Motor Protection Relay for High Voltage Induction Motor

Electrical4u
Field: Basic Electrical
0
China

What Is A Motor Protection Relay

Above 90% of motors used in an industry are induction motors, because they are cheap, robust and easy to maintain. For higher HP (>250HP) motors we prefer high voltage, because it will reduce operating current and the size of the motor.

Why We Require Protection of Motors?

To understand this we need to know the cost associated with the failure of motor, i.e.

  • Loss of production (Cost of production)

  • Replacement of motor (Replacement cost)

  • Cost of repair

  • Cost of man hours due to this emergency

The basic function of a protective relay is to identify the fault and isolate faulty part from the healthy part of the system. This will improve the reliability of power system.
For protection of motor, we have to identify the various causes of failure and to address the same. The various causes of failure are as below

  • Thermal stress on winding

  • Single phasing

  • Earth fault

  • Short circuit

  • Locked rotor

  • Number of hot starts

  • Bearing failure

Brief descriptions of the different failures are given below:

  • Thermal Stress on Winding –
    If a motor runs continuously more than its rated capacity then this will over heat the winding and insulation. Subsequently deteriorate the winding insulation resulting in failure of motor. If the 
    voltage is less than the designed value then also it will over heat the winding at rated load and failure of the motor can occur.

  • Single Phasing –
    Loss of one phase supplied to the motor (in case of 
    3-phase motor) leads to single phasing. If we start the motor on load, then the motor will fail due to imbalance.

  • Earth Fault –
    If any part of winding comes in contact with the ground then we can say the motor is earthed. If we start the motor then it will lead to failure of motor.

  • Short Circuit –
    If there is a contact between two phases of a three phase winding or between the turns of a phase, and then this will be termed as short circuit.

  • Locked Rotor –
    If the driven equipment is in jammed condition or the motor shaft is jammed, then this is known as locked rotor. If we start the motor then it will fail.

  • Number of Hot Start –
    Each motor is designed to withstand a certain number of hot starts. Consider a motor is in running condition, if we stop the motor and immediately start the same, then this is called as a hot start. Depending upon the thermal curve of a motor we have to give certain time to bring down the temperature of winding.

  • Bearing Failure –
    If bearing fails then rubbing of rotor on stator will occur, resulting physical damage of insulation and winding. The bearing failure can be avoided by monitoring the bearing temperature. Bearing temperature detector (BTD) is used for monitoring and tripping of motor in case of abnormality.

All motor protection relays operate on the basis of current taken by the motor. Motor protection relay is used for high voltage area having the following features

  • Thermal overload protection

  • Short circuit protection

  • Single phasing protection

  • Earth fault protection

  • Locked rotor protection

  • Number of start protection

For setting of the relay we require the CT ratio and full load current of the motor. The setting of different element is listed below

  • Thermal over Load Element –
    To set this element we have to identify the % of Full load current on which the motor is running continuously.

  • Short circuit Element –
    The range available for this element is 1 to 5 times of starting current. Time delay is also available. We normally set it at 2 times of starting current with a time delay of 0.1 second.

  • Single Phasing Element –
    This element will operate, if there is an unbalance in current of three phases. It is also called as unbalance protection. The element is set for 1/3rd of starting current. If it tripped during starting, then the parameter will changed to 1/2 of starting current.

  • Earth Fault Protection –
    This element measures the neutral current of star connected CT secondary. The range available for this element is 0.02 to 2 times of CT primary current. Time delay is also available. We normally set at 0.1 times of CT primary current with a time delay of 0.2 seconds. If tripped during starting of motor, then the time setting can be raised to 0.5 sec.

  • Locked rotor protection –
    The range available for this element is 1 to 5 times of full load current. Time delay is also available. We normally set at 2 times of FLC (Full Load Current). The time delay will be more than the starting time of the motor. “Starting time means the time require by the motor to reach its full speed.”

  • Number of hot start protection –
    Here we will provide the number of start allowed in specified time duration. By this we will limit the number of hot starts given to the motor.

The schematic diagram to connect a motor protection relay is as below

Modern digital motor protection relays are having some extra features, i.e. protection against no load running of a motor and thermal protection.
In case of no load running, the relay senses the motor current. If it is less than the specified value then it will trip the motor. We can also connect the temperature probe to the relay, which will monitor the bearing and winding temperature and trip the motor if it exceeds the specified value of temperature.

Statement: Respect the original, good articles worth sharing, if there is infringement please contact delete.

Give a tip and encourage the author!
Recommended
Transmission Line
In transmission lines, a "π" connection involves breaking the original line from Substation A to Substation B and inserting Substation C, forming a "π" configuration. After the "π" connection, the original single line is divided into two independent transmission lines. Following the "π" connection, Substations B and C may both be powered by Substation A (in this case, Substation C receives power via a feeder from Substation B's busbar, or possibly from another voltage point within Substation B);
Encyclopedia
09/04/2025
What are the principles of forced re-energization of transmission lines?
Principles of Forced Re-energization of Transmission LinesRegulations for Forced Re-energization of Transmission Lines Correctly select the forced re-energization end of the line. If necessary, change the connection configuration before forced re-energization, taking into account the reduction of short-circuit capacity and its impact on grid stability. There must be a transformer with its neutral point directly grounded on the busbar at the forced re-energization end. Pay attention to the impact
Edwiin
09/04/2025
Analysis of Accident Handling in Transmission Lines
Analysis of Transmission Line Fault HandlingAs a fundamental component of the power grid, transmission lines are widely distributed and numerous, often exposed to diverse geographical and climatic conditions, making them highly susceptible to faults. Common causes include overvoltage, pollution flashover, insulation damage, tree encroachment, and external damage. Line tripping is one of the most frequent faults in power plant and substation operations, with fault types including single-phase-to-
Leon
09/04/2025
The difference between transmission and distribution lines
Transmission lines and distribution lines are both used to carry electrical power from one location to another. However, they differ significantly in key aspects such as primary function, voltage levels, phase configuration, and conductor placement. These differences are essential for understanding their distinct roles in the power system.The Difference Between Transmission and Distribution Line is given below in the tabulated form.Electricity generation is a critical component of the power syst
Edwiin
09/04/2025
Related Products
  • IPXX Series Ingress Protection professional testing tool
  • KW-1 Series simulation rain - shower tester
Seed Inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.