1. Pananaw sa Accident

Ang bag-ong gipangutana nga 110kV substation’s GIS miexplosa samtang gikomisyon dahil sa short-circuit sa PT secondary circuit. Bisag simple ra ang hinungdan, severe ang mga resulta, na nagpuyo sa pag-usab.

2. Proseso sa Accident

Sa adlaw sa power-transmission:

  • Ang upper-level power supply naka-charge sa 110kV GIS (isang combined appliance).

  • 20s human sa pag-close sa incoming switch ug unang live-impacting sa 110kV bus, mibuntog ang puti nga usok tali sa PT compartment ug control cabinet.

  • Sa loob sa sampung segundo, miexplosa ang bus PT’s GIS compartment. Nag-trip ang upper power; ang disc insulator sa PT compartment naburst, ngadto sa GIS room ang mga fragmento sa insulator ug SF₆ combustion by-products.

3. Pagsusi sa Hinungdan
3.1 On-site Investigation

Ang 110kV PT (Shanghai MWB, electromagnetic type) adunay:

  • 1 basic secondary winding: 100/√3 V (150VA, 0.2 class).

  • 1 auxiliary secondary winding: 100V (150VA, 3P class), wala gamiton batas sa disenyo (nag-uli sa control cabinet terminal block, walay external connection).

Pangunhing natuklasan:

  • Phase C: Severe PT secondary winding insulation burns; basic winding conductor charred. Auxiliary winding conductor insulation totally burned; insulation cylinder between auxiliary winding & iron core charred. Insulation resistance between basic & auxiliary windings = 0.

  • Phase B: Basic secondary winding outer insulation had burning marks; internal paint film intact. Auxiliary winding surface insulation showed overheating charring.

  • Phase A: Slight basic secondary winding surface insulation burn; other conductors/insulation intact.

Preliminary conclusion: PT secondary circuit short-circuit, likely in B/C phase auxiliary windings.

Further control cabinet inspection: B/C phase auxiliary windings were shorted inside. Design-intended connections (C-ncf to terminal 11, B-nbf to terminal 15) were misrouted (C-ncf to 12, shorting to 14-cf; B-nbf to 16, shorting to 18-bf).

3.2 Pagpuyo sa Accident

  • Short-circuit start: After primary system closure, B/C phase auxiliary windings (cf, ncf; bf, nbf) shorted → B/C voltage drop.

  • B phase short-circuit end: After 20s, B phase short-circuit disconnected (primary lead burned by arc). Short time caused only B auxiliary winding overheating.

  • C phase consequence: 43s short-circuit (per accident recording) overheated C phase secondary conductor → insulation melt/char. White smoke came from this.

  • Insulation failure: PT auxiliary winding insulation melt degraded SF₆ gas in the PT chamber → lower insulation level.

  • Discharges: Reduced insulation + close phase-to-ground distances → A/B/C phases discharged to GIS shell.

  • Explosion: Arc energy raised gas chamber pressure → PT disc insulator burst.

3.3 Human Error

During commissioning:

  • Technicians rechecked PT polarity/insulation.

  • For convenience, they removed the PT secondary circuit from the control cabinet terminal block.

  • Mistakenly shorted B/C phase auxiliary winding ends; failed to verify → B/C auxiliary windings shorted.

4. Preventive Measures
4.1 PT Secondary Circuit Safety

Short-circuits in PT secondary circuits damage components or burn PTs. Installed in a closed GIS chamber, PT faults cause explosions (risking injury, delaying repairs). Thus, GIS PT installation/wiring demands strict attention.

4.2 Secondary Circuit Protocols

“Electrical Safety Work Regulations” and “Relay Protection On-site Work Security Regulations” mandate secondary work safety tickets for disassembly/wiring. Using these (and integrating risk control) could have prevented wrong wiring amid workload/time pressures.

4.3 Pre-energization Testing

Strengthen pre-energization PT tests (standardized, documented). Enforce strict test execution to avoid errors from careless work.

4.4 Organizational & Protection Measures

Protect commissioned equipment (lock cabinets, use seals). Modify only post-approval; have supervised restoration.

