• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


What are the principles of forced re-energization of transmission lines?

Edwiin
Edwiin
Field: Power switch
China

Principles of Forced Re-energization of Transmission Lines

Regulations for Forced Re-energization of Transmission Lines

  • Correctly select the forced re-energization end of the line. If necessary, change the connection configuration before forced re-energization, taking into account the reduction of short-circuit capacity and its impact on grid stability.

  • There must be a transformer with its neutral point directly grounded on the busbar at the forced re-energization end.

  • Pay attention to the impact of forced re-energization on the transient stability of adjacent lines. If necessary, first reduce the load on all lines and units within the dynamic stability range before performing forced re-energization.

  • When a line trips or fails to reclose, accompanied by obvious system oscillation, immediate forced re-energization should not be performed. The oscillation must be checked and eliminated before considering whether to perform forced re-energization.

  • The circuit breaker for forced re-energization and its auxiliary equipment must be in good condition, and protection must be complete and functional.

  • During forced re-energization, busbar differential protection should be selectively put into operation and have backup protection for the connection configuration, ensuring that a failure of the circuit breaker to trip will not result in a complete outage of both busbars. When only one busbar is in operation, forced re-energization of lines should be avoided as much as possible.

Principles of forced re-energization of transmission lines.jpg

The Following Cases Prohibit Forced Re-energization After a Line Trip

  • Standby lines in an unloaded charging state;

  • Lines under trial operation;

  • After a line trip, if the load has already been transferred to other lines via automatic backup power switching, and power supply is unaffected;

  • Cable lines;

  • Lines where live-line work is being performed;

  • Line-transformer group circuit breakers that trip and fail to reclose;

  • When operating personnel have already observed obvious fault phenomena;

  • Lines where the circuit breaker has defects or insufficient interrupting capacity;

  • Lines known to have serious defects (e.g., submerged by water, severely tilted towers, severely broken conductor strands, etc.).

In the Following Cases, Forced Re-energization Must Be Performed Only After Contacting and Obtaining Permission from Dispatch

  • Busbar fault, where no obvious fault point is found after inspection;

  • Ring network line fault trip;

  • One circuit of a double-circuit line trips due to fault;

  • Lines that may cause out-of-phase closing;

  • Transformer backup protection trip.

Give a tip and encourage the author!
Recommended
 Causes and Preventive Measures of Fire and Explosion in Oil Circuit Breakers
Causes and Preventive Measures of Fire and Explosion in Oil Circuit Breakers
Causes of Fire and Explosion in Oil Circuit Breakers When the oil level in an oil circuit breaker is too low, the oil layer covering the contacts becomes too thin. Under the effect of the electric arc, the oil decomposes and releases flammable gases. These gases accumulate in the space beneath the top cover, mixing with air to form an explosive mixture, which can ignite or explode under high temperature. If the oil level inside the tank is too high, the released gases have limited space to expan
Felix Spark
11/06/2025
THD Measurement Error Standards for Power Systems
THD Measurement Error Standards for Power Systems
Error Tolerance of Total Harmonic Distortion (THD): A Comprehensive Analysis Based on Application Scenarios, Equipment Accuracy, and Industry StandardsThe acceptable error range for Total Harmonic Distortion (THD) must be evaluated based on specific application contexts, measurement equipment accuracy, and applicable industry standards. Below is a detailed analysis of key performance indicators in power systems, industrial equipment, and general measurement applications.1. Harmonic Error Standar
Edwiin
11/03/2025
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
Ring main units (RMUs) are used in secondary power distribution, directly connecting to end-users such as residential communities, construction sites, commercial buildings, highways, etc.In a residential substation, the RMU introduces 12 kV medium voltage, which is then stepped down to 380 V low voltage through transformers. The low-voltage switchgear distributes electrical energy to various user units. For a 1250 kVA distribution transformer in a residential community, the medium-voltage ring m
James
11/03/2025
Why Monitoring Accuracy Matters in Power Quality Systems
Why Monitoring Accuracy Matters in Power Quality Systems
The Critical Role of Monitoring Accuracy in Power Quality Online DevicesThe measurement accuracy of online power quality monitoring devices is the core of the power system’s “perception capability,” directly determining the safety, economy, stability, and reliability of power supply to users. Inadequate accuracy leads to misjudgment, incorrect control, and flawed decision-making—potentially causing equipment damage, economic losses, or even grid failures. Conversely, high accuracy enables precis
Oliver Watts
10/30/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.