• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


High-Voltage Electrical Testing: Key Safety Requirements for Field Operations

Oliver Watts
Oliver Watts
Field: Inspection and testing
China

Power Testing Equipment...jpg

  • The test site layout must be reasonable and organized. High-voltage testing equipment should be placed close to the test object, live parts must be isolated from each other, and remain within the clear line of sight of test personnel.

  • Operational procedures must be rigorous and systematic. Unless otherwise specified, voltage must not be suddenly applied or removed during operation. In case of abnormal conditions, voltage increase must be stopped immediately, pressure rapidly reduced, power disconnected, discharge performed, and appropriate grounding measures taken before inspection and analysis begin.

  • On-site work must strictly enforce the work permit system, work authorization system, work supervision system, as well as procedures for work suspension, transfer, and completion.

  • Barriers or fences must be erected at the test site, warning signs hung, and a designated person assigned for on-site supervision.

  • During power-frequency partial discharge tests, no fewer than two high-voltage test personnel must be present, with the team leader being an experienced individual. Before commencement, the leader must conduct a detailed safety briefing for all test personnel.

  • If electrical connections need to be disconnected for testing purposes, proper markings must be made beforehand, and checks conducted after reconnection.

  • The enclosure of high-voltage testing equipment must be reliably grounded. High-voltage leads should be kept as short as possible and supported by insulating materials when necessary. To prevent discharges from any part of the high-voltage circuit to grounded objects, sufficient clearance must be maintained between the high-voltage circuit and ground.

  • Before applying voltage, wiring and instrument ranges must be carefully checked to ensure the voltage regulator is at zero position and all instruments are correctly set. Only after notifying relevant personnel to move away from the test object and obtaining approval from the team leader may voltage be applied.

  • When changing connections or concluding a test, voltage must first be reduced, power disconnected, and the high-voltage section of the boosting device short-circuited and grounded.

  • Large-capacity test objects without installed grounding wires must be discharged prior to testing.

Power Testing Equipment...jpg

When the rated voltage of the test equipment differs from the actual rated operating voltage of the equipment in service, the test voltage standard shall be determined according to the following principles:

  • When higher-rated-voltage equipment is used to enhance insulation, the test shall be conducted according to the equipment’s rated voltage standard;

  • When higher-rated-voltage equipment is used to meet product interchangeability requirements, the test shall be conducted according to the equipment’s actual rated operating voltage standard;

  • When higher-voltage-grade equipment is used to meet high-altitude or polluted area requirements, the test shall be conducted at the installation site according to the actual operating voltage standard.

Give a tip and encourage the author!
Recommended
A Guide to the Latest Transformer Testing Technologies
A Guide to the Latest Transformer Testing Technologies
Transformers come in many types, primarily oil-immersed and dry-type. Their fault manifestations are diverse, but most failures are concentrated in the windings, core, connecting components, and oil contamination. For example, winding insulation damage, open circuits, short circuits, and inter-turn short circuits at connection points. Common external symptoms of transformer faults include severe overheating, excessive temperature rise, abnormal noise, and three-phase imbalance.Routine transforme
Oliver Watts
10/20/2025
Inspection of transformers can be performed without any detection tools.
Inspection of transformers can be performed without any detection tools.
Transformers are electrical devices that change voltage and current based on the principle of electromagnetic induction. In power transmission and distribution systems, transformers are essential for stepping up or stepping down voltages to reduce energy losses during transmission. For example, industrial facilities typically receive power at 10 kV, which is then stepped down to low voltage via transformers for on-site use. Today, let’s learn about several common transformer inspection methods.1
Oliver Watts
10/20/2025
Vacuum Circuit Breakers for Capacitor Bank Switching
Vacuum Circuit Breakers for Capacitor Bank Switching
Reactive Power Compensation and Capacitor Switching in Power SystemsReactive power compensation is an effective means to increase system operating voltage, reduce network losses, and improve system stability.Conventional Loads in Power Systems (Impedance Types): Resistance Inductive reactance Capacitive reactanceInrush Current During Capacitor EnergizationIn power system operation, capacitors are switched in to improve power factor. At the moment of closing, a large inrush current is generated.
Oliver Watts
10/18/2025
Vacuum Circuit Breaker Withstand Voltage Test Guide
Vacuum Circuit Breaker Withstand Voltage Test Guide
Insulation Withstand Voltage Test Standards for Vacuum Circuit BreakersThe main purpose of the insulation withstand voltage test for vacuum circuit breakers is to verify whether the insulation performance of the equipment under high voltage is qualified, and to prevent breakdown or flashover accidents during operation. The test process must be strictly carried out in accordance with power industry standards to ensure equipment safety and power supply reliability.Test ObjectsThe test objects incl
Garca
10/18/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.