An GIS Equipment Explosion Accident Caused by PT Secondary Wiring Errors

07/08/2025

1. Accident Overview
A newly - built 110kV substation’s GIS exploded during commissioning due to a PT secondary circuit short - circuit. Though the cause was simple, consequences were severe, warranting reflection.
2. Accident Process
On the power - transmission day:
  • The upper - level power supply charged the 110kV GIS (a combined appliance).
  • 20s after closing the incoming switch and first live - impacting the 110kV bus, white smoke emerged between the PT compartment and control cabinet.
  • Within ten seconds, the bus PT’s GIS compartment exploded. The upper power tripped; the PT compartment’s disc insulator burst, filling the GIS room with insulator fragments and SF₆ combustion by - products.
3. Cause Analysis
3.1 On - site Investigation
The 110kV PT (Shanghai MWB, electromagnetic type) had:
  • 1 basic secondary winding: 100/√3 V (150VA, 0.2 class).
  • 1 auxiliary secondary winding: 100V (150VA, 3P class), unused per design (routed to the control cabinet terminal block, no external connection).
Key findings:
  • Phase C: Severe PT secondary winding insulation burns; basic winding conductor charred. Auxiliary winding conductor insulation totally burned; insulation cylinder between auxiliary winding & iron core charred. Insulation resistance between basic & auxiliary windings = 0.
  • Phase B: Basic secondary winding outer insulation had burning marks; internal paint film intact. Auxiliary winding surface insulation showed overheating charring.
  • Phase A: Slight basic secondary winding surface insulation burn; other conductors/insulation intact.

Preliminary conclusion: PT secondary circuit short - circuit, likely in B/C phase auxiliary windings.
Further control cabinet inspection: B/C phase auxiliary windings were shorted inside. Design - intended connections (C - ncf to terminal 11, B - nbf to terminal 15) were misrouted (C - ncf to 12, shorting to 14 - cf; B - nbf to 16, shorting to 18 - bf).
3.2 Accident Development
  • Short - circuit start: After primary system closure, B/C phase auxiliary windings (cf, ncf; bf, nbf) shorted → B/C voltage drop.
  • B phase short - circuit end: After 20s, B phase short - circuit disconnected (primary lead burned by arc). Short time caused only B auxiliary winding overheating.
  • C phase consequence: 43s short - circuit (per accident recording) overheated C phase secondary conductor → insulation melt/char. White smoke came from this.
  • Insulation failure: PT auxiliary winding insulation melt degraded SF₆ gas in the PT chamber → lower insulation level.
  • Discharges: Reduced insulation + close phase - to - ground distances → A/B/C phases discharged to GIS shell.
  • Explosion: Arc energy raised gas chamber pressure → PT disc insulator burst.

3.3 Human Error
During commissioning:
  • Technicians rechecked PT polarity/insulation.
  • For convenience, they removed the PT secondary circuit from the control cabinet terminal block.
  • Mistakenly shorted B/C phase auxiliary winding ends; failed to verify → B/C auxiliary windings shorted.
4. Preventive Measures
4.1 PT Secondary Circuit Safety
Short - circuits in PT secondary circuits damage components or burn PTs. Installed in a closed GIS chamber, PT faults cause explosions (risking injury, delaying repairs). Thus, GIS PT installation/wiring demands strict attention.
4.2 Secondary Circuit Protocols
“Electrical Safety Work Regulations” and “Relay Protection On - site Work Security Regulations” mandate secondary work safety tickets for disassembly/wiring. Using these (and integrating risk control) could have prevented wrong wiring amid workload/time pressures.
4.3 Pre - energization Testing
Strengthen pre - energization PT tests (standardized, documented). Enforce strict test execution to avoid errors from careless work.
4.4 Organizational & Protection Measures
Protect commissioned equipment (lock cabinets, use seals). Modify only post - approval; have supervised restoration.
4.5 Unused Circuit Removal
Remove unused secondary circuits (reduce error risks). Here, the unused auxiliary winding (routed to the control cabinet) caused the accident via miswiring.
4.6 PT Body Air Switch
Install secondary air switches in PT body wiring boxes (current setup in control cabinets can’t protect GIS - to - PT circuits). This isolates faults below the PT secondary outlet.By reconstructing the accident, analyzing causes, and proposing 6 preventive measures, a roadmap for GIS secondary circuit safety is established.

Hey there! I'm an electrical engineer specializing in Failure and Maintenance. I've dedicated my career to ensuring the seamless operation of electrical systems. I excel at diagnosing complex electrical failures, from malfunctioning industrial motors to glitchy power distribution networks. Using state - of - the - art diagnostic tools and my in - depth knowledge, I pinpoint issues quickly. On this platform, I'm eager to share my insights, exchange ideas, and collaborate with fellow experts. Let's work together to enhance the reliability of electrical setups.

Transformer Detection, Testing, Maintenance and Servicing
Transformer Detection, Testing, Maintenance and Servicing
Transformer testing, inspection, and maintenance are essential tasks to ensure normal operation and extend the service life of transformers. Below are some recommended steps:Visual Inspection: Regularly inspect the transformer's exterior, including the enclosure, cooling system, and oil tank. Ensure the enclosure is intact, free from corrosion, damage, or leakage.Insulation Resistance Testing: Use an insulation resistance tester to check the transformer's insulation system. Verify that the insul
Vziman
08/29/2025
What are the Common Operation Faults of Indoor Load Switches?
What are the Common Operation Faults of Indoor Load Switches?
Common operational faults of indoor load switches primarily concentrate on three core aspects: mechanical operation, electrical performance, insulation, and arc extinguishing. These issues can be broadly categorized as follows and are often related to component aging, environmental influences, or improper operation.1.Mechanical Faults The most typical issue is abnormal operation during opening and closing. This includes excessive resistance, jamming, or even refusal to operate when manually turn
08/27/2025
What should be done if the fuse element on the high-voltage side of the transformer melts?
What should be done if the fuse element on the high-voltage side of the transformer melts?
If the fuse element on the high-voltage side of the transformer blows or the circuit trips, the first step is to determine whether one phase, two phases, or all three phases are interrupted. This can be determined according to the fault symptoms as shown in the following table:When a fuse element blows, first check whether the high-voltage side fuse or the lightning arrester gap has short-circuited to ground. If no abnormalities are found during external inspection, it can be concluded that an i
08/26/2025
Usage and Maintenance of Fuses
Usage and Maintenance of Fuses
Use and MaintenanceIn low-voltage power distribution systems, fuses are protective electrical devices. Widely used for power grid and electrical equipment protection, fuses automatically cut off circuits when short circuits or overloads occur in the grid or equipment, preventing damage to electrical devices and preventing accidents from spreading.A fuse consists of an insulating base (or support), contacts, and a fuse element. The fuse element is the primary working component, acting like a spec
08/26/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!