The skid-mounted substation at the Rockwell Energy mine uses an integral steel frame to support medium-voltage switchgear and transformers. It can be moved either by crane lifting or tractor towing, eliminating the need for civil construction or dedicated switchgear rooms.
As the open-pit mining face advances, the substation can be relocated within 1–2 days. Its open-design ensures reliable operation even in dusty environments without any reduction in capacity.

|
Parameter |
Rockwell Energy Mining Area Skid-Mounted Platform |
Standard anchor point |
|
Rated voltage |
Medium voltage: 12/24/35 kV; Low voltage: 400–1000 V |
IEC 62271-200 |
|
Transformer capacity |
Oil-immersed, standard series 0.63–3.5 MVA |
IEC 60076 |
|
Short-circuit level |
25kA–3s (standard specification) |
IEC 62271-100 |
|
Protection level |
IP54 (dust-resistant) |
IEC 60529 |
|
Structural strength |
Lifting/Dragging Dual-Condition Load Calculation Document |
Issued by project |
|
Operating temperature |
-40℃ ~ +50℃ (low-temperature option) |
IEC 60068 |
|
Comparison item |
Fixed substation |
Rockwell Energy Skid-Mounted Mobile Station |
|
Station relocation capability |
Non-transferable |
Lifting or towing, completed in 1–2 days. |
|
Civil engineering |
Architecture + Basics |
Just site leveling (optional subbase) |
|
Power supply radius |
As the working face extends, pressure drops and deterioration worsen. |
Always stay close to the working surface, with stable voltage quality. |
|
Downtime window |
Relocation requires rebuilding (several months). |
Power outage – migration – power restoration, 1–2 days |
|
Dust environment |
Enclosed computer rooms require dust-filter maintenance. |
Open-type IP54, natural air cooling with no capacity reduction. |

|
Project |
Acceptance value |
Standard anchor point |
|
Transformer temperature rise |
Top oil ≤ 60K, winding ≤ 65K |
IEC 60076-2 Table 1 |
|
Protection level |
IP54 tested and verified |
IEC 60529 |
|
Structural load |
Lifting/dragging condition verification passed. |
Project Structural Calculation Document |
|
Voltage Fluctuation (with Optional Compensation) |
Fluctuations and variations meet grid connection requirements. |
IEEE 519 / Local Power Grid |
Enclosure with IP54 protection + positive-pressure dust filtration option; open-style cooling design reduces dust accumulation in enclosed spaces.
The entire process—from power outage, cable removal, relocation, and power restoration—takes 1–2 days. During the station relocation window, the workload on the affected work area will be temporarily supplied by adjacent circuits.
The frame is verified against drag-and-impact loads and a calculation report is provided. Steel cables connect to anchoring points, provide speed-limiting traction, and allow for relocation even on uneven ground.