• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Correct Power Off and Power On Sequence for Distribution Rooms and Step-by-Step Energizing Procedure

Echo
Field: Transformer Analysis
China

Power Off and Power On Sequence in the Distribution Room

Power-off sequence:
When de-energizing, first disconnect the low-voltage (LV) side, then the high-voltage (HV) side.

  • When de-energizing the LV side:
    First open all LV branch circuit breakers, then open the LV main breaker. Additionally, disconnect the control circuits before de-energizing the main power circuits.

  • When de-energizing the HV side:
    First open the circuit breaker, then open the isolating switch (disconnector).
    If the HV incoming line has two isolating switches, first open the load-side isolating switch, then the source-side isolating switch.

Power-on sequence: Reverse the above order.

Never operate an isolating switch under load.

Power-On Operation Procedure for the Distribution Room

The power-on procedure is as follows:

  • Confirm that no personnel are working on any electrical equipment in the entire distribution room. Remove temporary grounding wires and warning signs. When removing grounding wires, disconnect the line end first, then the grounding end.

  • Verify that the incoming line switches for both circuits WL1 and WL2 are in the open position. Then close the bus-tie isolating switch between the two HV busbars WB1 and WB2 to allow them to operate in parallel.

  • Sequentially close all isolating switches on WL1, then close the incoming circuit breaker. If the closing is successful, it indicates that WB1 and WB2 are in good condition.

  • Close the isolating switches for the voltage transformer (VT) circuits connected to WB1 and WB2, and verify that the supply voltage is normal.

  • Close all HV outgoing isolating switches, then close all HV outgoing circuit breakers to energize the main transformers of the distribution room.

  • Close the LV-side knife switch of the main transformer in Distribution Room No. 2, followed by the LV circuit breaker. Successful closing indicates that the LV busbar is intact.

  • Use voltmeters connected to both LV busbar sections to verify normal LV voltage.

  • Close all LV outgoing knife switches in Distribution Room No. 2, then close the LV circuit breakers (or close LV fuse-switch disconnectors) to energize all LV outgoing circuits. At this point, the entire HV distribution substation and its associated workshop substations are fully operational.

Restoring Power After Fault Clearance:

If power is being restored after a fault-related outage, the procedure depends on the type of switching device installed at the incoming line:

  • If the incoming line uses a high-voltage circuit breaker:
    In the event of a short-circuit fault on the HV busbar, the circuit breaker will trip automatically. After the fault is cleared, power can be restored simply by reclosing the circuit breaker.

  • If the incoming line uses a high-voltage load-break switch:
    After fault clearance, first replace the fuse cartridge, then close the load-break switch to restore power.

  • If the incoming line uses a high-voltage isolating switch with fuses (fuse-disconnector combination):
    After fault clearance, first replace the fuse tube, then open all outgoing circuit breakers. Only then may the isolating switch be closed, followed by reclosing all outgoing breakers to restore power.

  • If the incoming line uses a drop-out fuse (expulsion fuse):
    The same procedure applies—replace the fuse tube, ensure all outgoing switches are open, close the fuse, then re-energize the outgoing circuits.

Give a tip and encourage the author!
Recommended
Impact of DC Bias in Transformers at Renewable Energy Stations Near UHVDC Grounding Electrodes
Impact of DC Bias in Transformers at Renewable Energy Stations Near UHVDC Grounding ElectrodesWhen the grounding electrode of an Ultra-High-Voltage Direct Current (UHVDC) transmission system is located close to a renewable energy power station, the return current flowing through the earth can cause a rise in ground potential around the electrode area. This ground potential rise leads to a shift in the neutral-point potential of nearby power transformers, inducing DC bias (or DC offset) in their
01/15/2026
HECI GCB for Generators – Fast SF6 Circuit Breaker
1.Definition and Function1.1 Role of the Generator Circuit BreakerThe Generator Circuit Breaker (GCB) is a controllable disconnect point located between the generator and the step-up transformer, serving as an interface between the generator and the power grid. Its primary functions include isolating generator-side faults and enabling operational control during generator synchronization and grid connection. The operating principle of a GCB is not significantly different from that of a standard c
01/06/2026
Distribution Equipment Transformer Testing, Inspection, and Maintenance
1.Transformer Maintenance and Inspection Open the low-voltage (LV) circuit breaker of the transformer under maintenance, remove the control power fuse, and hang a “Do Not Close” warning sign on the switch handle. Open the high-voltage (HV) circuit breaker of the transformer under maintenance, close the grounding switch, fully discharge the transformer, lock the HV switchgear, and hang a “Do Not Close” warning sign on the switch handle. For dry-type transformer maintenance: first clean the porcel
12/25/2025
How to Test Insulation Resistance of Distribution Transformers
In practical work, insulation resistance of distribution transformers is generally measured twice: the insulation resistance between thehigh-voltage (HV) windingand thelow-voltage (LV) winding plus the transformer tank, and the insulation resistance between theLV windingand theHV winding plus the transformer tank.If both measurements yield acceptable values, it indicates that the insulation among the HV winding, LV winding, and transformer tank is qualified. If either measurement fails, pairwise
12/25/2025
Related Products
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.