Dynamic (contact) resistance measurements (DRM) test on circuit breakers

Edwiin
Field: Power switch
China

缩略图.jpg

This test serves to ascertain the length and condition of the current - carrying section of the arcing contacts within SF6 circuit breakers. DRM (Dynamic Resistance Measurement) tests are carried out by passing DC current through the breaker's main contacts during the breaker's operation. Subsequently, the breaker analyser computes and plots the resistance as a function of time. When contact movement is concurrently recorded, the resistance at each contact position can be determined. Through DRM measurement, the length of the arcing contact can be accurately estimated. The only alternative method for this is to disassemble the circuit breaker.

In SF6 breakers, the arcing contact is typically composed of a tungsten/copper alloy. With each interruption of current, it burns off and becomes shorter. A circuit breaker experiences arcing contact wear not only during normal operation but also when interrupting short - circuit currents. If the arcing contact is overly short or in poor condition, the main contact surfaces can be damaged by arcing. This leads to increased resistance, excessive heating, and in the most severe cases, an explosion. As shown in the figure, the main contact resistance is measured dynamically during an open or close operation in DRM.

Give a tip and encourage the author!

Recommended

HECI GCB for Generators – Fast SF6 Circuit Breaker
1.Definition and Function1.1 Role of the Generator Circuit BreakerThe Generator Circuit Breaker (GCB) is a controllable disconnect point located between the generator and the step-up transformer, serving as an interface between the generator and the power grid. Its primary functions include isolating generator-side faults and enabling operational control during generator synchronization and grid connection. The operating principle of a GCB is not significantly different from that of a standard c
01/06/2026
Rockwill Passes Single-Phase Ground Fault Test for Smart Feeder Terminal
Rockwill Electric Co., Ltd. has successfully passed the real-scenario single-phase-to-ground fault test conducted by the Wenzhou of China Electric Power Research Institute for its DA-F200-302 hood-type feeder terminal and integrated primary-secondary pole-mounted circuit breakers—ZW20-12/T630-20 and ZW68-12/T630-20—receiving an official qualified test report. This achievement marks Rockwill Electric as a leader in single-phase ground fault detection technology within distribution networks.The DA
12/25/2025
Case Studies of Installation and Manufacturing Defects in 110kV HV Circuit Breaker Porcelain Insulators
1. SF6 gas leakage occurred in the ABB LTB 72 D1 72.5 kV circuit breaker.Inspection revealed gas leakage at the fixed contact and cover plate area. This was caused by improper or careless assembly, where the dual O-rings slipped and were misplaced, resulting in gas leakage over time.2. Manufacturing Defects on the Outer Surface of 110kV Circuit Breaker Porcelain InsulatorsAlthough high-voltage circuit breakers typically have their porcelain insulators protected with covering materials during tra
12/16/2025
Overview of Defect Diagnosis Methods for High-Voltage AC Circuit Breakers
1. What are the characteristic parameters of the coil current waveform in high-voltage circuit breaker operating mechanisms? How to extract these characteristic parameters from the original trip coil current signal?Answer: The characteristic parameters of the coil current waveform in high-voltage circuit breaker operating mechanisms may include the following: Steady-state peak current: The maximum steady-state current value in the electromagnet coil waveform, representing the position where the
12/16/2025
Related Products
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.