One slopping ground, however, elaborate packing of the low side is essential before assembly commences.

After the assembly is complete the tower is picked up from the ground with the help of a crane and carried to its location, and set on its foundation. For this method of erection, a level piece of ground close to footing is chosen from the tower assembly.

This method is not useful when the towers are large and heavy and the foundations are located in arable land where building and erecting complete towers would cause damage to large areas or in hilly terrain where the assembly of the complete tower on the sloping ground may not be possible and it may be difficult to get the crane into position to raise the complete tower.

In India, this method is not generally adopted because of the prohibitive cost of mobile crane, and the non-availability of good approach roads to tower locations.

Helicopter Method of Transmission Tower Erection

In the helicopter method, the transmission tower is erected in section. For example, the bottom section is first lifted on to the stubs and then the upper section is lifted and bolted to the first section and the process is repeated till the complete tower is erected.

Sometimes a completely assembled tower is raised with the help of a helicopter. Helicopters are also used for lifting completely assembled towers with guys from the marshaling yards where these are fabricated and then transported one by one to line locations. A helicopter hovers over the line location while the tower is securely guyed.

The ground crewmen connect and tighten the tower guys. As soon as the guy wires are adequately tensioned the helicopter disengages and files to the marshaling yard. This method is adopted where the approach is very difficult or to speed up the construction of the transmission line.

Tightening of Nuts and Punching of Threads and Tack Welding of Nuts of Transmission Towers

All nuts shall be tightened properly using correct sized spanners. Before tightening it is ensured that filter washers and plates are placed in relevant gaps between members, a bolt of proper size and length are inserted and one spring washer is inserted under each nut.

In the case of step bolts, the spring washer shall be placed under the outer nut. The tightening shall be carried on progressively from the top downwards, care being taken that all bolts at every level are tightened simultaneously. It may be better to employ four persons, each covering one leg and the face to his right.

The threads of bolts shall be projected outside the nuts by one to two threads and shall be punched at three positions on the top inner periphery of the nut and bolt to ensure that the nuts are not loosened in course of time. If during tightening a nut is found to be slipping or running over the bolt threads, the bolt together with the nut shall be changed outright.

Painting of Joints of Transmission Tower

For galvanized towers is coastal or highly polluted areas, the joints shall be painted with zinc paint on all contact surfaces during the course of erection.

Checking the Verticality of Erected Transmission Towers

The finally erected tower shall be truly vertical after erection and no straining is permitted to bring it in alignment. The tolerance limit for vertical shall be one in 360 of the tower height.

Statement: Respect the original, good articles worth sharing, if there is infringement please contact delete.

Give a tip and encourage the author!
Recommended
Ensuring Reliability: A Deep Dive into Transformer Maintenance
IntroductionElectric transformers are the backbone of modern power distribution systems, silently enabling the reliable delivery of electricity to homes, businesses, and industries. As these critical assets age and the demand for uninterrupted power grows, the importance of diligent transformer maintenance has never been greater. This essay explores the essential role of transformer maintenance, highlighting the value of proactive care, the impact of advanced diagnostic technologies, and the tra
Vziman
09/03/2025
How does a transformer work?
Transformer Operation PrincipleA transformer is an electrical device that operates on the principle of electromagnetic induction to transfer electrical energy from one circuit to another. It enables the adjustment of voltage levels within an alternating current (AC) system, either stepping up (increasing) or stepping down (decreasing) voltage while maintaining the same frequency.Working Principle:Basic ComponentsA transformer consists of two coils, known as windings—the "primary winding" connect
Rockwell
09/03/2025
What is the difference between a dielectric and an insulator?
Dielectrics and insulators are distinguished primarily by their applications. One of the main differences is that a dielectric can store electrical energy by becoming polarized in an electric field, whereas an insulator resists the flow of electrons to prevent current conduction. Other key differences between them are outlined in the comparison chart below.Definition of DielectricA dielectric material is a type of insulator that contains few or no free electrons. When subjected to an electric fi
Edwiin
08/30/2025
What losses occur during operation of the transformer? How to reduce losses?
Transformers experience various types of losses during operation, primarily categorized into two main types: copper losses and iron losses.Copper LossesCopper losses, also known as I²R losses, are caused by the electrical resistance of the transformer windings—typically made of copper. As current flows through the windings, energy is dissipated in the form of heat. These losses are proportional to the square of the load current (I²R), meaning they increase significantly with high
Rockwell
08/29/2025
Seed Inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.