• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


GIS Dual Grounding & Direct Grounding: State Grid 2018 Anti-Accident Measures GIS Dual na Grounding ug Direct na Grounding: Mga Pamaagi sa Pag-uli sa mga Aksidente sa State Grid 2018

Echo
Echo
Larangan: Pagsusi sa Transformer
China

1. Mahitungod sa GIS, unsa ang pagkatuod sa gipangutana sa Clause 14.1.1.4 sa "Eighteen Anti-Accident Measures" (2018 Edition) sa State Grid?

14.1.1.4: Ang neutral point sa transformer kailangan i-connection ngadto sa duha ka uban-uban nga bahin sa main mesh sa grounding grid pinaagi sa duha ka grounding down conductors, ug ang bawg konduktor kailangan mobati sa thermal stability verification requirements. Ang main equipment ug equipment structures kailangan adunay duha ka grounding down conductors nga i-connection ngadto sa uban-uban nga trunks sa main grounding grid, ug ang bawg konduktor usab kailangan mobati sa thermal stability verification requirements. Ang mga connection leads kailangan ig-arrange aron madali ang periodic inspection ug testing.

Kumpara sa 2012 edition sa "Eighteen Anti-Accident Measures," ang wording gihulagway gikan sa “main equipment ug equipment structures should preferably adunay duha ka grounding down conductors nga i-connection ngadto sa uban-uban nga trunks sa main grounding grid” ngadto sa “main equipment ug equipment structures kailangan adunay duha ka grounding down conductors nga i-connection ngadto sa uban-uban nga trunks sa main grounding grid.” Kini nga pag-usab nag-upgrade sa requirement gikan sa recommendatory (“should preferably”) ngadto sa mandatory (“kailangan”). Sa kasagaran, tanang substations sa China adunay implementasyon sa dual grounding down conductors isip gipangutana. Aron mas protektahan ang main equipment, ang dual grounding down conductors kailangan obligatorily applied.

Explanation of Clause 14.1.1.4 sa 2018 Edition State Grid “Eighteen Anti-Accident Measures” mahitungod sa GIS:

Ang GIS gi-classify isip main equipment sa substation ug kailangan mobati sa kini nga clause:

  • Ang enclosure sa GIS ug ang iyang associated support structures kailangan adunay duha ka grounding down conductors, ug kini duha ka conductors kailangan i-connection ngadto sa uban-uban nga trunks sa main grounding grid (arong makalimtan ang single-point failure leading to loss of grounding);

  • Ang bawg grounding down conductor kailangan mobati sa thermal stability verification (arong mabati nga dili mag-damage sa overheating kung ang fault current mogdaot);

  • Ang layout sa mga grounding conductors kailangan allow for convenient periodic inspection ug testing (arong mobati sa operational ug maintenance requirements para sa grounding reliability).

Kini nga clause nag-upgrade sa 2012 version’s “recommendatory requirement” ngadto sa “mandatory requirement.” Isip core piece sa main equipment, ang GIS kailangan configure sa dual grounding down conductors aron mapadako ang redundancy ug reliability sa grounding system.

Combined with the on-site situation as shown in the figure below.
220 kV disconnector main equipment.jpg

Para sa standalone main equipment nga gitray sa picture sa itaas, ang requirement sa double grounding relatable straightforward to understand. Pero para sa GIS—diin ang circuit breakers, disconnectors, ug uban pang major components integrated together—interpretations of "double grounding for main equipment" may vary among individuals. In my view, the entire GIS should simply be regarded as one single main equipment unit. The basis for this is as follows:

Ang bawg bay’s enclosure base ug support structure kailangan adunay wala pa dugay sa duha ka reliable grounding points. Ang grounding down conductors kailangan securely connected, free from corrosion, damage, or deformation, ug maintain good electrical continuity. Exposed horizontal grounding busbars kailangan adunay additional supports installed at intervals of 0.5–1.5 m, vertical sections at intervals of 1.5–3 m, ug bends at intervals of 0.3–0.5 m.

As applied on-site, this is illustrated in the figure below: Points A and B represent the two reliable grounding connections between the base and the main grounding grid. The base is then reliably bonded to the GIS support structure via the jumper at point C. Individual GIS modules are reliably interconnected through jumpers at point D (metal flanges do not require bonding jumpers). This configuration establishes a reliable dual-point grounding system for the entire GIS assembly (with the GIS enclosure itself serving as part of the grounding path).

220 kV disconnector main equipment.jpg

Someone might then ask: "If that’s the case, what is the purpose of all those individual grounding leads on the GIS?" as shown in the figure below:

220 kV disconnector main equipment.jpg

This leads to the second question:

2. Mahitungod sa GIS, unsa ang pagkatuod sa gipangutana sa requirement for direct grounding?

The figure above shows grounding conductors directly led from different parts of the GIS to dedicated grounding terminals or grounding blocks—rather than relying on the GIS enclosure for grounding. The reason is specified in the following regulation:

“Voltage transformers, surge arresters, ug fast grounding switches kailangan i-connection directly to the main grounding grid pinaagi sa dedicated grounding conductors, ug dili grounded through the enclosure or support structures.”

