Temperature Rise Test of Transformer

Encyclopedia
Encyclopedia
Field: Encyclopedia
0
China


Temperature Rise Test Definition


A temperature rise test of a transformer checks if the temperature increase of its winding and oil meets specified limits.


Temperature Rise Test for Top Oil of Transformer


  • First, the LV winding of the transformer is short-circuited.



  • Then one thermometer is placed in a pocket in the transformer top cover. Other two thermometers are placed at the inlet and outlet of the cooler bank respectively.



  • The voltage of such value is applied to the HV winding that power input is equal to no load losses plus load losses corrected to a reference temperature of 75oC.



  • The total losses are measured by three wattmeters method.



  • During the test, hourly readings of top oil temperature are taken from the thermometer already placed in the pocket of the top cover.



  • Hourly readings of the thermometers placed at inlet and outlet of the cooler bank are also noted to calculate the mean temperature of the oil.



  • Ambient temperature is measured by means of a thermometer placed around the transformer at three or four points situated at a distance of 1 to 2 meter from and half-way up the cooling surface of the transformer.



  • Continue the temperature rise test for top oil until the temperature increase is less than 3°C in one hour. This steady value is the final temperature rise of the transformer oil.

 

cf19ff764b18119ef5d392ae77c51857.jpeg

 

  • There is another method of determination of oil temperature. Here the test is allowed to be continued until the top oil temperature rise does not vary more than 1oC per hour for four consecutive hours. The loweest reading during this time is taken as the final value for the temperature rise of the oil.

 

9a49deb29480f10339b6c515e8c52a66.jpeg

 

During the top oil temperature rise test, we short-circuit the LV winding and apply voltage to the HV winding. The supply voltage needed is much less than the rated voltage because core losses depend on voltage. Since core losses are minimal, we compensate by increasing the current to create additional copper loss. This ensures the actual temperature rise in the transformer oil.

 

Temperature rise limits of transformer when it is oil immersed, given in the table below

 

80fa8554a19da5777113318b9d716e34.jpeg

 

NB: These temperature rises limits mentioned in the above table are the temperature rise above the temperature of cooling medium. That means these are the difference between winding or oil temperature and temperature of cooling air or water.


Winding Temperature Rise Test on Transformer


  • After completion of temperature rise test for top oil of transformer the current is reduced to its rated value for transformer and is maintained for one hour.



  • After one hour the supply is switch off and short circuit and supply connection to the HV side and short circuit connection to the LV side are opened.



  • But, the fans and pumps are kept running (if any).

 

879da59e5ec4001618ed29d3b4301fa2.jpeg

 

  • Then resistance of the windings are measured quickly.



  • But there is always a minimum 3 to 4 minutes time gap between first measurement of resistance and the instant of switching off the transformer, which can not be avoided.



  • Then the resistances are measured at the same 3 to 4 minutes time intervals over a period of 15 minutes.



  • Graph of hot resistance versus time is plotted, from which winding resistance (R2) at the instant of shut down can be extrapolated.


  • From this value, θ2, the winding temperature at the instant of shut down can be determined by the formula given below


7348f0ab87de5cbc345ed8dcdad54fb9.jpeg

Where, R 1 is the cold resistance of the winding at temperature t1.For determining winding temperature rise we have to apply the above discussed indirect method. 


That means hot winding resistance is measured and determined first and then from that value we have to calculate the winding temperature rise, by applying resistance temperature relation formula. This is because unlike oil the winding of transformer is not accessible for external temperature measurement.

Give a tip and encourage the author!
Recommended
What Are Combined Transformer Standards? Key Specs & Tests
What Are Combined Transformer Standards? Key Specs & Tests
Combined Instrument Transformers: Technical Requirements and Testing Standards Explained with DataA combined instrument transformer integrates a voltage transformer (VT) and a current transformer (CT) into a single unit. Its design and performance are governed by comprehensive standards covering technical specifications, testing procedures, and operational reliability.1. Technical RequirementsRated Voltage:The primary rated voltages include 3kV, 6kV, 10kV, and 35kV, among others. The secondary v
Edwiin
10/23/2025
How to Choose & Maintain Electric Motors: 6 Key Steps
How to Choose & Maintain Electric Motors: 6 Key Steps
"Selecting a High-Quality Motor" – Remember the Six Key Steps Inspect (Look): Check the motor’s appearanceThe motor’s surface should have a smooth, even paint finish. The nameplate must be properly installed with complete and clear markings, including: model number, serial number, rated power, rated current, rated voltage, allowable temperature rise, connection method, speed, noise level, frequency, protection rating, weight, standard code, duty type, insulation class, manufacturing date, and ma
Felix Spark
10/21/2025
 What Is the Working Principle of a Power Plant Boiler?
What Is the Working Principle of a Power Plant Boiler?
The working principle of a power plant boiler is to utilize the thermal energy released from fuel combustion to heat feedwater, producing a sufficient quantity of superheated steam that meets specified parameters and quality requirements. The amount of steam produced is known as the boiler's evaporation capacity, typically measured in tons per hour (t/h). Steam parameters primarily refer to pressure and temperature, expressed in megapascals (MPa) and degrees Celsius (°C), respectively. Steam qua
Edwiin
10/10/2025
What is the principle of live-line washing for substations?
What is the principle of live-line washing for substations?
Why Do Electrical Equipment Need a "Bath"?Due to atmospheric pollution, contaminants accumulate on insulating porcelain insulators and posts. During rain, this can lead to pollution flashover, which in severe cases may cause insulation breakdown, resulting in short circuits or grounding faults. Therefore, the insulating parts of substation equipment must be periodically washed with water to prevent flashover and avoid insulation degradation that could lead to equipment failure.Which Equipment Is
Encyclopedia
10/10/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.