• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


What are the key considerations for photovoltaic transformer selection?

Echo
Field: Transformer Analysis
China
Sizing Principles and Technical Parameters of Photovoltaic Transformers
Sizing photovoltaic transformers requires a comprehensive consideration of multiple factors, including capacity matching, voltage ratio selection, short - circuit impedance setting, insulation class determination, and thermal design optimization.  The key sizing principles are as follows:
(I) Capacity Matching: Fundamental for Load Bearing
Capacity matching is the core prerequisite in sizing photovoltaic transformers. It requires accurately matching the transformer capacity to the installed capacity of the photovoltaic system and the expected maximum output power, ensuring stable operation under the intended load. The capacity calculation formula is:
where U2 represents the secondary - side voltage of the transformer (typically 400V). Considering the inherent variability of photovoltaic systems (e.g., fluctuations in sunlight and load changes), the calculation must incorporate a safety margin (1.1–1.2 times), load - rate fluctuation coefficient (e.g., KT = 1.05, and power factor (usually 0.95).
Example: For a photovoltaic system with a peak power output of 500kW, a 630kVA, 800V/400V transformer can be selected to adapt to different sunlight and load conditions. Additionally, in accordance with the Technical Guidelines for Distributed Photovoltaic Grid Connection, the capacity of a single distributed photovoltaic power station should not exceed 25% of the maximum load in the power supply area of the upper - level transformer, to avoid grid impacts.
(II) Voltage Ratio Selection: Adapting to Fluctuations and Voltage Regulation
The voltage ratio must align with the output characteristics of the photovoltaic system (inverter voltage typically fluctuates by ±5%) and grid connection requirements, featuring dynamic adjustment capabilities. There are two main adjustment methods:
  • Tap - changer adjustment: Applicable to off - load tap - changing transformers, usually with three ±5% taps (e.g., 10.5kV/10kV/9.5kV), requiring a power - off operation.
  • Automatic voltage regulation module adjustment: Applicable to on - load tap - changing transformers, enabling online dynamic adjustment with a response time ≤200ms.
In actual operation, appropriate taps should be selected based on load characteristics: 5% tap for light loads, and 2.5% or 0% taps for heavy loads, balancing voltage rise during high photovoltaic generation and voltage drop during nighttime peak loads.
(III) Short - Circuit Impedance Setting: Balancing Protection and Stability
Short - circuit impedance should be designed according to the system's short - circuit current level and transformer type (oil - immersed/dry - type), with the calculation formula:
Oil - immersed: 4%–8%; dry - type: 6%–12%. For large transformers (e.g., 9150kVA), increase impedance ( Zk ≥ 20% ). Do temperature correction (75°C for oil - immersed, 120°C for dry - type).
(IV) Insulation Class
Fit outdoor environments. Prefer Class F (155°C) or H (180°C). Use H - class for deserts, salt - spray - resistant materials for coasts, moisture - resistant for high humidity. Consider thermal aging: +6°C doubles aging; - 6°C halves it.
(V) Thermal Design
Optimize by environment. Cooling methods: natural/forced air cooling, oil - immersed self - cooling. For high - temp areas: forced air or hybrid; high - humidity: dry - type + axial ducts; high - dust: IP54 + filters. A desert station uses micro - channel liquid cooling (7:3 deionized water + ethylene glycol) for 3× efficiency.
V. Sizing & Inspection for Different Scenarios
Solutions for typical scenarios:
(I) Grid - Connected
Sizing: Cover inverter/auxiliary power + 1.15× margin (e.g., 1092.5kVA). Match ±5% voltage, 4%–8% impedance, ≥Class F, natural/oil - air cooling. Inspection: Check insulation,THD ≤ 5%, voltage regulation (±2.5%), impedance (±2% of factory value).
(II) Off - Grid
Sizing: 1.2–1.5× load power. Adapt to inverter (e.g., 800V/400V), 6%–12% impedance, ≤200ms voltage regulation, 400V + 220V windings.
 Inspection: Test overload (≥120%), voltage regulation response, voltage balance, and system fluctuations.
(III) High - Temperature
Sizing: Dry - type + forced air or oil - immersed + naphthenic oil. Use high - temp insulation, IP55, 80°C - start/60°C - stop fans. Inspection: Quarterly thermography, semi - annual oil tests, check cooling, monitor winding temp.
(IV) High - Humidity/Coastal
Sizing: IP65 epoxy dry - type, 316L + fluorocarbon coating, salt - resistant insulation, increased spacing. Inspection: Check coating, oil moisture/gases, salt - spray test (≤5% power drop), monitor hydrogen.
(V) High - Dust
Sizing: Fully sealed, IP54, three - stage filters, enlarged cooling area, wear - resistant windings. Inspection: Replace filters quarterly, thermography, check dust - proofing, clean regularly.
(VI) Electromagnetic Interference
Sizing: Sandwich windings (≤500pF), LC filters ( THD ≤ 4% ), meet EMC (GB/T 21419 - 2013), dual - redundant comms. Inspection: Annual EMC tests, monitor harmonics/unbalance, check grounding (≤0.5Ω), test bit error 10-8.
(VII) PV - Energy Storage Integration
Sizing: Integrate PCS (Modbus RTU), 400V + 220V windings, ≤200ms reactive compensation, consider combined loads. Inspection: Verify PCS compatibility, voltage balance (≤1%), test voltage regulation (≤±2%), check storage connections.
Summary: Accurate matching of capacity, voltage, impedance, insulation, and thermal design, plus thorough inspection, ensures safe, efficient, and long - life operation, aligning with distributed PV development under carbon goals.
Give a tip and encourage the author!
Recommended
Technical Analysis of 220 kV High-Voltage Cable Construction in Winter
1.Work Environment Requirements and Safeguard MeasuresBased on technical requirements for cable equipment storage, laying, transportation, laying, transposition, testing, and cable terminations, the project owner and construction units have conducted extensive trials and implemented protective measures regarding ambient temperature, humidity, bending radius, traction control, and route optimization. These measures ensure high-voltage cable quality and on-site safety under harsh winter conditions
James
09/03/2025
Considerations and Recommendations for Flame-Retardant Selection of High-Voltage Cables
1.Flame-Retardant Cable Classification StandardsThe flame-retardant standard system is divided into two main categories. The first category follows the "Classification of Burning Behavior for Electric and Optical Fiber Cables" GB 31247. Cables complying with this standard system are widely used in densely populated areas such as high-speed railways and subways. This standard imposes strict requirements on parameters such as smoke density, heat release, and total smoke production, and cables typi
James
09/03/2025
Must DC circuit breakers always be bipolar?
For a 24V switch-mode power supply branch, I used a single-pole DC circuit breaker, with the negative pole subjected to equipotential bonding (previously, I even directly used AC breakers as substitutes—the main difference being arc-extinguishing performance, but how significant can the arc be in a few-amp low-current short circuit?).During a design review, an expert stated that DC circuit breakers must be bipolar, arguing that DC has positive and negative poles, unlike AC!I'm puzzled—where is t
James
09/02/2025
What Should Be Noted During the Installation Process of Indoor Load Switches?
The installation quality of indoor load switches directly affects their operational safety and service life. It must be carried out focusing on four core principles: "safety protection, standardized wiring, mechanical compatibility, and insulation assurance." Specific precautions are as follows:1.Basic Preparation and Safety Protection Before Installation: Verify that the switch model and specifications (e.g., rated voltage, current) match the actual power distribution requirements to avoid "usi
James
08/27/2025
Seed Inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.