• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


An GIS Equipment Explosion Accident Caused by PT Secondary Wiring Errors

Felix Spark
Felix Spark
Field: Failure and maintenance
China

1. Accident Overview

A newly - built 110kV substation’s GIS exploded during commissioning due to a PT secondary circuit short - circuit. Though the cause was simple, consequences were severe, warranting reflection.

2. Accident Process

On the power - transmission day:

  • The upper - level power supply charged the 110kV GIS (a combined appliance).

  • 20s after closing the incoming switch and first live - impacting the 110kV bus, white smoke emerged between the PT compartment and control cabinet.

  • Within ten seconds, the bus PT’s GIS compartment exploded. The upper power tripped; the PT compartment’s disc insulator burst, filling the GIS room with insulator fragments and SF₆ combustion by - products.

3. Cause Analysis
3.1 On - site Investigation

The 110kV PT (Shanghai MWB, electromagnetic type) had:

  • 1 basic secondary winding: 100/√3 V (150VA, 0.2 class).

  • 1 auxiliary secondary winding: 100V (150VA, 3P class), unused per design (routed to the control cabinet terminal block, no external connection).

Key findings:

  • Phase C: Severe PT secondary winding insulation burns; basic winding conductor charred. Auxiliary winding conductor insulation totally burned; insulation cylinder between auxiliary winding & iron core charred. Insulation resistance between basic & auxiliary windings = 0.

  • Phase B: Basic secondary winding outer insulation had burning marks; internal paint film intact. Auxiliary winding surface insulation showed overheating charring.

  • Phase A: Slight basic secondary winding surface insulation burn; other conductors/insulation intact.

Preliminary conclusion: PT secondary circuit short - circuit, likely in B/C phase auxiliary windings.

Further control cabinet inspection: B/C phase auxiliary windings were shorted inside. Design - intended connections (C - ncf to terminal 11, B - nbf to terminal 15) were misrouted (C - ncf to 12, shorting to 14 - cf; B - nbf to 16, shorting to 18 - bf).

3.2 Accident Development

  • Short - circuit start: After primary system closure, B/C phase auxiliary windings (cf, ncf; bf, nbf) shorted → B/C voltage drop.

  • B phase short - circuit end: After 20s, B phase short - circuit disconnected (primary lead burned by arc). Short time caused only B auxiliary winding overheating.

  • C phase consequence: 43s short - circuit (per accident recording) overheated C phase secondary conductor → insulation melt/char. White smoke came from this.

  • Insulation failure: PT auxiliary winding insulation melt degraded SF₆ gas in the PT chamber → lower insulation level.

  • Discharges: Reduced insulation + close phase - to - ground distances → A/B/C phases discharged to GIS shell.

  • Explosion: Arc energy raised gas chamber pressure → PT disc insulator burst.

3.3 Human Error

During commissioning:

  • Technicians rechecked PT polarity/insulation.

  • For convenience, they removed the PT secondary circuit from the control cabinet terminal block.

  • Mistakenly shorted B/C phase auxiliary winding ends; failed to verify → B/C auxiliary windings shorted.

4. Preventive Measures
4.1 PT Secondary Circuit Safety

Short - circuits in PT secondary circuits damage components or burn PTs. Installed in a closed GIS chamber, PT faults cause explosions (risking injury, delaying repairs). Thus, GIS PT installation/wiring demands strict attention.

4.2 Secondary Circuit Protocols

“Electrical Safety Work Regulations” and “Relay Protection On - site Work Security Regulations” mandate secondary work safety tickets for disassembly/wiring. Using these (and integrating risk control) could have prevented wrong wiring amid workload/time pressures.

4.3 Pre - energization Testing

Strengthen pre - energization PT tests (standardized, documented). Enforce strict test execution to avoid errors from careless work.

4.4 Organizational & Protection Measures

Protect commissioned equipment (lock cabinets, use seals). Modify only post - approval; have supervised restoration.

4.5 Unused Circuit Removal

Remove unused secondary circuits (reduce error risks). Here, the unused auxiliary winding (routed to the control cabinet) caused the accident via miswiring.

4.6 PT Body Air Switch

Install secondary air switches in PT body wiring boxes (current setup in control cabinets can’t protect GIS - to - PT circuits). This isolates faults below the PT secondary outlet.By reconstructing the accident, analyzing causes, and proposing 6 preventive measures, a roadmap for GIS secondary circuit safety is established.

Give a tip and encourage the author!
Recommended
10kV RMU Common Faults & Solutions Guide
10kV RMU Common Faults & Solutions Guide
Application Issues and Handling Measures for 10kV Ring Main Units (RMUs)The 10kV ring main unit (RMU) is a common electrical distribution device in urban power distribution networks, primarily used for medium-voltage power supply and distribution. During actual operation, various issues may arise. Below are common problems and corresponding corrective measures.I. Electrical Faults Internal Short Circuit or Poor WiringA short circuit or loose connection inside the RMU can lead to abnormal operati
Echo
10/20/2025
High-Voltage Circuit Breaker Types & Fault Guide
High-Voltage Circuit Breaker Types & Fault Guide
High-Voltage Circuit Breakers: Classification and Fault DiagnosisHigh-voltage circuit breakers are critical protective devices in power systems. They rapidly interrupt current when a fault occurs, preventing damage to equipment from overloads or short circuits. However, due to long-term operation and other factors, circuit breakers may develop faults that require timely diagnosis and troubleshooting.I. Classification of High-Voltage Circuit Breakers1. By Installation Location: Indoor-type: Insta
Felix Spark
10/20/2025
10 Prohibitions for Transformer Installation and Operation!
10 Prohibitions for Transformer Installation and Operation!
10 Prohibitions for Transformer Installation and Operation! Never install the transformer too far away—avoid placing it in remote mountains or wilderness. Excessive distance not only wastes cables and increases line losses, but also makes management and maintenance difficult. Never choose transformer capacity arbitrarily. Selecting the right capacity is essential. If the capacity is too small, the transformer may be overloaded and easily damaged—overloading beyond 30% should not exceed two hours
James
10/20/2025
How to Maintain Dry-Type Transformers Safely?
How to Maintain Dry-Type Transformers Safely?
Maintenance Procedures for Dry-Type Transformers Put the standby transformer into operation, open the low-voltage side circuit breaker of the transformer to be maintained, remove the control power fuse, and hang a "DO NOT CLOSE" sign on the switch handle. Open the high-voltage side circuit breaker of the transformer under maintenance, close the grounding switch, fully discharge the transformer, lock the high-voltage cabinet, and hang a "DO NOT CLOSE" sign on the switch handle. For dry-type trans
Felix Spark
10/20/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.