• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Ano ang mga Essential na Tests nga Gibutangan ang Qualified na Combined Instrument Transformers?

Oliver Watts
Oliver Watts
Larangan: Pagsusi ug Paghunahuna
China

Hi everyone, I’m Oliver, and I’ve been working in the instrument transformer industry for almost eight years now. From a complete newbie to someone who can now handle things independently, I’ve participated in dozens of combined instrument transformer inspections over the years.

Today, I’d like to share with you: What tests must a qualified combined instrument transformer go through before leaving the factory or being put into operation? After all, it's a very critical piece of equipment in the power system — there’s no room for carelessness.

1. Insulation Test: Is the “Protective Layer” Reliable?

First and most importantly, we have the insulation performance test. Combined instrument transformers usually operate at high voltages like 35kV. If the insulation isn’t up to standard, it could cause anything from inaccurate measurements to short circuits or even explosions.

We perform several key tests:

  • Insulation resistance test – using a megohmmeter to measure the insulation resistance between windings, which should generally be no less than 1000MΩ.

  • Power frequency withstand voltage test – simulating extreme voltage conditions to see if the transformer can withstand voltage surges higher than its rated level for a short time.

  • Partial discharge test – to detect any tiny internal defects like bubbles or cracks, which could lead to major issues during long-term operation.

I once dealt with a customer complaint where the transformer broke down after just a few months of operation. The root cause was poor insulation treatment. So this step really cannot be skipped!

2. Ratio and Error Test: Accuracy Is the Key!

One of the core functions of a combined instrument transformer is to accurately measure current and voltage, which means its ratio must be precise, and the error must be within standard limits.

We usually perform:

  • Ratio test – verifying that the voltage and current ratio between the primary and secondary sides matches the design specifications.

  • Error test (ratio error and phase error) – especially for metering-grade transformers, the error must be controlled within ±0.2%.

Sometimes, customers say things like, “My transformer looks fine, but the electricity bills never match.” That’s when we usually suspect the error has exceeded acceptable limits. So this step directly affects the user’s interests.

3. Polarity Test: If the Direction Is Wrong, Everything Goes Wrong!

Don’t underestimate this step — the polarity test is really important. If the polarity of the transformer is reversed, it can cause the protective relay to misjudge and even disable the entire protection system.

We use either the DC method or AC method to confirm the polarity of the transformer. Especially for combined transformers, which contain both voltage and current components, the polarity must match exactly — otherwise, the whole system could fail.

4. Volt-Ampere Characteristic Test: The “Ultimate Challenge” for Current Transformers

This test mainly applies to the current transformer part. The volt-ampere characteristic reflects the magnetization performance of the iron core and helps us determine whether the transformer can function properly under fault current without saturation.

We gradually increase the voltage, record the current changes, and draw the volt-ampere curve. If the curve is abnormal, it indicates there may be a problem with the core, and the unit needs to be sent back for repair.

I remember a project where the customer reported that the protection system kept malfunctioning. After checking the volt-ampere curve, we found the core was already severely saturated — that was the root of the problem.

5. Short Circuit and Open Circuit Test: Simulating Extreme Conditions

To verify the transformer’s performance under abnormal conditions, we also perform:

  • Secondary short circuit test – checking the protection performance of the voltage transformer when the secondary side is shorted.

  • Secondary open circuit test – observing whether the current transformer generates overvoltage when open-circuited.

These tests aren’t part of the regular routine, but they are essential for special applications, such as important substations or new energy grid-connection projects.

6. Temperature Rise Test: Can It Handle the Heat?

During long-term operation, instrument transformers will generate heat. If the heat dissipation design is poor or the materials can’t withstand high temperatures, it could lead to insulation aging or even burnout.

We simulate rated or even overloaded conditions and measure the temperature rise across different parts to ensure it stays within acceptable limits.

This test is especially important in high-temperature environments or areas with high load demands.

7. Sealing Test (for SF6 Transformers)

For SF6 gas-insulated combined instrument transformers, the sealing test is a must. If the gas leaks, it not only affects insulation performance but also causes environmental pollution and can even endanger personal safety.

We use infrared imaging leak detectors or gas leak detectors to thoroughly inspect all sealing surfaces and weld points.

