• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Mga Dapat I-ground sa mga Cable Lines ug ang mga Prinsipyo sa Pag-handle sa mga Insidente

Felix Spark
Larangan: Pagkabag-o ug Pagpangutana
China

Ang atong substation sa 220 kV nahimutang sa layo gikan sa sentro ngadto sa isla, gibulag ug sa primarya industriyal nga mga zonal sama sa Lanshan, Hebin, ug Tasha Industrial Parks. Ang mga major nga high-load consumers sa mga zonal niini—kasama ang silicon carbide, ferroalloy, ug calcium carbide plants—naghahatag og mahigit 83.87% sa total nga load sa atong bureau. Ang substation nagoperasyon sa mga voltage levels nga 220 kV, 110 kV, ug 35 kV.

Ang 35 kV low-voltage side pangunaa nga naghahatag og feeders sa ferroalloy ug silicon carbide plants. Ang mga energy-intensive nga factories naa duol sa substation, resulta mao ang heavy loads, short feeder lines, ug severe pollution. Ang mga feeders naa sa kabuokan connected pinaagi sa cables, sharing a common cable trench. Kini nagresulta og significant risks sa substation kung adunay line fault. Ang paper na niini gi-analyze ang causes sa 35 kV line faults ug gitumong ang corresponding countermeasures. Sa Pebrero 2010, ang 220 kV substation sa atong bureau naka-experience og frequent grounding faults sa 35 kV II bus ug 35 kV III bus, as detailed in Table 1.

fault.jpg

1 Analysis of Grounding Causes in Cable Lines
Sumala sa atong bureau’s 2010 statistics sa cable incidents, ang main causes sa cable line failures mao kini:

  • Temperature effects: Sa mga facilities sama sa Sanyou Chemical, ang high temperatures sa furnace transformers ug cable terminations nagresulta sa insulation breakdown. Naka-occur kini sa mahigit 18 incidents, requiring the fabrication of 15 cable terminations.

  • High cable density in cable trenches: Sa Rongsheng Yinbei Ferroalloy Plant, ang manhole covers nagsilip ug nangabot sa cables sa trench, causing short circuits ug fires nga naaffect sa uban pang plants’ cables. A total of 51 cable splices were made.

  • Severe customer overloading: Ang mga plants sama sa Huanghe Ferroalloy, Pengsheng Metallurgy, Lingyun Chemical, ug Rongsheng Yinbei Ferroalloy nag-operate sa cables sa long-term overload conditions, accelerating cable aging ug increasing temperatures. Especially during hot summers, thermal stress caused insulation breakdown in cables and terminations, requiring approximately 50 cable terminations.

  • Mechanical damage: Ang excavators sa construction ug earthworks nangabot sa cables, causing fractures ug insulation damage. A total of 25 cable terminations and splices were made.

  • Cable quality issues: Ang mga defects sama sa air bubbles in insulation o broken shielding sa manufacturing nagresulta sa 9 accidents, requiring 9 cable terminations and splices.

  • Damage during cable laying: Ang excessive pulling tension sa long cable runs nagresulta sa scraping sa sharp objects, resulting in 13 cable damage incidents.

  • Poor cable termination workmanship: Ang insufficient technical expertise ug improper procedures sa installation nagresulta sa moisture ingress in cable insulation. A total of 16 cable splices and terminations were fabricated.

  • Surface discharge on cable terminations: Ang heavy pollution gikan sa high-energy-consuming plants nagresulta sa contaminants settling on cable equipment. Ang dirty cable termination surfaces, combined with rain or humid weather, caused surface flashover, damaging insulation and leading to breakdowns. In such cases, 13 cable terminations were replaced.

2 Principles for Handling Cable Grounding Faults
Adunay standard procedures sa handling sa 35 kV cable grounding faults. Pero sa atong bureau, ang mga voltage-level lines primarya nga nagsilbi sa high-energy consumers sa large individual capacities (minimum 12,500 kVA), direct supply loads, heavy loading, ug high currents. 

Ang sudden load shedding nagresulta sa significant grid disturbances. Moreover, ang cable grounding faults dili easy locate, ug prolonged fault duration nag-increase sa risks. If not addressed promptly, such faults can endanger grid safety, placing higher demands on dispatchers. Ang uban nga 35 kV customers coal mines o chemical plants—classified as critical users. Ang power outages para sa mga users naa potential mag-lead sa casualties, fires, o explosions. Therefore, ang customers categorized as general or critical, sumala sa following handling principles:

  • Para sa general customers (mainly silicon carbide and ferroalloy plants), once a faulted line is identified, contact the customer immediately to disconnect the load and de-energize the faulty line promptly. For non-cooperative customers, enforce load shedding with warning measures.

