• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Why You Can't Remove Siemens GIS Bushing Cover for PD Testing

James
Field: Electrical Operations
China

As the title suggests, when performing live partial discharge (PD) testing on Siemens GIS using the UHF method—specifically by accessing the signal through the metal flange of the bushing insulator—you must not directly remove the metal cover on the bushing insulator.

Why?

You won’t realize the danger until you try. Once removed, the GIS will leak SF₆ gas while energized! Enough talk—let’s go straight to the diagrams.

GIS.jpg

As shown in Figure 1, the small aluminum cover inside the red box is typically the one users intend to remove. Removing it allows electromagnetic waves from partial discharge to escape, enabling detection with offline PD equipment. This method is commonly used on many GIS brands. But why does removing it on Siemens equipment cause gas leakage?

Siemens bushing insulators are designed with two sealing rings. As labeled in Figure 2:

GIS.jpg

  • No. 01: The first seal, located on the epoxy resin casting of the bushing insulator.

  • No. 02: The second seal, located on the aluminum alloy metal flange.

The small aluminum cover you intend to remove is mounted on this metal flange. If these two seals were independent and not interconnected, removing the small cover (Figure 1) would pose no risk—no gas leakage would occur.

However, in Siemens design, there is a small notch in the lower-left area of Figure 2 that connects the gas chambers of the two sealing rings. For a clearer view, see the enlarged Figure 3.

GIS.jpg

Due to this small notch (Figure 3), the GIS gas sealing relies not only on the second seal (No. 02) on the metal flange but also on the small aluminum cover itself. Underneath that small cover is high-pressure SF₆ gas—remove it, and you’ll get a shocking surprise.

GIS.jpg

In contrast, for single-phase bushing insulators like the one shown in Figure 4, the two seals are not interconnected. The internal high-pressure SF₆ gas is primarily sealed by the first seal (No. 01) on the epoxy bushing. Therefore, removing the small aluminum cover as shown in Figure 5 is safe—no gas leakage will occur.

GIS.jpg

Conclusion:
Before removing any small cover on a bushing insulator for live (offline-type) partial discharge testing on GIS from any manufacturer, always consult the manufacturer to confirm whether the cover can be safely removed—especially for Siemens equipment, where improper removal can lead to dangerous SF₆ gas leakage under live conditions.

Give a tip and encourage the author!

Recommended

Classification of Equipment Defects for Relay Protection and Safety Automatic Devices in Substations
In daily operations, various equipment defects are inevitably encountered. Whether maintenance personnel, operation and maintenance staff, or specialized management personnel, all must understand the defect classification system and adopt appropriate measures according to different situations.According to Q/GDW 11024-2013 "Operation and Management Guide for Relay Protection and Safety Automatic Devices in Smart Substations," equipment defects are classified into three levels based on severity an
12/15/2025
Under What Conditions Will the Line Circuit Breaker Auto-Reclosing Signal Be Locked Out?
The line circuit breaker auto-reclosing signal will be locked out if any of the following conditions occur:(1) Low SF6 gas pressure in circuit breaker chamber at 0.5MPa(2) Insufficient energy storage in circuit breaker operating mechanism or low oil pressure at 30MPa(3) Busbar protection operation(4) Circuit breaker failure protection operation(5) Line distance protection zone II or zone III operation(6) Short lead protection operation of circuit breaker(7) Presence of remote tripping signal(8)
12/15/2025
Application of Auto-Reclosing Residual Current Protective Devices in Lightning Protection for Communication Power Supplies
1. Power Interruption Problems Caused by RCD False Tripping During Lightning StrikesA typical communication power supply circuit is shown in Figure 1. A residual current device (RCD) is installed at the power supply input terminal. The RCD primarily provides protection against electrical equipment leakage currents to ensure personal safety, while surge protective devices (SPDs) are installed on power supply branches to protect against lightning intrusions. When lightning strikes occur, the senso
12/15/2025
Reclosing Charge Time: Why Does Reclosing Require Charging? What Effects Does Charging Time Have?
1. Function and Significance of Reclosing ChargingReclosing is a protective measure in power systems. After faults such as short circuits or circuit overloads occur, the system isolates the faulty circuit and then restores normal operation through reclosing. The function of reclosing is to ensure continuous operation of the power system, improving its reliability and safety.Before performing reclosing, the circuit breaker must be charged. For high-voltage circuit breakers, the charging time is g
12/15/2025
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.