Temperature Rise Test of Transformer

09/19/2024

Temperature Rise Test Definition


A temperature rise test of a transformer checks if the temperature increase of its winding and oil meets specified limits.


Temperature Rise Test for Top Oil of Transformer


  • First, the LV winding of the transformer is short-circuited.


  • Then one thermometer is placed in a pocket in the transformer top cover. Other two thermometers are placed at the inlet and outlet of the cooler bank respectively.


  • The voltage of such value is applied to the HV winding that power input is equal to no load losses plus load losses corrected to a reference temperature of 75oC.


  • The total losses are measured by three wattmeters method.


  • During the test, hourly readings of top oil temperature are taken from the thermometer already placed in the pocket of the top cover.


  • Hourly readings of the thermometers placed at inlet and outlet of the cooler bank are also noted to calculate the mean temperature of the oil.


  • Ambient temperature is measured by means of a thermometer placed around the transformer at three or four points situated at a distance of 1 to 2 meter from and half-way up the cooling surface of the transformer.


  • Continue the temperature rise test for top oil until the temperature increase is less than 3°C in one hour. This steady value is the final temperature rise of the transformer oil.

 

cf19ff764b18119ef5d392ae77c51857.jpeg

 

  • There is another method of determination of oil temperature. Here the test is allowed to be continued until the top oil temperature rise does not vary more than 1oC per hour for four consecutive hours. The loweest reading during this time is taken as the final value for the temperature rise of the oil.

 

9a49deb29480f10339b6c515e8c52a66.jpeg

 

During the top oil temperature rise test, we short-circuit the LV winding and apply voltage to the HV winding. The supply voltage needed is much less than the rated voltage because core losses depend on voltage. Since core losses are minimal, we compensate by increasing the current to create additional copper loss. This ensures the actual temperature rise in the transformer oil.

 

Temperature rise limits of transformer when it is oil immersed, given in the table below

 

80fa8554a19da5777113318b9d716e34.jpeg

 

NB: These temperature rises limits mentioned in the above table are the temperature rise above the temperature of cooling medium. That means these are the difference between winding or oil temperature and temperature of cooling air or water.


Winding Temperature Rise Test on Transformer


  • After completion of temperature rise test for top oil of transformer the current is reduced to its rated value for transformer and is maintained for one hour.


  • After one hour the supply is switch off and short circuit and supply connection to the HV side and short circuit connection to the LV side are opened.


  • But, the fans and pumps are kept running (if any).

 

879da59e5ec4001618ed29d3b4301fa2.jpeg

 

  • Then resistance of the windings are measured quickly.


  • But there is always a minimum 3 to 4 minutes time gap between first measurement of resistance and the instant of switching off the transformer, which can not be avoided.


  • Then the resistances are measured at the same 3 to 4 minutes time intervals over a period of 15 minutes.


  • Graph of hot resistance versus time is plotted, from which winding resistance (R2) at the instant of shut down can be extrapolated.


  • From this value, θ2, the winding temperature at the instant of shut down can be determined by the formula given below


7348f0ab87de5cbc345ed8dcdad54fb9.jpeg

Where, R 1 is the cold resistance of the winding at temperature t1.For determining winding temperature rise we have to apply the above discussed indirect method. 


That means hot winding resistance is measured and determined first and then from that value we have to calculate the winding temperature rise, by applying resistance temperature relation formula. This is because unlike oil the winding of transformer is not accessible for external temperature measurement.

The Electricity Encyclopedia is dedicated to accelerating the dissemination and application of electricity knowledge and adding impetus to the development and innovation of the electricity industry.

Fault Analysis and Treatment of Oil-Immersed Transformers
Fault Analysis and Treatment of Oil-Immersed Transformers
Oil Leakage at Welded JointsOil leakage at welded joints primarily stems from poor welding quality, such as incomplete or detached welds, and defects like pinholes and gas pores. Although oil-immersed transformers are initially coated with solder and paint during manufacturing, potentially masking these issues temporarily, the defects tend to surface during operation. Additionally, electromagnetic vibration can cause weld cracks, leading to oil leakage.To resolve such leaks, the first critical s
08/29/2025
Transformer Connection Sections
Transformer Connection Sections
Transformer Connection DesignationsThe transformer connection designation indicates the winding connection method and the phase relationship between the line voltages of the primary and secondary windings. It consists of two parts: letters and a number. The letters on the left denote the connection configurations of the high-voltage and low-voltage windings, while the number on the right is an integer from 0 to 11.This number represents the phase shift of the low-voltage winding's line voltage r
08/15/2025
Functions of power transformers
Functions of power transformers
The power transformer is a key component in power plants and substations. Its functions are diverse: it can step up voltage to transmit electrical energy over long distances to load centers, as well as step down voltage to various required levels to meet different power demands. In short, both voltage step-up and step-down processes are accomplished through transformers.In power system transmission, voltage and power losses are inevitable. When transmitting a constant amount of power, voltage dr
08/08/2025
Why Should a Transformer Core be Grounded?
Why Should a Transformer Core be Grounded?
During transformer operation, the core and the metallic structures and components that secure the core and windings are exposed to a strong electric field, inducing a high potential relative to ground. If the core is left ungrounded, a potential difference can develop between the core and grounded parts such as clamps and the tank, leading to intermittent discharges. Additionally, the magnetic field surrounding the windings induces varying electromotive forces (EMF) in different metallic compone
08/07/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!