• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Masu maimai na muhimmanci suna da tukar-zane na turbin da ke kula da zuba a cikin masana'antu mai gida ta shirya rarraba?

Echo
Echo
فیلڈ: Takardarwa na Tansufurza
China

Karamin lura, wanda ya shafi da yawa da kuma yadda ake iya gina tafkin da ita ce, yana cikin abubuwa masu muhimmanci da ake taimaka a kasar China. Tana da ayyuka mai kyau (17,000 bilion ton kafofin karkashin lura) da fadada aiki mai yawa. Aiki na aiki da ake yi a kan photovoltaic, wanda ya faru ne da ake yi a wurare da kuma kan aiki da ake yi a kan hanyoyin kan gida, ta zama aiki da ake yi a wurin birnin da kuma aiki mai tsawon a kan gida.

Littattafan ya nuna bayanai game da split-winding transformers a aiki da ake yi a kan grid-connected photovoltaic power stations tun daga fahimtar ilimi zuwa misalai na injiniringa.

1 Muhimman Abubuwan Main Circuit wa Grid-Connected Photovoltaic Power Stations

Main circuit na photovoltaic power stations yana da alaka da kungiyoyin inverters: distributed inverters sun fi dacewa a wurin birnin, amma centralized inverters sun fi dacewa a desert photovoltaic power stations (don samun aiki mai tsawo a kan uniform illumination via centralized Maximum Power Point Tracking - MPPT).

Amma, ba a halayen da za a iya tabbatar da ingantaccen strings ko inverters da suka sauri, ba zan iya tabbatar da zan yi fa'idar jiki, voltage drop, da kuma cost-performance. Saboda haka, jiki daga strings zuwa combiner boxes zuwa inverters da kuma arewacin photovoltaic blocks yana cikin ratios na investment-return. Don samun aiki mai kyau, capacity na centralized inverters tana da 500 kW zuwa 630 kW.

Grid-connected photovoltaic power stations sun yanayi da uku na main circuit schemes (kamar yadda aka nuna a Figure 1). Single-string scheme (da step-up transformers) yana da tsari, amma ana bukatar transformers da suka sauri. Large-unit scheme (da step-up transformers) yana da tsari, amma ana bukatar transformers da suka sauri. Scheme na large-unit (da step-up transformers) yana cikin designs na yanzu, tana bincike da cost da kuma efficiency da ma'ana.

Littattafan ya nuna abubuwan da ke da split-winding transformers a expanded-unit wiring. Wannan transformer yana da uku na operating modes: through operation, half-through operation, da kuma split operation. Idan an yi parallel branches na split winding don iya gudanar low-voltage winding da zai yi aiki da high-voltage winding, wannan yana nufin through operation, da short-circuit impedance na transformer yana nufin through impedance X1 - 2. Idan branch na low-voltage split winding take yi aiki da high-voltage winding, wannan yana nufin half-through operation, da short-circuit impedance yana nufin half-through impedance X1 - 2'. Idan branch na split winding take yi aiki da branch na biyu, wannan yana nufin split operation, da short-circuit impedance yana nufin split impedance X2 - 2'.

2 Abubuwan da ke da Split-Winding Transformers

Don samun aiki mai kyau, an yi quantitative comparison da ordinary double-winding transformers da technical parameters na products masu matara. A maida 2500 kVA split-winding transformer: 37 &plusmn; 2&times;2.5% / 0.36 kV / 0.36 kV, 50 Hz, short-circuit reactance percentage 6.5%, full-through reactance percentage 6.5%, half-through reactance percentage 11.7%, split coefficient < 3.6%.Calculations give:

Full-through reactance: X1 - 2 = X1 + X2 // X2

Half-through reactance: X1 - 2' = X1 + X2   

Per-unit values:

High-voltage side branch reactance:

Low-voltage side branch reactance:

