• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Verification of time quantities in commissioning test for Generator circuit breaker (GCB) according to IEC/IEEE

Edwiin
Edwiin
Field: Power switch
China

Commissioning Tests for Generator Circuit Breakers

Once a Generator circuit breaker has been installed, comprehensive commissioning tests must be conducted. The primary objectives of these tests are to:

  • Ensure that no damage has occurred during transportation and storage.

  • Verify the compatibility of individual components.

  • Confirm that the assembly has been carried out correctly.

  • Validate the proper performance of the fully assembled generator circuit breaker.

Verification of Generator Circuit Breaker Time Quantities

During commissioning, the following time - related parameters of the generator circuit breaker need to be verified:

Closing and Opening Times, Time Spread

Measurements should be taken at the maximum pressure and at the supply voltage of the auxiliary and control circuits. The voltage should be measured at the equipment terminals and under typical load conditions of the supply voltage source. The specific measurements include:

  • Closing Time: For each pole, determine the individual closing time, the time spread among the poles, and, if feasible, the time spread of the breaking units or groups of units within each pole.

  • Opening Time: Similarly, measure the opening time of each pole, the time spread of the poles, and, where possible, the time spread of the breaking units or groups of units per pole.

These measurements should be performed for both separate opening and closing operations, as well as for the opening and closing operations within a CO (close - open) operating cycle. In cases where the circuit breaker is equipped with multiple trip coils, all coils must be tested, and the corresponding times for each coil should be accurately recorded.

It is essential to document the supply voltage both before and during the operations. Additionally, if a three - pole control relay is present, the moment it is energized should be recorded. This information is crucial for calculating the total time in three - pole operation, which is the sum of the relay activation time and either the closing or opening time. When the circuit breaker incorporates resistor closing or opening units, the resistor insertion times must also be carefully recorded.

Operation of Control and Auxiliary Contacts

The timing of the operation of one representative of each type (make and break) of control and auxiliary contacts should be determined relative to the operation of the main contacts during both the closing and opening of the generator circuit breaker. This ensures proper coordination and functionality of the control and monitoring elements associated with the circuit breaker.

Recharging Time of the Operating Mechanism

The relevant recharging times must be verified according to the type of operating mechanism:

  • Fluid - Operated Mechanism:

    • Between the minimum and maximum pressure levels (corresponding to the cut - in and cut - off points of the pumping device).

    • During specific operations or sequences, each starting from the minimum pressure (cut - in of the pumping device), including:

    • Closing all three poles.

    • Opening all three poles.

    • Performing a CO operation on all three poles.

    • Measure the operation time of the pumping device (such as a pump, compressor, or control valve) in the following scenarios:

  • Spring - Operated Mechanism: Measure the recharging time of the motor after a closing operation, ensuring that the measurement is taken at the actual site supply voltage. This helps to confirm that the spring - charging mechanism can quickly and effectively prepare the circuit breaker for subsequent operations.

Give a tip and encourage the author!
Recommended
What are the common issues in SF₆ gas circuit faults and circuit breaker failure-to-operate faults?
What are the common issues in SF₆ gas circuit faults and circuit breaker failure-to-operate faults?
This article categorizes faults into two main types: SF₆ gas circuit faults and circuit breaker failure-to-operate faults. Each is described below:1.SF₆ Gas Circuit Faults1.1 Fault Type: Low gas pressure, but density relay does not trigger alarm or lockout signalCause: Faulty density gauge (i.e., contact not closing)Inspection & Handling: Calibrate actual pressure using a standard gauge. If confirmed, replace the density gauge.1.2 Density Relay Triggers Alarm or Lockout Signal (but pressure
Felix Spark
10/24/2025
Are PM Actuators Reliable? Compare Types & Benefits
Are PM Actuators Reliable? Compare Types & Benefits
The performance of circuit breaker operating mechanisms is decisive for reliable and safe power supply. While various mechanisms each have their advantages, the emergence of a new type does not completely replace traditional ones. For example, despite the rise of eco-friendly gas insulation, solid insulation ring main units still hold about 8% of the market, showing new technologies rarely fully displace existing solutions.The permanent magnet actuator (PMA) consists of permanent magnets, a clos
Edwiin
10/23/2025
How to Choose & Maintain Electric Motors: 6 Key Steps
How to Choose & Maintain Electric Motors: 6 Key Steps
"Selecting a High-Quality Motor" – Remember the Six Key Steps Inspect (Look): Check the motor’s appearanceThe motor’s surface should have a smooth, even paint finish. The nameplate must be properly installed with complete and clear markings, including: model number, serial number, rated power, rated current, rated voltage, allowable temperature rise, connection method, speed, noise level, frequency, protection rating, weight, standard code, duty type, insulation class, manufacturing date, and ma
Felix Spark
10/21/2025
High-Voltage Circuit Breaker Types & Fault Guide
High-Voltage Circuit Breaker Types & Fault Guide
High-Voltage Circuit Breakers: Classification and Fault DiagnosisHigh-voltage circuit breakers are critical protective devices in power systems. They rapidly interrupt current when a fault occurs, preventing damage to equipment from overloads or short circuits. However, due to long-term operation and other factors, circuit breakers may develop faults that require timely diagnosis and troubleshooting.I. Classification of High-Voltage Circuit Breakers1. By Installation Location: Indoor-type: Insta
Felix Spark
10/20/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.