• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


The Necessity of Power Distribution System Maintenance

Leon
Field: Fault Diagnosis
China

Fault Phenomenon

A power distribution system fault occurred in a customer's server room, resulting in damage to some IT equipment and instruments. Upon receiving the feedback, our company's engineers immediately rushed to the site to inspect the power distribution system and analyze the cause of the fault.

Fault Inspection

The server room uses a three-phase five-wire power supply system. Two three-phase input, three-phase output UPS units (without output isolation transformers) are operating in parallel to power the IT equipment in the room. Both the UPS input and output circuit breakers are controlled using 4-pole (4P) breakers.

Upon inspection of the damaged IT equipment, it was found that all affected devices and instruments were connected to the load side of the UPS output phase C, while equipment connected to phases A and B were operating normally. Further inspection revealed that the neutral wire (zero line) on the UPS input circuit breaker was loose, causing the neutral line to become disconnected (floating) on the downstream side of the UPS.

Fault Analysis

In a three-phase five-wire power supply system, when the neutral line is broken, single-phase loads lose their return path, creating phase voltage at the break point, which poses a risk to personal safety. If the three-phase loads are unbalanced, the neutral point will shift, causing the voltage on each phase to either increase or decrease. According to the principle of voltage division in a series circuit, because phase C had a lighter load, it acquired the highest voltage, approaching the 380V line voltage, which led to the destruction of equipment on that phase.

Severe three-phase load imbalance, combined with overheating of the distribution system circuit breakers and loose wiring terminals, created a latent fault that was not promptly eliminated. This led to poor contact on the neutral line, causing sparking, heating, oxidation, and ultimately complete disconnection.

Additionally, the use of 4P circuit breakers for both UPS input and output means that when the UPS input breaker is opened (for example, during battery discharge maintenance), the neutral line is also cut off, which can similarly cause equipment failure.

Summary

The server room's power distribution system requires regular inspection and maintenance by qualified personnel in the following aspects:

  • Measure whether circuit breakers, cables, and terminal connections are overheating.
  • Check if instrument displays are functioning normally.
  • For UPS three-phase output power supply, the load on each phase should be distributed as evenly as possible to maintain three-phase load balance. Strengthen monitoring of three-phase currents and make timely adjustments upon detecting imbalance.
  • Measure whether the line current is within the safe operating range of the circuit breakers.
  • The cross-sectional area of the neutral and ground wires must not be less than the minimum specified by national standards, and connections must be secure and reliable.
  • Fuses or individual switching devices must not be installed on the neutral line.
  • When disconnecting a three-phase four-wire circuit, the phase (live) conductors should be disconnected first, followed by the neutral conductor. The reverse order should be followed when reconnecting.
  • Functional labels for all components must be accurate and clear.
Give a tip and encourage the author!

Recommended

Faults and Handling of Single-phase Grounding in 10kV Distribution Lines
Characteristics and Detection Devices for Single-Phase Ground Faults1. Characteristics of Single-Phase Ground FaultsCentral Alarm Signals:The warning bell rings, and the indicator lamp labeled “Ground Fault on [X] kV Bus Section [Y]” illuminates. In systems with a Petersen coil (arc suppression coil) grounding the neutral point, the “Petersen Coil Operated” indicator also lights up.Insulation Monitoring Voltmeter Indications:The voltage of the faulted phase decreases (in
01/30/2026
Neutral point grounding operation mode for 110kV~220kV power grid transformers
The arrangement of neutral point grounding operation modes for 110kV~220kV power grid transformers shall meet the insulation withstand requirements of transformer neutral points, and shall also strive to keep the zero-sequence impedance of substations basically unchanged, while ensuring that the zero-sequence comprehensive impedance at any short-circuit point in the system does not exceed three times the positive-sequence comprehensive impedance.For 220kV and 110kV transformers in new constructi
01/29/2026
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?In substations, equipment such as power and distribution transformers, transmission lines, voltage transformers, current transformers, and disconnect switches all require grounding. Beyond grounding, we will now explore in depth why gravel and crushed stone are commonly used in substations. Though they appear ordinary, these stones play a critical safety and functional role.In substation grounding design—especially when multiple gr
01/29/2026
How to Judge, Detect and Troubleshoot Transformer Core Faults
1. Hazards, Causes, and Types of Multi-Point Grounding Faults in Transformer Cores1.1 Hazards of Multi-Point Grounding Faults in the CoreUnder normal operation, a transformer core must be grounded at only one point. During operation, alternating magnetic fields surround the windings. Due to electromagnetic induction, parasitic capacitances exist between the high-voltage and low-voltage windings, between the low-voltage winding and the core, and between the core and the tank. The energized windin
01/27/2026
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.