• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Misali da kisan gari da tsawon shirin 35 kV GIS voltage transformer?

Felix Spark
Felix Spark
فیلڈ: Kashe da Kayan Aiki
China

1. Gariyar Gari
1.1 Tashar da Kungiyar Saita na Turanci 35kV GIS

An yi amfani da ZX2 gas-insulated double-bus switchgear a watan Maris 2011 kuma an yi aiki a watan Yuli 2012, tana da sauran bus voltage transformers (PTs) bi masu hukuma guda daga cikin kungiyar bus. An yi tasirin PTs bi masu hukuma guda a cikin babbanta 600 mm. An yanke PTs bi na turanci a cikin babbanta a kwanaki.

An haɗa PTs zuwa disconnectors a cikin chamber na bus na PT switchgear ta hanyar short cable plugs. An haɗa disconnectors zuwa three-phase bus ta hanyar moving contacts a cikin SF₆ fully-enclosed bus chamber. Tashar fully-enclosed bus yana rage muhimman nasarorin, kuma bus ba ta da sabbin babban bus protection. Ana koyar bus faults ta hanyar backup protection na power incoming switch.

1.2 Na'urar Aiki Idan Ma Duni Gariya

Idan ma duni gariya, an yi aiki a cikin power grid haka:

  • 220kV System: Qiaoshi Line da Huishi Line sun yi aiki a cikin parallel da bus tie switch closed.

  • Main Transformer Load: No.1 main transformer ya shiga 47 MW, kuma No.2 ya shiga 14 MW.

  • 35kV System: Unit A ta yi aiki a cikin double buses a split operation. Generator No.2, ya shiga 30.5 MW, an haɗa shi zuwa Bus II na Unit A ta hanyar Bus 1 na Unit E, hot oil interconnection line switchgears 361 da 367, kuma ta yi aiki a cikin parallel da No.2 main transformer.

1.3 Tsarin Gariya

  • Alamun Gariya

    • Daga lokacin 15:11:20.393 na ranar 19 ga Afrilu, protection device na switch 367 a Unit E (Bus Unit for Generators 1 and 2) ta fito PT disconnection alarms, kuma ana iya reset su daidai.

  • Gariyar Equipment

    • A lokacin 15:12:59, ana iya samun smoke da arcing a cikin PT cabinet na Bus 1 a Unit E. Zero-sequence overcurrent protection na switches 361 da 367 ta zama, kuma ana iya trip abubuwan switches.

  • Nasara na Gariya

    • Babban babbanta ta fito. Phase A PT ta shida daidai, kuma plug na Phase B ta zama fractured. Zafi na iyakoki ta shida.

    • Secondary wires na arrester cabinet na jirgin yanki ta shida. Chamber pressure da insulation tests na bus sun zama normal.

2. Tashar Muhimmanci
2.1 Kasuwanci da Kungiyar Amfani Da Defects

  • Tashar Design da Manufacturing Issues

    • Matsalolin insulation paint process wanda ke rage partial discharge.

    • Loose lamination of iron cores wanda ke rage eddy current heating.

    • Irregular coil winding wanda ke rage inter-turn short circuits.

  • Installation and Maintenance Defects

    • Poor welding of grounding screws wanda ke rage contact resistance.

    • Deformation of iron cores during transportation/installation.

    • Transverse stress from short cable plugs wanda ke rage epoxy cracking over time.

2.2 Abnormal Operating Conditions

  • Secondary Circuit Faults

    • Overloading in the secondary circuit due to excessive parallel loops, resulting in increased heat generation according to \(Q = I²rt\).

    • Secondary short circuits triggering primary current surges and overheating.

  • System Overvoltage

    • Ferroresonance caused by switching operations or arcing grounding, generating overvoltages up to 2.5 times the rated value.

    • Waveform distortion accelerating insulation aging.

  • Three-Phase Imbalance

    • High harmonic content (mainly odd harmonics) causing impedance imbalance.

    • Neutral point displacement current leading to overheating in the zero-sequence circuit.

2.3 Manufacturer's Disassembly Analysis

  • Fault Location

    • Epoxy cracking at the flange mounting hole of Phase A PT led to intermittent grounding.

    • Mechanical fracture of Phase B plug triggered phase-to-phase short circuit.

  • Stress Analysis

    • Non-flexible cable connections generated transverse stress concentrated at flange holes.

    • Fault progression: Intermittent grounding → Aluminum coating ablation → Fault reset → Final breakdown.

3. Retrofit Plan
3.1 Equipment Monitoring Optimization

  • Implement online partial discharge monitoring for GIS switchgears of the same model and establish baseline data.

  • Conduct periodic insulation resistance tests with a threshold of 200 MΩ.

3.2 Structural Design Improvement

  • Cabinet Expansion: Increase cabinet width from 600 mm to 800 mm to improve heat dissipation.

  • Connection Upgrade: Replace short cable plugs with direct connections to reduce stress.

  • Modular Design: Adopt pluggable PTs/arresters to minimize maintenance time.

3.3 Protection System Enhancement

  • Add dedicated circuit breakers for PT switchgears with overcurrent/overvoltage protection.

  • Install dedicated bus protection devices for rapid fault isolation.

  • Optimize zero-sequence circuit design to reduce resonance risk.

3.4 Operation and Maintenance Strategy Adjustment

  • Establish full lifecycle management records for equipment, documenting installation and maintenance data.

