Top 5 Faults Found in H61 Distribution Transformers

Felix Spark
Field: Failure and maintenance
China

Five Common Defects of H61 Distribution Transformers

1.Lead Wire Defects
Inspection Method: The three-phase DC resistance imbalance rate significantly exceeds 4%, or one phase is essentially open-circuited.
Remedial Measures: The core should be lifted for inspection to locate the defective area. For poor contacts, re-polish and tighten the connection. Poorly welded joints should be re-welded. If the welding surface area is insufficient, it should be enlarged. If the lead wire cross-section is inadequate, it should be replaced (with a larger size) to meet requirements.

2.Tap Changer Defects
Inspection Method: Measure DC resistance at different tap positions. If there is complete open circuit, the switch is likely burned out. If DC resistance imbalance occurs at a specific tap, individual contacts may be burned. A strong burnt smell indicates overheating or arcing.
Remedial Measures: Lift the core for inspection. If the switch contacts only show mild overheating, poor contact, or slight arcing marks, they can be removed, repaired, and reused. If severely burned or if there is evidence of ground discharge between contacts, the switch must be replaced. Ground discharge often causes deformation of the high-voltage winding’s tap section; in severe cases, the winding must be repaired or rewound (replaced).

3.Winding Defects
Inspection Method: Winding faults typically manifest as oil spraying from the conservator tank, bulging of the tank body, and a burnt oil odor. Insulation resistance and DC resistance measurements can be performed—insulation resistance near “zero” and unstable, increased DC resistance indicate winding issues.
Remedial Measures: Lift the core to assess the fault condition. Minor damage may be repairable for continued use. Severe faults require winding replacement. For conservator tank sealing issues, technical modifications should be implemented.

4.Reduced Insulation
Inspection Method: Regular insulation resistance tests and oil tests should be conducted on the transformer. Significant changes in measured values or results below the requirements specified in the "Regulations" indicate moisture ingress or degraded oil insulation performance.
Remedial Measures: If the transformer’s insulation resistance decreases, thorough drying is required. If oil insulation degrades, the oil should be replaced or filtered. Faulty seals and defective breathers (dehydrating breathers) must be repaired.

5.Core Defects
Inspection Method: Measure the insulation resistance of the core-through bolts. If it is less than 10 MΩ, repairs are needed.
Remedial Measures: After lifting the core, remove the damaged core-through bolt and replace its insulation.

Give a tip and encourage the author!

Recommended

Distribution Equipment Transformer Testing, Inspection, and Maintenance
1.Transformer Maintenance and Inspection Open the low-voltage (LV) circuit breaker of the transformer under maintenance, remove the control power fuse, and hang a “Do Not Close” warning sign on the switch handle. Open the high-voltage (HV) circuit breaker of the transformer under maintenance, close the grounding switch, fully discharge the transformer, lock the HV switchgear, and hang a “Do Not Close” warning sign on the switch handle. For dry-type transformer maintenance: first clean the porcel
12/25/2025
Design Principles for Pole-Mounted Distribution Transformers
Design Principles for Pole-Mounted Distribution Transformers(1) Location and Layout PrinciplesPole-mounted transformer platforms should be located near the load center or close to critical loads, following the principle of “small capacity, multiple locations” to facilitate equipment replacement and maintenance. For residential power supply, three-phase transformers may be installed nearby based on current demand and future growth projections.(2) Capacity Selection for Three-Phase Pole-Mounted Tr
12/25/2025
Risk Identification and Control Measures for Distribution Transformer Replacement Work
1.Electric Shock Risk Prevention and ControlAccording to typical design standards for distribution network upgrades, the distance between the transformer’s drop-out fuse and the high-voltage terminal is 1.5 meters. If a crane is used for replacement, it is often impossible to maintain the required minimum safety clearance of 2 meters between the crane boom, lifting gear, slings, wire ropes, and the 10 kV live parts, posing a severe risk of electric shock.Control Measures:Measure 1:De-energize th
12/25/2025
Analysis of Common Faults and Causes in Routine Inspection of Distribution Transformers
Common Faults and Causes in Routine Inspection of Distribution TransformersAs the terminal component of power transmission and distribution systems, distribution transformers play a critical role in supplying reliable electricity to end users. However, many users have limited knowledge of power equipment, and routine maintenance is often carried out without professional support. If any of the following conditions are observed during transformer operation, immediate action should be taken: Excess
12/24/2025
Related Products
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.