Correct Power Off and Power On Sequence for Distribution Rooms and Step-by-Step Energizing Procedure
Power Off and Power On Sequence in the Distribution RoomPower-off sequence:When de-energizing, first disconnect the low-voltage (LV) side, then the high-voltage (HV) side. When de-energizing the LV side:First open all LV branch circuit breakers, then open the LV main breaker. Additionally, disconnect the control circuits before de-energizing the main power circuits. When de-energizing the HV side:First open the circuit breaker, then open the isolating switch (disconnector).If the HV incoming lin