  • Perform quarterly SF₆ moisture content tests with a threshold ≤300 ppm.

  • Conduct annual PT volt-ampere characteristic tests for comparison with factory data.

4. Lessons Learned and Preventive Measures
4.1 Key Lessons

  • Design Flaw: Co-location of PTs increased fault propagation risk.

  • Maintenance Gap: Failure to detect cumulative stress damage.

  • Protection Deficiency: Reliance on backup protection delayed fault clearance.

4.2 Preventive Measures

  • Strengthen equipment manufacturing supervision, focusing on insulation processes and structural integrity.

  • Promote condition-based maintenance using vibration monitoring to assess stress levels.

  • Revise design specifications to mandate flexible connections between PTs and buses.

  • Conduct anti-accident drills to standardize emergency response procedures for PT faults.

4.3 Implementation Results

Post-retrofit data shows:

  • Partial discharge reduced from 80 pC to 15 pC.

  • Temperature rise under full load decreased by 12°C.

  • Fault response time shortened from 600 ms to 40 ms.

5. Conclusion

This accident revealed multiple hidden risks in GIS equipment design, installation, and maintenance. Through structural optimization, protection system upgrade, and management enhancement, a comprehensive risk prevention system has been established. Continuous monitoring of equipment performance will provide replicable retrofit experience for similar substations.

Ba da kyau kuma kara mai rubutu!
Tambayar Da Yawanci
Gidajin Gida da Ka'idojin 10kV RMU Da Dalilin Hallareshi
Gidajin Gida da Ka'idojin 10kV RMU Da Dalilin Hallareshi
Masu Gwaji-gwaji da Kudin Farkon Matafiya na 10kV (RMUs)Matafiya na 10kV (RMU) ita ce karamin tashar zangancewar kasa a cikin hanyoyi na gajimareta kasa, ya kunshi amfani da shi wajen kai tsari da kudin farko. A lokacin mulkin gwamnati, za su iya samun tasiri masu. Duk da cewa, wasu muhimman abubuwa da kayan aiki suna cika ta haka.I. Tasiri Mai Kirkiro Kirkiro na Tsakiyar Da Kuma Tashar Mai KirkiroIdan akwai kirkiro ko tashar mai kirkiro a cikin RMU, zai iya ba da aiki mai yawa ko kuma tabbatar
Echo
10/20/2025
Nau'o'i da Fasahar Kirkiya na Tsuron Kula da Kungiyar Gida
Nau'o'i da Fasahar Kirkiya na Tsuron Kula da Kungiyar Gida
Fuska mai Yawan Kirki na Kashi: Taurari da Tasirin DukkukaFuska mai yawan kirki na kashi suna cikin manyan abubuwa masu muhimmanci a cikin lamarin kashi. Suna hana kirkinta karkashin lokaci da dukku ya faru, wanda ke nuna babban tsohon kashi ko kudaden tsawo. Amma saboda ingantaccen aiki da wasu batutu, ana iya samun dukukawa a cikin fuska kamar haka da ke bukatar tasirin dukkukan da kammalan.I. Taurari na Fuska Mai Yawan Kirki Na Kashi1. Saboda Ingantaccen Aiki: Na farko: Ana sauya a cikin maka
Felix Spark
10/20/2025
10 Daɗi'uni na Tashin da Turanci da Amfani da Turanci!
10 Daɗi'uni na Tashin da Turanci da Amfani da Turanci!
10 Maimaita da Ma'aikata Masu Kirkiro da Kula! Ba a yi kirkiro masu kula da yawan lokaci—ba a yi shi a wurare ko kungiyar. Yawancin lokaci tana haɗa ciki tsirrai da zama na kayan abincin mafi girma, amma yana ba da hanyoyin gudanar da kananan gudanar. Ba a zaɓe kyauwa masu kula taƙamfi. Zan iya samun kyauwa masu kula ita ce. Idan kyauwa ta mai kadan, zan iya haɗa ciki masu kula da yake daɗe da zama na iya daɗe. Haɗa ciki da yawa 30% ba zai iya fi shi a wajen rike biyu. Idan kyauwa ta mai yawan,
James
10/20/2025
Kanan Da Kula Tandankin Maimaita na Turanci de Noma?
Kanan Da Kula Tandankin Maimaita na Turanci de Noma?
Dalilai na Aiki na Turbin Mai Yawan Ruwa Saka turbin da za a yi aiki, kuma buɗe mai cutar cin karamin tsakiyar turbin da za a yi aiki, kafin kafa faduwar kontrol, kuma haɗa alama ta "BA TAKI" a karamin cutar. Bude mai cutar cin tsakiyar turbin da za a yi aiki, saka kafin kafin tsakiya, kawo karamin tsakiyar turbin, kuma haɗa alama ta "BA TAKI" a karamin cutar. Don aiki na turbin mai yawan ruwa, faɗi kwanaki da kaya, kuma tafi shirin kaya, gajeru, da kwanaki. Tuntubi kaya, gajeru, da kwanaki don
Felix Spark
10/20/2025
Aika tambaya
Kwamfuta
Samun IEE Business Application
Yi amfani da IEE-Business app don samun abubuwan aikin, samun halayyin, haɗi da malamai, kuma kai tsauraran takaiddun kasoshin duka lokaci, duka wurin—dole bai karfin takamaltar hulɗin ku na alintakargida da kasuwanci.