  • Para sa critical customers sama sa coal mines ug chemical plants, instruct them to transfer loads to backup power sources. If no backup exists, prepare for outage before taking the faulty line out of service.

  • Given the strong overload capability of smelting furnaces, for substations and lines operating under long-term heavy load, if current exceeds 90% of the current transformer rating, enhance monitoring, notify customers to reduce load, and implement a three-step process: notification → warning → forced load shedding, to ensure equipment safety.

  • For customers with frequent cable failures, require enhanced line inspections and regular maintenance during scheduled outages, performed by qualified professional contractors to ensure reliable operation.

  • Strict quality control from the source: For dedicated-line customers, require submission of all relevant documentation to the dispatch center and signing of a "Dispatch Agreement" before commissioning. Customers without a signed agreement or with incomplete/inadequate documentation shall not be connected to the grid.

  • For cable trenches with excessive and dense cabling, recommend limiting cable numbers to prevent fault propagation and minimize incident escalation.

3 Conclusion
Ang safe grid operation requires not only careful dispatching and dedication but also proficient use of legal tools to protect both personnel and equipment. Especially when dealing with power customers, the "Dispatch Agreement" must be fully utilized to regulate customer behavior, ensure proper operation, and prevent disputes. It is essential to understand customer line characteristics, load profiles, capacities, and usage patterns in daily operations, enabling swift, accurate, and decisive fault response, and ensuring the safe and stable operation of the power grid.

Maghatag og tip ug pagsalig sa author

Gipareserbado

Mga Sayop ug Paghunahuna Sa Pag-atas Sa Iisa Ka Fasa Sa 10kV Distribution Lines
Mga Kinaiya ug mga Kaugalingong Detektor sa Single-Phase Ground Fault1. Mga Kinaiya sa Single-Phase Ground FaultMga Signal sa Central Alarm:Nagring ang warning bell, ug naglitaw ang indicator lamp nga gilabel “Ground Fault on [X] kV Bus Section [Y]”. Sa mga sistema nga may Petersen coil (arc suppression coil) nga naka-ground sa neutral point, ang “Petersen Coil Operated” nga indicator usab motindog.Mga Indikasyon sa Insulation Monitoring Voltmeter:Ang voltage sa nahisalaan nga phase mokubos (kon
01/30/2026
Neutral nga punto sa grounding operation mode alang sa 110kV~220kV power grid transformers
Ang pag-arrange sa mga modo ng operasyon ng grounding ng neutral point para sa 110kV~220kV power grid transformers dapat matugunan ang mga requirement ng insulation withstand sa mga neutral points ng transformer, ug usahay mao usab ang pagpanalipod sa zero-sequence impedance sa mga substation nga walay dako nga kausaban, samtang sigurado nga ang zero-sequence comprehensive impedance sa anumang punto sa short-circuit sa sistema dili mogawas sa tulo ka beses sa positive-sequence comprehensive impe
01/29/2026
Unsa ang Katuyohan sa Paggamit og Bato Gravel Pebbles ug Crushed Rock sa mga Substation?
Asa Kini ang mga Substation Usa ka Bato, Gravel, Pebbles, ug Crushed Rock?Sa mga substation, ang mga equipment sama sa power ug distribution transformers, transmission lines, voltage transformers, current transformers, ug disconnect switches nimo kinahanglan og grounding. Padulong sa grounding, karon atong ibutangan ang kahibawo bahin kon asa kini nga gravel ug crushed stone gamiton sa mga substation. Bisag ordinaryohan ra sila, importante kaayo ang papel nila sa seguridad ug pagkabana-bana.Sa d
01/29/2026
HECI GCB para sa Mga Generator – Fast SF₆ Circuit Breaker
1.Pagtulun-an ug Funcion1.1 Papeles sa Generator Circuit BreakerAng Generator Circuit Breaker (GCB) mao ang ma-kontrol nga punto sa pagkonektar nga nahimutang tali sa generator ug step-up transformer, nagserbi isip interface tali sa generator ug power grid. Ang iyang primary nga mga funcion kinahanglan ng adunay pag-isolate sa mga fault sa gilid sa generator ug pag-enable sa operasyonal nga kontrol sa panahon sa synchronization sa generator ug koneksyon sa grid. Ang operasyonal nga prinsipyong G
01/06/2026
Inquiry
+86
I-klik aron i-upload ang file
Pangutana
Pangutana sa IEE-Business Application
Pangita og mga equipment gamit ang IEE-Business app asa asa ug kailan man sugad og pagkuha og solusyon pagsulay sa mga eksperto ug pagpadayon sa industriya nga pakisayran suportahan ang imong proyekto sa kuryente ug negosyo