1. Bayani
Yadda yake da PT dabiya da fuse mai karamin sauran jama'a a cikin combined transformers ya zama wani abu mai zurfi da ke taimakawa wadannan tsarin masana'antu na noma ta hanyar kula da kuma tsaftace gwamnatiyar gida. Wannan littafi yana neman matsalolin da suka faruwa a kan PT da kuma fuse a cikin combined transformer na 35 kV, yana bincika sabbin masu maitaccen bayanai, yana ba da kayan aiki, da kuma yana sake tabbatar da adadin kilowattota da aka fito a cikin al'amari. Wannan yana taimaka wajen ya kawo kammalin gwamnatiyar gida da kuma inganta masu wasu.
1.1 Bayani game da Combined Transformers
A cikin tsarin masana'antu, combined transformers suna da muhimmanci a cikin al'amari da kuma gwamnatiyar gida. Suna samun shugaban voltage transformers (PT) da kuma current transformers, suna amfani da farkon tsari a cikin primary da secondary coils don in tabbatar da primary - side currents da voltages da suke so kuɗi zuwa currents da voltages masu kyau don secondary instruments da kuma relay protection. Amma, suna taimaka waɗanda suke yi aiki a cikin secondary side don hankali masu aiki da kuma ƙasashen kwallo.
2. Masu Dabba da Take da Faults a Cikin Combined Transformers
Saboda haka, PT a cikin combined transformer yana da muhimmanci a cikin tsarin masana'antu, yana da shugaba kan nan da za a yi aiki a cikin al'amari/daidaitaccen bayanai. Idan PT ya zama da maƙashe ko high - voltage fuse ya dabiya, akwai masu dabba kamar:
Idan a yi aiki, combined transformers suna da maƙashe da dabiya da fuse mai karamin sauran jama'a. Sabbin masu maitaccen include:
4. Case Analysis
4.1 Basic User Information
A ranar 23 ga Agusta, 2021, an samu maƙashe da PT burnout fault a cikin combined transformer na 35 kV user, wanda yake ƙare al'amari mai yawan tabbataccen. A shekarar da ya ɗauke, wannan combined transformer ya samu 3 faults. Idan an samu karfin Janairu, 2021, user ya samu power supply daga 35 kV Shazi Substation da al'amari mai tsarki. Ba ƙanan Agusta, 2021, an yi ƙaramin supply zuwa 35 kV outgoing line na 110 kV Zhoujiaba Substation (Zhouwan Line #353 da Zhouri Line #354 dual - circuit power supply). Total line length yana da yarda 1.5 km. 35 kV side yana da ground via arc - suppression coil. Metering points suna da shugaban 2 - circuit 35 kV outgoing lines na 110 kV Zhoujiaba Substation. Primary wiring yana nuna a Figure 1.
4.2 Metering Points and Fault Timeline
Duk metering points suna amfani da 35 kV combined transformers, da three - phase three - wire connection da V/V connection don voltage transformers. Daga cikinsu:
Fault Timeline:
23 ga Agusta, 2021: First PT burnout, an ƙara da products na Henan Xinyang Hutong Electric Co., Ltd.;
4 ga Maris, 2022: PT burns out again, an ƙara da combined transformers na Jiangxi Gandi Electric Co., Ltd.;
13 ga Yuni, 2022: C - phase high - voltage fuse melts, voltage loss;
21 ga Satumba, 2022: A - phase high - voltage fuse melts, voltage loss again.
4.3 Fault Analysis
A lokacin da fault ya faru, user load yana da kyau, secondary wiring yana da tsarki, da kuma babu short circuit. Ba a yi test:
A ƙare da fault phenomena da common causes, ana neman sabbin maitaccen za a ƙare ferromagnetic resonance overvoltage, da specific triggering scenarios:
4.4 Solutions
Ba a yi analysis da sabbin masu maitaccen, ana ƙara da measures:
Implementation Effect: Ba a ƙara da measures, combined transformer yana yi aiki da tsarki, babu PT burnout ko fuse melting faults.
4.5 Electricity Quantity Reconciliation Calculation
Tushen al'amari na electric energy yana da muhimmanci ga economic interests na both power supply and consumption parties. Faults ƙara reconciliation. Wannan littafi yana ƙara third fault a cikin example da kuma amfani da correction coefficient method don in ƙara calculation:
Principle: Compare active power during correct metering and incorrect metering don in neman correction coefficient k, da kuma ƙara reconciliation electricity quantity \(\Delta W\). Assuming three - phase load balance, formula na correction coefficient k ce:
(1) Interpretation of Correction Coefficient k
Idan k = 1, energy meter yana neman tsarki. Idan 0 < k < 1, energy meter yana over - register electricity, da kuma reconciliation electricity yana ƙara refund to the customer. Idan k < 0, energy meter yana reverse, da kuma customer yana ƙara reconciliation electricity. , active power during correct metering yana da tsayi da incorrect metering. Energy meter yana under - register electricity during the fault, da kuma customer yana ƙara reconciliation electricity. Idan
(2) User - related Metering Parameters
User's receiving capacity yana da 2500 kVA, da kuma metering method yana da high - supply high - metering (metered by a high - voltage combined metering box). Voltage ratio yana da 35000 V/100 V, da kuma current ratio yana da 50 A/5 A. Comprehensive metering multiplier yana da 3500. Energy meter capacity yana da 3×100 V/3×1.5 - 6 A, da accuracy da 0.5S.
User's third fault yana faru a 13 ga Yuni, 2022, idan phase C yana lose voltage. Power yana ƙara a ƙanan 8:00 a 4 ga Agusta, 2022. Time - of - use electricity pricing yana faru a 1 ga Yuli, 2022. Collected data such as system voltage, power, and power factor yana nuna a Table 1.
Calculation of Reconciliation Electricity Quantity for the First Stage
As can be seen from Table 1, during the period from 13 ga Yuni, 2022 to 30 ga Yuni, 2022, voltage na phase A yana da tsarki, average power factor yana da 0.82, da kuma element angle yana da 34°(L). Then power factor angle φ=4°(L).Assuming that the load is balanced, the correction coefficient is:
The calculation of the reconciliation electricity quantity is as follows:
From Formula (2) and Formula (3), it can be seen that 29°(L). Then power factor angle φ=0°.Assuming that the load is balanced, the correction coefficient is: , meaning the electricity is under - measured, and an additional electricity quantity of 15,134 kWh should be recovered.(2) Calculation of Reconciliation Electricity Quantity for the Second Stage.During the period from 1 ga Yuli, 2022 to 4 ga Agusta, 2022, voltage na phase A yana da tsarki, average power factor yana da 0.87, da kuma element angle yana da
The calculation of the reconciliation electricity quantity is as follows:
From Formula (4) and Formula (5), it can be seen that , meaning the electricity is under - measured, and an additional electricity quantity of 51,996 kWh should be recovered.Total reconciliation electricity quantity to be recovered:
5. Conclusion
A cikin aiki, combined transformers suna da maƙashe da dabiya da high - voltage fuses, wanda ke haɓaka kammalin grid. Duk da cewa wadannan issues suna da resonance overvoltage, amma akwai kuma improper equipment design/selection da parameter mismatches.
A lokacin da a yi analysis da faults: Kafin, check for transformer defects and verify high - voltage fuse capacity. Kafin, install proper primary harmonic elimination devices don in ƙara resonance overvoltage. Ba a faru accident, respond promptly and handle correctly don in ƙara escalation and social impacts. Kafin, learn from experience, improve fault - handling skills, and ensure grid safety.