2.1 Reducing Short-Circuit Current

A lokacin da short-circuit yake faru a d1 a Figure 2, short-circuit current yana da uku na components: from the system (high-voltage side, with non-decaying periodic components), non-fault branch I''p1, and fault branch I''p2. For the low-voltage circuit breaker on the fault branch, its breaking capacity considers the sum of system and non-fault branch currents. With a split-winding transformer:

System-supplied short-circuit current:

Inverter-type distributed power short-circuit current is 2&ndash;4 times the rated current (duration 1.2&ndash;5 ms, 0.06&ndash;0.25 cycles), and the non-fault branch current is ~4 kA. For an ordinary double-winding transformer (for comparability, assume uk% = 6.5, same as the full-through reactance percentage of the split-winding transformer uk1 - 2%:

The per-unit reactance is:

The system-supplied short-circuit current is:

with additional contributions from non-fault branches. Clearly, using split-winding transformers for expanded-unit wiring significantly reduces the breaking-capacity requirement for low-voltage side branch circuit breakers.

Assume that the parameters of the parallel modules are completely the same and the MPPT control parameters of the inverters are the same. Then, C1 = C2 = C, L1 = L2 = L, and the inductor current of each inverter is:

It can be seen that the inductor current of each inverter consists of two parts: The first is the load current, which is the same for both inverters; the second is the circulating current, related to the amplitude, phase, and frequency differences of the inverters&rsquo; output voltages.

Currently, the main control logic for inverters in PV power stations is Maximum Power Point Tracking (MPPT). Solar cell modules have internal and external resistances. When MPPT control makes these resistances equal at a certain moment, the PV module operates at the maximum power point. Taking Figure 3 as an example, the active power P1 and reactive power Q1 output by Inverter 1 are:

2.3 Maintaining Voltage of Non-Fault Branches

Taking Figures 2 and 3 as examples, photovoltaic power stations usually adopt a centralized inverter-transformer layout, and the cable impedance between the inverter and transformer is negligible. With an ordinary double-winding transformer, the voltage of the non-fault branch drops to zero potential. In this case, relay protection is generally used to delay the operation of the non-fault branch circuit breaker to reduce the fault removal range. However, this method may not meet the protection requirements for photovoltaic power stations. If the removal time of the fault branch exceeds the low-voltage ride-through capability of the inverter, the non-fault branch will be forced to disconnect from the grid, increasing the risk of expanding the fault range.

With a split-winding transformer, due to the existence of split impedance, the short-circuit current provided by the system is equivalent to operating in the half-through mode of the split-winding transformer. The short-circuit current supplied by the non-fault branch inverter is equivalent to the split operation mode of the split-winding transformer. At the moment of short-circuit, the output voltage U''2 of the non-fault branch inverter is I''s &times; X'2+ I''p2&times; (X''2 + X'''2). Since the high-voltage side is an infinite system, according to the previous discussion, I''s is much larger than I''p2. Therefore, the first part I''s &times; X'2 does not decay and is larger than the second part I''p2 &times; (X''2 + X'''2).

Calculations show that U''s > I''s &times; X'2 = 185 V. The output voltage of the non-fault branch inverter can be maintained at least at about 0.5Un. According to the low-voltage ride-through requirements of the photovoltaic power

station, the removal time is greater than 1 s (50 cycles). Thus, the expanded-unit wiring with split-winding transformers can reliably meet the requirement that the non-fault branch does not disconnect from the grid within the removal time of the fault branch circuit breaker.

3 Conclusion

Split-winding transformers are widely used in engineering, especially suitable for grid-connected photovoltaic power stations. As discussed above, their advantages mainly lie in reducing short-circuit current, restricting operating circulating current, and maintaining the voltage of non-fault branches. Based on engineering design examples, this paper theoretically analyzes their application advantages in photovoltaic power stations, providing certain guiding significance for the selection of wiring forms and equipment in grid-connected photovoltaic power station projects.

