Dielectric Test Definition


The dielectric test of a transformer checks the insulation’s ability to handle voltage without breaking down.


Separate Source Voltage Withstand Test of Transformer


This dielectric test checks the main insulation’s ability to withstand voltage between the winding and the earth.


Procedure


  • All three line terminals of the winding to be tested are connected together.



  • Other winding terminals not under test and the transformer tank should be connected to the earth.



  • Then a single-phase power frequency voltage of shape approximately sinusoidal is applied for 60 seconds to the terminals of the winding under test.



  • The test shall be performed on all the windings one by one.


  • The test is successful if the insulation does not break down during the test.

 

750ffe8af9fa2b8ac85537cdc5a2db18.jpeg

 

In this transformer testing, the peak value of voltage is measured, that is why the capacitor voltage divider with digital peak voltmeter is employed as shown in the diagram above. The peal value multiplied by 0.707 (1/√2) is the test voltage.


The values of test voltage for different fully insulated winding are furnished below in the table.


a3b510e758c200156aaccb1913125fc5.jpeg


Induced Voltage Test of Transformer


19d86833ccd9abc79b3a28c9c1e10767.jpeg

 

The induced voltage test of transformer is intended to check the inter turn and line end insulation as well as main insulation to earth and between windings-

 


  • Keep the primary winding of transformer open circuited.



  • Apply three phase voltage to the secondary winding. The applied voltage should be twice of rated voltage of secondary winding in magnitude and frequency.



  • The test should last for 60 seconds.



  • The test shall start with a voltage lower than 1/3 the full test voltage, and it shall be quickly increased up to desired value.



The test is successful if no break down occurs at full test voltage during test.

Give a tip and encourage the author!

Recommended

Impact of DC Bias in Transformers at Renewable Energy Stations Near UHVDC Grounding Electrodes
Impact of DC Bias in Transformers at Renewable Energy Stations Near UHVDC Grounding ElectrodesWhen the grounding electrode of an Ultra-High-Voltage Direct Current (UHVDC) transmission system is located close to a renewable energy power station, the return current flowing through the earth can cause a rise in ground potential around the electrode area. This ground potential rise leads to a shift in the neutral-point potential of nearby power transformers, inducing DC bias (or DC offset) in their
01/15/2026
How to Test Insulation Resistance of Distribution Transformers
In practical work, insulation resistance of distribution transformers is generally measured twice: the insulation resistance between thehigh-voltage (HV) windingand thelow-voltage (LV) winding plus the transformer tank, and the insulation resistance between theLV windingand theHV winding plus the transformer tank.If both measurements yield acceptable values, it indicates that the insulation among the HV winding, LV winding, and transformer tank is qualified. If either measurement fails, pairwise
12/25/2025
Design Principles for Pole-Mounted Distribution Transformers
Design Principles for Pole-Mounted Distribution Transformers(1) Location and Layout PrinciplesPole-mounted transformer platforms should be located near the load center or close to critical loads, following the principle of “small capacity, multiple locations” to facilitate equipment replacement and maintenance. For residential power supply, three-phase transformers may be installed nearby based on current demand and future growth projections.(2) Capacity Selection for Three-Phase Pole-Mounted Tr
12/25/2025
Analysis of Common Faults and Causes in Routine Inspection of Distribution Transformers
Common Faults and Causes in Routine Inspection of Distribution TransformersAs the terminal component of power transmission and distribution systems, distribution transformers play a critical role in supplying reliable electricity to end users. However, many users have limited knowledge of power equipment, and routine maintenance is often carried out without professional support. If any of the following conditions are observed during transformer operation, immediate action should be taken: Excess
12/24/2025
Related Products
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.