What is Transmission Tower Foundation?


Transmission Tower Foundation Definition


A transmission tower foundation is defined as the base that supports the tower and transfers loads to the ground.

 

583d30402f464d0fe559cf6286f031ed.jpeg


Types of Loads


The foundation of towers are normally subjected to three types of forces. These are:

 


  • The compression or downward thrust.



  • The tension or uplift.



  • The lateral forces of side thrusts in both transverse and longitudinal directions.



  • The magnitude or limit loads for foundations should be taken 10% higher than these for the corresponding towers.

 


The base slab of the foundation should be designed to handle extra forces caused by uneven load distribution.

 


The weight of concrete both above and below ground level, along with any embedded steel, should be considered to add to the down-thrust.

 


6546f68d06f1ce1b5e1e628b18ceeb1c.jpeg

 


Soil Parameters


Soil parameters For designing the foundations, following parameters are required.

 


  • Limit bearing capacity of soil.

  • Density of soil.

  • Angle of earth frustum.

 


The above values are available from soil test report.

 


 

Stability Analysis


Besides strength design, stability analysis must be conducted to prevent failures like overturning, uprooting, sliding, and tilting. Soil resistance is key to counteracting the loads on the foundation.

 


Resistance Against Uplift


The uplift loads shall be assumed to be resisted by the weight of earth in an inverted frustum of a pyramid of earth whose sides make an angle equal to the angle of report of the earth with the vertical in average soil. The volume of earth computation shall be as per enclosed drawing (Fig.3) The weight of concrete embedded in earth and that above the ground level shall also be considered for resisting the uplift. In case where the frustum of earth pyramid of two adjoining legs overlaps each other, the earth frustum shall be assumed truncated by a vertical plane passing through the center line of the tower base. Over load factor (OLF) of 10% (Ten percent) shall be considered over the design load i.e. OLF = 1.10 for suspension tower and 1.15 for angle including dead end and anchor tower. However, for special tower OLF shall be 1.20.

 


Resistance Against Down Thrust of Transmission Tower Foundation


The following load combinations shall be resisted by the bearing strength of the soil:

 


  • The down thrust loads combined with an additional weight of concrete above earth are assumed to be acting on the total area of the bottom of the footing.The moment due to side thrust forces at the bottom of the footing.


  • The structural design of the base slab shall be developed for the above load combination. In case of toe (τ) pressure calculation due to above load combination allowable bearing pressure to be increased by 25%.

 


Resistance Against Side Thrust of Transmission Tower Foundation


The chimney shall be designed as per limit state method for the combined action of axial forces, tension and compression and the associated maximum bending moment. In these calculations, the tensile strength of concrete shall be ignored.

 


Resistance Against Uprooting of Stub of Transmission Tower Foundation


OLF of 10% (Ten percent) shall be considered i.e. OLF = 1.10 for normal suspension towers and 1.15 for angle tower including Dead end/anchor tower. For special towers OLF shall be 1.20.

  


Give a tip and encourage the author!

Recommended

Faults and Handling of Single-phase Grounding in 10kV Distribution Lines
Characteristics and Detection Devices for Single-Phase Ground Faults1. Characteristics of Single-Phase Ground FaultsCentral Alarm Signals:The warning bell rings, and the indicator lamp labeled “Ground Fault on [X] kV Bus Section [Y]” illuminates. In systems with a Petersen coil (arc suppression coil) grounding the neutral point, the “Petersen Coil Operated” indicator also lights up.Insulation Monitoring Voltmeter Indications:The voltage of the faulted phase decreases (in
01/30/2026
Classification of Equipment Defects for Relay Protection and Safety Automatic Devices in Substations
In daily operations, various equipment defects are inevitably encountered. Whether maintenance personnel, operation and maintenance staff, or specialized management personnel, all must understand the defect classification system and adopt appropriate measures according to different situations.According to Q/GDW 11024-2013 "Operation and Management Guide for Relay Protection and Safety Automatic Devices in Smart Substations," equipment defects are classified into three levels based on severity an
12/15/2025
Under What Conditions Will the Line Circuit Breaker Auto-Reclosing Signal Be Locked Out?
The line circuit breaker auto-reclosing signal will be locked out if any of the following conditions occur:(1) Low SF6 gas pressure in circuit breaker chamber at 0.5MPa(2) Insufficient energy storage in circuit breaker operating mechanism or low oil pressure at 30MPa(3) Busbar protection operation(4) Circuit breaker failure protection operation(5) Line distance protection zone II or zone III operation(6) Short lead protection operation of circuit breaker(7) Presence of remote tripping signal(8)
12/15/2025
Application of Auto-Reclosing Residual Current Protective Devices in Lightning Protection for Communication Power Supplies
1. Power Interruption Problems Caused by RCD False Tripping During Lightning StrikesA typical communication power supply circuit is shown in Figure 1. A residual current device (RCD) is installed at the power supply input terminal. The RCD primarily provides protection against electrical equipment leakage currents to ensure personal safety, while surge protective devices (SPDs) are installed on power supply branches to protect against lightning intrusions. When lightning strikes occur, the senso
12/15/2025
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.