Avoid H59 Transformer Failure with Proper Inspection & Care

Noah
Field: Design & Maintenance
Australia

Measures to Prevent H59 Oil Immersed Power Distribution Transformer from Burning Out

In power systems, H59 Oil Immersed Power Distribution Transformer play an extremely critical role. Once burned out, they can cause widespread power outages, directly or indirectly affecting the production and daily lives of a large number of electricity users. Based on the analysis of multiple transformer burnout incidents, the author believes that a considerable number of such failures could have been avoided or eliminated at an early stage by implementing the following preventive measures.

1.Pre-Commissioning Inspection of H59 Oil Immersed Power Distribution Transformer

To ensure that the H59 Oil Immersed Power Distribution Transformer is ready for operation and to prevent burnout, on-site inspections must be conducted before commissioning. The main inspection items include:

  • Check whether the oil level gauge on the conservator tank is intact and whether the oil level is appropriate. If the oil level is too high, the oil may expand due to temperature rise after the transformer is energized under load and possibly overflow from the breather connection pipe at the top of the conservator. If the oil level is too low, it may drop below visible levels during light-load winter operation or short-term shutdowns, reducing the transformer’s insulation and cooling performance and affecting its operation.

  • Inspect whether covers, bushings, oil level gauges, drain valves, etc., are well sealed and free of oil leakage. Otherwise, more severe leakage may occur under thermal conditions once the transformer is loaded.

  • Check whether the explosion-proof diaphragm of the pressure relief device (explosion vent) is intact.

  • Inspect bushings for damage, cracks, or signs of discharge.

  • Verify whether the desiccant (silica gel) inside the breather (silica gel canister) has become ineffective.

  • Confirm that the transformer tank grounding is firm and reliable.

  • Check whether the primary and secondary bushings and their connections to conductors are secure and whether phase color markings are correct.

  • Verify that the nameplate data matches the required transformer specifications, including voltage ratings on all sides, winding connection group, rated capacity, and tap changer position.

  • Measure insulation resistance using a 1,000–2,500 MΩ megohmmeter to test the insulation resistance of both primary and secondary windings to ground and between windings. Record the ambient temperature during measurement. Although there is no rigid standard for acceptable insulation resistance values, the measured values should be compared with historical or factory data and should not fall below 70% of the original value.

  • Measure the DC resistance of the transformer windings together with bushings. For distribution transformers, the difference between phase DC resistances should be less than 4% of the average value, and the difference between line-to-line DC resistances should be less than 2% of the average value.

  • Check whether fuse selection is appropriate. The primary-side fuse should be rated at 1.5–2 times the transformer’s rated current, while the secondary-side fuse should typically match the secondary rated current.

If all the above inspections pass, the transformer should first be energized without load (“cold energization”). During this test, check for abnormal electromagnetic noise and measure whether the secondary voltages are balanced. Balanced voltages indicate normal turns ratio and absence of inter-turn short circuits, confirming the transformer is ready for normal loaded operation.

H59 H61 13.2kV 13.8kV 15kV 33kV Oil Immersed Power Distribution Transformer Manufacturer.jpg

2. Operational Precautions for H59 Oil Immersed Power Distribution Transformer

  • During operation, regularly monitor whether the three-phase voltages are balanced. If significant imbalance is detected, take corrective actions immediately. Also, routinely inspect oil level and oil color, and check the tank for oil leaks. Address any defects promptly to prevent tap changers or windings from burning out due to moisture ingress.

  • Regularly clean dirt and contaminants from the transformer surface. Inspect bushings for flashover or discharge, verify good grounding, and check for broken, poorly soldered, or fractured grounding conductors. Periodically measure ground resistance—ensuring it does not exceed 4 Ω for transformers ≥100 kVA or 10 Ω for transformers <100 kVA—or implement anti-pollution measures such as installing pollution-resistant bushing caps.

  • When connecting or disconnecting transformer leads, strictly follow inspection and installation procedures to avoid internal conductor breakage. Select appropriate connection methods for secondary conductors.

  • When installing surge arresters on both primary and secondary sides of the H59 Oil Immersed Power Distribution Transformer, connect the arrester grounding lead, transformer tank, and secondary neutral point to a common grounding point. Conduct regular preventive tests and promptly replace any defective arresters to reduce the risk of overvoltage damage caused by lightning or resonance.

  • When switching the off-load tap changer, always measure DC resistance twice after each tap change, record the values, and compare the three-phase DC resistances for balance. Only put the transformer back into service after confirming normal tap operation. When measuring across all tap positions, keep detailed records and ensure the DC resistance of the operating tap is measured last.

  • Implement effective load monitoring and management for each service area. Promptly replace transformers in areas experiencing overload to prevent burnout due to prolonged overloading.

Give a tip and encourage the author!

Recommended

Distribution Equipment Transformer Testing, Inspection, and Maintenance
1.Transformer Maintenance and Inspection Open the low-voltage (LV) circuit breaker of the transformer under maintenance, remove the control power fuse, and hang a “Do Not Close” warning sign on the switch handle. Open the high-voltage (HV) circuit breaker of the transformer under maintenance, close the grounding switch, fully discharge the transformer, lock the HV switchgear, and hang a “Do Not Close” warning sign on the switch handle. For dry-type transformer maintenance: first clean the porcel
12/25/2025
Design Principles for Pole-Mounted Distribution Transformers
Design Principles for Pole-Mounted Distribution Transformers(1) Location and Layout PrinciplesPole-mounted transformer platforms should be located near the load center or close to critical loads, following the principle of “small capacity, multiple locations” to facilitate equipment replacement and maintenance. For residential power supply, three-phase transformers may be installed nearby based on current demand and future growth projections.(2) Capacity Selection for Three-Phase Pole-Mounted Tr
12/25/2025
Risk Identification and Control Measures for Distribution Transformer Replacement Work
1.Electric Shock Risk Prevention and ControlAccording to typical design standards for distribution network upgrades, the distance between the transformer’s drop-out fuse and the high-voltage terminal is 1.5 meters. If a crane is used for replacement, it is often impossible to maintain the required minimum safety clearance of 2 meters between the crane boom, lifting gear, slings, wire ropes, and the 10 kV live parts, posing a severe risk of electric shock.Control Measures:Measure 1:De-energize th
12/25/2025
14 Measures to Improve Distribution Transformer Quality
1. Design Requirements to Improve Transformer Short-Circuit Withstand CapabilityDistribution transformers should be designed to withstand symmetrical short-circuit currents (thermal stability current) at 1.1 times the current under the most unfavorable three-phase short-circuit conditions. The peak short-circuit current (dynamic stability current) should be designed for 1.05 times the current when short-circuit occurs at the instant of zero terminal voltage (maximum peak current factor). Based o
12/24/2025
Related Products
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.