220 kV disconnector main equipment.jpg

Looking at the figure above, another question arises:

3. For surge arresters, voltage transformers, ug fast grounding switches inside GIS, is there a requirement for dual direct grounding?
As shown in the figure below:

220 kV disconnector main equipment.jpg

Ang mga eksperto mihatag usab nga ang paspas nga switch sa grounding sa substation nga gipakita sa figura sa itaas dapat usab adunay duha ka direct nga mga grounding conductor nga direktang gipangutana sa grounding block. Isip tugon niining isyu, konsulta nami ang manufacturer, ug ang pagbalik sa manufacturer mihatag nga wala may requirement sa mandatory nga dual direct grounding—ang direct grounding lang ang kinahanglan, basta ang grounding conductor makapugos sa required nga grounding fault current.

Maghatag og tip ug pagsalig sa author
Gipareserbado
Tulo ka mga pamantaran sa IEC sa field sa insulator, nga gisulay sa China, giirelease na.
Tulo ka mga pamantaran sa IEC sa field sa insulator, nga gisulay sa China, giirelease na.
Lahat kini, tulo ka mga pamantaran sa IEC bahin sa insulators, ang unang gihatag nga liderhan sa China, nailhan na og opisyal. Ang tanang pamantaran mao ang nagbahin sa mga marka sa coupling, dimensyon, ug mga pagsulay sa mga end fittings sa insulator, kasagaran ang IEC 60120:2020, IEC 60372:2020, ug IEC 60471:2020. Ang tulo ka mga pamantaran mao ang gitapos sa pagtambok ug koordinasyon sa daghang mga eksperto gikan sa National Technical Committee on Insulators of China (SAC/TC80). Ang pagkuha n
Baker
11/29/2025
Ang unang ±550 kV DC GIS sa China nahuman na og long-term energized test.
Ang unang ±550 kV DC GIS sa China nahuman na og long-term energized test.
Kamakarong, ang ±550 kV DC GIS (Gas-Insulated Switchgear), nga gisulay pinaagi sa usa ka Chinese GIS manufacturer ug daghang kompanya, nakaabot sa maayong pagkamalihok sa 180 ka adlaw nga outdoor long-term energized reliability test sa Xi’an High Voltage Apparatus Research Institute. Kini mao ang unang higayon sa industriya nga ang next-generation ±550 kV DC GIS nakaabot sa matagamtam nga pagkamalihok sa energized evaluation.Ang ±550 kV DC GIS nakaabot na sa komprehensibo nga performance verific
Baker
11/25/2025
Unang Tumbong nga Wala na sa Pagsusi sa GIS sa ±800kV UHV Station
Unang Tumbong nga Wala na sa Pagsusi sa GIS sa ±800kV UHV Station
Sa Oktubre 16, natapos ang tanang gipangandar nga pagpanindot sa ±800 kV ultra-high-voltage (UHV) transmission project ug human na gibag-o gipatrabaho. Sa panahon niini, ang usa ka regional power company makapatulog sa unang pagka-ila nga inspeksyon sa GIS (Gas-Insulated Switchgear) room sa UHV converter station sa sistema sa kuryente.Isip usa ka pangunang bahin sa China’s “West-to-East Power Transmission” strategy, ang ±800 kV UHV project nagoperasyon nang adtong 2016 ug naghatag na og kasagol
Baker
11/21/2025
Ang unang produktong 252 kV mixed-gas double-break GIS sa China makayla nga nagsugyot sa on-site power frequency withstand voltage test.
Ang unang produktong 252 kV mixed-gas double-break GIS sa China makayla nga nagsugyot sa on-site power frequency withstand voltage test.
Bag-o, ang mga Chinese GIS manufacturers miingon og usa ka kabarangan: ang unang ZF11C-252(L) mixed-gas double-break GIS product nga gibuhat sa usa ka Chinese GIS manufacturer adunay kasinatian sa pagpasa sa ilang on-site power frequency withstand voltage test sa una nga pag-ensayo sa project site. Kini nga achievement marka og usa pang milestone alang sa Chinese GIS manufacturers isip sila nagpadayon sa pagbutang ug green ug high-quality development sa power grids.Ang ZF11C-252(L) mixed-gas dou
Baker
11/18/2025
Inquiry
Pangutana
Pangutana sa IEE-Business Application
Pangita og mga equipment gamit ang IEE-Business app asa asa ug kailan man sugad og pagkuha og solusyon pagsulay sa mga eksperto ug pagpadayon sa industriya nga pakisayran suportahan ang imong proyekto sa kuryente ug negosyo