Ba da kyau kuma kara mai rubutu!
Tambayar Da Yawanci
3D Wound-Core Transformer: Tarihin Ayyuka na Iyakokin Kirkiro Rike
3D Wound-Core Transformer: Tarihin Ayyuka na Iyakokin Kirkiro Rike
Muhimmanci Bincike da Turukanin Nuna na Masu Farko Kasance kadan, musamman kasance kadan da ba a kan wani abu; yana nuna aiki a cikin inganci. Kasance kwaikwayo, musamman a lokacin da ya fi sani; don in tabbatar da masu shirya tattalin arziki. Talakawa mai karfi don in hada zafi na masu kasa zuwa gaba, wanda ke samun aiki a cikin karfin baka. Masu alama a cikin takar, wanda ke samu aiki a cikin hanyar kudan; ya kawo muhimmanci a kan tsarin masu kasa don in yi amfani da shi a kan yanayin. Yana iy
Echo
10/20/2025
Kaduna Dabara Da Digital MV Circuit Breakers
Kaduna Dabara Da Digital MV Circuit Breakers
Amince Wata Daga Samun Digitized Medium-Voltage Switchgear da Circuit Breakers"Wata" - wannan wani kalma da ba ake so in fuskantar ma'aikatar gida bai, musamman idan ya shafi da haka. Na gode da circuit breakers (MV) na farko da switchgear, za ku iya amfani da tushen digital don kare masu shiga da zama mai kyau.Switchgear da circuit breakers na MV na zamani suna da sensors digital da suka fito da su, wanda ke taimaka da kawo abubuwan da za a duba game da manyan abubuwa. Wannan yana ba ku karfin
Echo
10/18/2025
Wani Maqala Don Fahimtar Yadda Makashe A Cikin Kirkiro Vakuumi Ne
Wani Maqala Don Fahimtar Yadda Makashe A Cikin Kirkiro Vakuumi Ne
Tsunukan Gwamnati na Tafin Maimaita: Tashin Tafi, Tashin Tafin Maimaita, da Jirgin YawanciYanayi 1: Tafin Daga Bari (Tashin Tafi, 0-3 mm)Limadda tana bayarwa cewa yanayin tafin daga bari (0-3 mm) yana da muhimmanci sosai wajen tushen tafin maimaita gwamnatin tsunukan. A farkon tafin daga bari, takambari tafi yana zama daga hali na sauki zuwa hali na tafina - ya kamata wannan tashin zama kadan da kyau saboda haka yana ba da tushen tafin maimaita.Dalilu uku suna iya taka tashin daga hali na sauki
Echo
10/16/2025
Mafiya da Tattalin Aiki na Kirkiro Masu Sauci a Tsakiyar Karamin Kirkiro Masu Sauci Da Rike Kadan
Mafiya da Tattalin Aiki na Kirkiro Masu Sauci a Tsakiyar Karamin Kirkiro Masu Sauci Da Rike Kadan
Maimaito da Amfani da Maimaito na Tsakiyar Karamin Rike na Zafiya: Muhimman Matafi, Amfani, da MuhimmanciSaboda darajinsa na rike da zafiya, maimaito na tsakiyar karamin rike na zafiya suna da fara da yawa da dama cewa mai tsarki da suka. A kan wannan farar da yawa, tattalin magana mai tsayi (TMF) ya fi shahara da tattalin magana mai ci (AMF) don gudanar da amfani da karamin rike mai yawa. Idan an gudanar da amfani da karamin rike masu yawa, tsakiyar zafiya yana haifi don koyar da yanayi mai yaw
Echo
10/16/2025
Aika tambaya
Kwamfuta
Samun IEE Business Application
Yi amfani da IEE-Business app don samun abubuwan aikin, samun halayyin, haɗi da malamai, kuma kai tsauraran takaiddun kasoshin duka lokaci, duka wurin—dole bai karfin takamaltar hulɗin ku na alintakargida da kasuwanci.