4.5 Unused Circuit Removal

Remove unused secondary circuits (reduce error risks). Here, the unused auxiliary winding (routed to the control cabinet) caused the accident via miswiring.

4.6 PT Body Air Switch

Install secondary air switches in PT body wiring boxes (current setup in control cabinets can’t protect GIS-to-PT circuits). This isolates faults below the PT secondary outlet.By reconstructing the accident, analyzing causes, and proposing 6 preventive measures, a roadmap for GIS secondary circuit safety is established.

Maghatag og tip ug pagsalig sa author
Gipareserbado
10kV RMU Common Faults & Solutions Guide

Gidagway sa mga Karaniwang Sayop ug Solusyon alang sa 10kV RMU
10kV RMU Common Faults & Solutions Guide Gidagway sa mga Karaniwang Sayop ug Solusyon alang sa 10kV RMU
Mga Isyu sa Pag-apply ug mga Pamaagi sa Pag-handle para sa 10kV Ring Main Units (RMUs)Ang 10kV ring main unit (RMU) usa ka kasagaran nga pananglitan sa elektrikal nga distribusyon sa urban nga mga network sa kuryente, gamiton sa paghatag ug distribusyon sa medium-voltage nga kuryente. Sa aktwal nga operasyon, mahimong madungog ang uban pang mga isyu. Ania ang mga kasagaran nga problema ug ang naka-corresponding nga mga pamaagi sa pag-handle.I. Mga Electrical Faults Internal Short Circuit o Pobre
Echo
10/20/2025
Mga Tipo sa High-Voltage Circuit Breaker ug Guide sa Mga Pagsayop
Mga Tipo sa High-Voltage Circuit Breaker ug Guide sa Mga Pagsayop
High-Voltage Circuit Breakers: Classification and Fault DiagnosisAng mga high-voltage circuit breakers mao ang mga kritikal nga protective devices sa mga power systems. Sila nag-intererrupt sa current ngadto sa pag-occur og fault, nang maprevent ang pag-damage sa equipment gikan sa overloads o short circuits. Sa wala pa, tungod sa long-term operation ug uban pang factors, ang mga circuit breakers mahimong mag-develop og faults nga angay nga i-diagnose ug troubleshoot niadtong maayo nga panahon.I
Felix Spark
10/20/2025
10 Prohibitions para sa Pag-install ug Paggamit sa Transformer!
10 Prohibitions para sa Pag-install ug Paggamit sa Transformer!
10 Prohibitions for Transformer Installation and Operation! Dili ang pag-install sa transformer nang labi ka layo—ayaw ihatag kini sa mga remote nga bukid o wilderness. Ang labi ka dako nga distansya wala lang magwasto sa cables apan adunay mas daghan pa nga line losses, ug mahadlok usab ang pag-manage ug maintenance. Dili ang pagpili sa capacity sa transformer nang random. Importante nga ang tama nga capacity. Kon ang capacity mubo, ang transformer mahimong mag-overload ug madaling mapuslan—ang
James
10/20/2025
Paunsa ang mga Transformer nga walay Lanas sa Maayo nga Paraan?
Paunsa ang mga Transformer nga walay Lanas sa Maayo nga Paraan?
Ang mga Prosidyur sa Pagmamaintain sa Dry-Type Transformers Ibutang ang standby transformer sa operasyon, buksan ang circuit breaker sa low-voltage side sa transformer nga gi-maintain, tangtangon ang control power fuse, ug ihapad ang "DO NOT CLOSE" sign sa switch handle. Buksan ang high-voltage side circuit breaker sa transformer nga gi-maintain, isara ang grounding switch, fully discharge ang transformer, lock ang high-voltage cabinet, ug ihapad ang "DO NOT CLOSE" sign sa switch handle. Para sa
Felix Spark
10/20/2025
Inquiry
Pangutana
Pangutana sa IEE-Business Application
Pangita og mga equipment gamit ang IEE-Business app asa asa ug kailan man sugad og pagkuha og solusyon pagsulay sa mga eksperto ug pagpadayon sa industriya nga pakisayran suportahan ang imong proyekto sa kuryente ug negosyo