Why Cement Sealing Is Banned for GIS Wall Penetrations?

Echo
Echo
Field: Transformer Analysis
China

Indoor GIS equipment typically involves wall-penetrating installations, except in cases with cable in/out connections. In most cases, the main or branch bus duct extends from indoors through a wall to the outdoor side, where it connects to porcelain or composite bushings for overhead line connections. The gap between the wall opening and the GIS bus enclosure, however, is prone to water and air leakage and therefore usually requires sealing. This article discusses why cement-based sealing is not allowed.

The 2015 edition of China Southern Power Grid’s Anti-Accident Measures explicitly prohibits the use of cement to seal wall-penetrating sections of GIS bus ducts.

GIS.jpg

The primary reason for this prohibition is the risk of chemical reactions between alkaline components in cement and the aluminum alloy used in GIS enclosures. When wet (unhardened) cement or rainwater-soaked cement comes into contact with the aluminum surface, corrosion can occur, potentially leading to gas leakage. Note that the reaction only occurs when the cement is damp—once fully hardened, the risk is significantly reduced. However, this issue requires special attention during the construction phase.

When cement particles come into contact with water, hydration begins on the surface layer by layer. The main hydration products include: calcium silicate hydrate (C-S-H) gel, calcium ferrite hydrate gel, calcium hydroxide (Ca(OH)₂), calcium aluminate hydrate, and ettringite. Among these, alkaline substances such as calcium hydroxide and calcium aluminate hydrate can react with aluminum alloy, causing damage to the GIS enclosure.

image.png

Besides cement, other sealing materials like asbestos boards or waterproof sealants may also be used at wall-penetrating points. However, asbestos boards often contain cementitious components, and improperly selected sealants—especially alkaline types—can similarly corrode the aluminum alloy enclosure, risking gas leakage.

Although aluminum alloy is naturally corrosion-resistant in air, another possible corrosion mechanism exists: cement may first degrade the protective paint layer on the enclosure surface, since paint is less corrosion-resistant than aluminum. Once the coating is compromised, the underlying metal becomes vulnerable. In the construction industry, this is why a primer or putty layer is typically applied before painting over cement.

This explains the origin of the prohibition against using cement to seal wall-penetrating GIS bus ducts.

Give a tip and encourage the author!
Recommended
Maintenance and Repair Items for 10kV High-Voltage Switchgear
Maintenance and Repair Items for 10kV High-Voltage Switchgear
I. Routine Maintenance and Inspection(1) Visual Inspection of Switchgear Enclosure No deformation or physical damage to the enclosure. Protective paint coating shows no severe rust, peeling, or flaking. Cabinet is securely installed, clean on the surface, and free of foreign objects. Nameplates and identification labels are neatly affixed and not falling off.(2) Check of Switchgear Operating Parameters Instruments and meters indicate normal values (comparable to typical operating data, with no s
Edwiin
10/24/2025
What are the common issues in SF₆ gas circuit faults and circuit breaker failure-to-operate faults?
What are the common issues in SF₆ gas circuit faults and circuit breaker failure-to-operate faults?
This article categorizes faults into two main types: SF₆ gas circuit faults and circuit breaker failure-to-operate faults. Each is described below:1.SF₆ Gas Circuit Faults1.1 Fault Type: Low gas pressure, but density relay does not trigger alarm or lockout signalCause: Faulty density gauge (i.e., contact not closing)Inspection & Handling: Calibrate actual pressure using a standard gauge. If confirmed, replace the density gauge.1.2 Density Relay Triggers Alarm or Lockout Signal (but pressure
Felix Spark
10/24/2025
GIS Bolt Tightening Torque Standards by Material & Size
GIS Bolt Tightening Torque Standards by Material & Size
GIS (Gas-Insulated Metal-Enclosed Switchgear) contains numerous bolted and screwed connections, and the tightening torque varies depending on bolt material, size, and application. The recommended tightening torque values are listed below for reference:Table 1 Tightening Torque Values for Bolts of Different Materials and Sizes (N·m / kgf·cm) Thread Diameter (mm) Q235 (A3) Cast Insulator 45 Steel Chrome-Molybdenum Steel Stainless Steel M6 5.88/60 3.92/40 12.3/125 19.6/
Encyclopedia
10/24/2025
Why You Can't Remove Siemens GIS Bushing Cover for PD Testing
Why You Can't Remove Siemens GIS Bushing Cover for PD Testing
As the title suggests, when performing live partial discharge (PD) testing on Siemens GIS using the UHF method—specifically by accessing the signal through the metal flange of the bushing insulator—you must not directly remove the metal cover on the bushing insulator.Why?You won’t realize the danger until you try. Once removed, the GIS will leak SF₆ gas while energized! Enough talk—let’s go straight to the diagrams.As shown in Figure 1, the small aluminum cover inside the red box is typically th
James
10/24/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.