Annealing Test for Wires and Conductors

Electrical4u
Electrical4u
Field: Basic Electrical
0
China

What Is The Annealing Test For Wires And Conductors

This test is normally carried on annealed copper wires, aluminum wires for welding cables and solid conductors of electric power cables. The current carrier conductors of power cable is subjected to twist and bend during laying and installation hence it should be flexible enough to take any desired bending and twisting without breaking and cracking. Annealing test for wires and conductors is performed to confirm the durability of conductor during twisting and bending.

Process of annealing test for wires and conductors

A specimen of conductor of cable is taken. The specimen should be of at least specified gauge length that is the sampled length of that conductor on which test result is measured. The total length of the specimen should be its gauge length plus the lengths at two ends which are used for holding the specimen by tensile test machine holder grips.

A tension test machine is used for this purpose. The Tensile Testing Machine is an Automatic one, having capacity to meet the requirement of this test and the rate of separation of jaws as specified. The grips shall be such as to firmly hold the test specimen. This test also requires a Plane Faced Micrometer with scale division at least 0.01 mm and a measuring scale with least scale division 1 mm. Here only one specimen of test material is required for performing this test. Moreover the specimen is not required to pre conditioned before test. After the specimen is fixed between grips of the machine, tensile stress is applied gradually and uniformly that means the gap between the grips is increased gradually and uniformly till the specimen conductor gets fractured. The rate of elongation of specimen i.e. rate of increase of gap between grips of the machine should not be more than 100 mm per minute.

The elongation is measured on the gauge length after the fractured ends have been fitted together. The elongation is expressed as a percentage of the original specimen gauge length. Main observation of annealing test for wires and conductors is that whether the specimen meets or does not meet the specified maximum allowed elongation. Plane Faced Micrometer with scale division at least 0.01 mm is used to measure the diameter of the specimen used in the test.
tensile test machineIf L is the length of the specimen and L is the length of the entire specimen after it gets fractured due to elongation. More precisely, L is the summation of the length of two fractured parts of the specimen. Then percentage elongation would be expressed as

Tabulation of Observations of Annealing Test

Diameter of Circular Wire in mm

Size of Shaped Solidal Conductor in mm2

Original Gauge Length, L in mm

Length After

Fracture, L in mm

Elongation (L – L) in mm

Calculation

Where, L = original gauge length of specimen
and L = elongated length of specimen

Report

Sample No

Diameter of Circular Wire

Size of Shaped Solidal Conductor

Elongation, percent




Observed

Specified

Conclution :Specimen meets/does not meet the requirements of specification.

Statement: Respect the original, good articles worth sharing, if there is infringement please contact delete.

Give a tip and encourage the author!
Recommended
PT Fuse Slow Blow: Causes, Detection & Prevention
PT Fuse Slow Blow: Causes, Detection & Prevention
I. Fuse Structure and Root Cause AnalysisSlow Fuse Blowing:From the design principle of fuses, when a large fault current passes through the fuse element, due to the metal effect (certain refractory metals become fusible under specific alloy conditions), the fuse first melts at the soldered tin ball. The arc then rapidly vaporizes the entire fuse element. The resulting arc is quickly extinguished by quartz sand.However, due to harsh operating environments, the fuse element may age under the comb
Edwiin
10/24/2025
Why Fuses Blow: Overload, Short Circuit & Surge Causes
Why Fuses Blow: Overload, Short Circuit & Surge Causes
Common Causes of Fuse BlowingCommon reasons for fuse blowing include voltage fluctuations, short circuits, lightning strikes during storms, and current overloads. These conditions can easily cause the fuse element to melt.A fuse is an electrical device that interrupts the circuit by melting its fusible element due to heat generated when current exceeds a specified value. It operates on the principle that, after an overcurrent persists for a certain period, the heat produced by the current melts
Echo
10/24/2025
Fuse Maintenance & Replacement: Safety and Best Practices
Fuse Maintenance & Replacement: Safety and Best Practices
1. Fuse MaintenanceFuses in service should be regularly inspected. The inspection includes the following items: Load current should be compatible with the rated current of the fuse element. For fuses equipped with a fuse blown indicator, check whether the indicator has actuated. Check the conductors, connection points, and the fuse itself for overheating; ensure connections are tight and making good contact. Inspect the fuse exterior for cracks, contamination, or signs of arcing/discharge. Liste
James
10/24/2025
Maintenance and Repair Items for 10kV High-Voltage Switchgear
Maintenance and Repair Items for 10kV High-Voltage Switchgear
I. Routine Maintenance and Inspection(1) Visual Inspection of Switchgear Enclosure No deformation or physical damage to the enclosure. Protective paint coating shows no severe rust, peeling, or flaking. Cabinet is securely installed, clean on the surface, and free of foreign objects. Nameplates and identification labels are neatly affixed and not falling off.(2) Check of Switchgear Operating Parameters Instruments and meters indicate normal values (comparable to typical operating data, with no s
Edwiin
10/24/2025
Related Products
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.