8. Appearance and Structure Inspection: Details Make the Difference

Don’t think this is just superficial — the appearance and structure inspection is actually very important. We check:

  • Whether the housing is deformed or cracked

  • Whether the terminal connections are tight and clearly marked

  • Whether the nameplate information is accurate

  • Whether the installation structure is reasonable

Once, we found a loose grounding terminal on a transformer. While it might seem minor, if it goes unnoticed and is put into operation, the consequences could be serious.

Conclusion: Being Qualified Is Not the Goal — Safety Is the Foundation

As someone who has worked in the instrument transformer industry for eight years, I know firsthand that behind every qualified combined instrument transformer are layers of strict testing. Each test isn’t just a formality — it ensures that the equipment can operate stably, safely, and reliably in real-world conditions.

If you're in the industry, I hope this article helps you organize the testing process. And if you're a client or engineer, I hope it gives you a better understanding of what goes on behind the scenes with instrument transformers.

A qualified instrument transformer isn’t just about words — it’s truly “tested” into existence.

I’m Oliver — catch you next time for more instrument transformer insights. Bye!

Maghatag og tip ug pagsalig sa author
Gipareserbado
Ang inspeksyon sa mga transformer mahimo ang gihapon bisan walay mga kasangkapan alang sa pagdetece.
Ang inspeksyon sa mga transformer mahimo ang gihapon bisan walay mga kasangkapan alang sa pagdetece.
Ang mga transformers mao ang mga electrical devices nga nag-usab sa voltage ug current batas sa principle sa electromagnetic induction. Sa power transmission ug distribution systems, importante kaayo ang mga transformers aron mopataas o mobaba ang mga voltages aron mapangita ang energy losses sa panahon sa transmission. Tumong, ang mga industrial facilities kasagaran mogawas og power sa 10 kV, nga usab mobaba sa low voltage pinaagi sa transformers alang sa on-site use. Karon, atong pagbatasan an
Oliver Watts
10/20/2025
Pagsulay sa Vacuum Circuit Breakers alang sa Capacitor Bank
Pagsulay sa Vacuum Circuit Breakers alang sa Capacitor Bank
Pagkompensar sa Reactive Power ug Pagpaila ngadto sa Capacitor sa mga System sa PowerAng pagkompensar sa reactive power usa ka epektibong paagi aron mapataas ang sistema nga operasyon voltage, mapabag-o ang network losses, ug mapahimulos ang stability sa sistema.Ang Konbensional nga Mga Load sa mga System sa Power (Impedance Types): Resistance Inductive reactance Capacitive reactanceInrush Current Sa Panahon sa Energization sa CapacitorSa operasyon sa sistema sa power, ang mga capacitor gi-switc
Oliver Watts
10/18/2025
Pahimong Guide sa Pagsusi sa Voltage ng Vacuum Circuit Breaker
Pahimong Guide sa Pagsusi sa Voltage ng Vacuum Circuit Breaker
Pangutana sa Voltage sa Insulation sa Vacuum Circuit BreakersAng pangunahon nga butang sa insulation voltage test sa vacuum circuit breakers mao ang pag-verify kung ang insulation performance sa equipment sa dako nga voltage maoy qualified, ug ang pag-prevent sa breakdown o flashover accidents sa panahon sa operasyon. Ang proseso sa test dili bayad mahimong gihatagan og importansya batasan sa power industry aron masiguro ang seguridad sa equipment ug reliability sa power supply.Test ObjectsAng m
Garca
10/18/2025
Paunsa ang Bango sa Vacuum sa mga Vacuum Circuit Breakers
Paunsa ang Bango sa Vacuum sa mga Vacuum Circuit Breakers
Pagsusi sa Integrity sa Vacuum sa mga Circuit Breakers: Isang Kritikal nga Medida alang sa Evaluation sa PerformanceAng pagsusi sa integrity sa vacuum usa ka pangunahon nga paagi alang sa pag-ila sa performance sa vacuum sa mga circuit breakers. Kini nga test mahimong maayo nga i-evaluate ang insulating ug arc-quenching capabilities sa breaker.Bago ang pag-test, siguraduhon nga ang circuit breaker naka-install ug naka-connect sa husto. Ang mga common nga paagi sa pagsukat sa vacuum mao ang high-
Oliver Watts
10/16/2025
Inquiry
Pangutana
Pangutana sa IEE-Business Application
Pangita og mga equipment gamit ang IEE-Business app asa asa ug kailan man sugad og pagkuha og solusyon pagsulay sa mga eksperto ug pagpadayon sa industriya nga pakisayran suportahan ang imong proyekto sa kuryente ug negosyo