In modern power grids, particularly in substations of power plants and large industrial parks, the parallel operation of multiple transformers or generators is widely adopted to enhance power supply reliability and energy efficiency. However, this leads to a sharp increase in system short-circuit current levels, often exceeding the rated withstand capacity (e.g., dynamic/thermal withstand current) of existing equipment such as switchgear, circuit breakers, and transformers.
Traditional solutions face significant challenges:
II. Solution: Core Application Value of the Ultra-Fast Current Limiter (FCL)
The Ultra-Fast Current Limiter (FCL) provided in this solution is an intelligent device based on a parallel configuration of a "fast switch" and a "current-limiting fuse." It fundamentally addresses the aforementioned challenges, with its core application value lying in "millisecond-level breaking" and "full lifecycle economic benefits."
Core Application Advantages:
III. Typical Application Scenarios and Solutions
Application Scenario |
Core Problem |
FCL Solution |
1. Bus Sectionalizing / Transformer Parallel Operation |
Parallel operation of multiple transformers causes short-circuit current to far exceed levels under single transformer operation, surpassing the withstand limit of switchgear (e.g., cabinet withstands 2Ik, 4 parallel units can reach 4Ik). |
Install FCL at the bus sectionalizing point (e.g., between sections 1-2 and 3-4). Ensures bus tie during normal operation; rapidly breaks during faults, limiting short-circuit current to an acceptable system level without replacing switchgear. |
2. Bypassing Current Limiting Reactors |
Existing reactors cause high energy consumption and voltage drop during long-term operation. |
Connect the FCL in parallel with the reactor. During normal operation, the FCL conducts, bypassing the reactor for zero loss and zero voltage drop; during a short circuit, the FCL breaks, transferring current to the reactor for limiting. |
3. Grid and Captive Power Source Connection Point |
Commissioning of captive generators within an enterprise can cause short-circuit current at the Point of Common Coupling (PCC) to exceed limits, threatening upstream grid equipment. |
Installing an FCL at the connection point is the only reasonable solution. Directional protection functionality can be added to ensure operation only for grid-side faults, avoiding maloperation. |
4. Power Plant or Large Factory Feeders |
The large short-circuit capacity of auxiliary power systems makes it difficult for outgoing feeder equipment to withstand. |
Install FCLs on feeder circuits at the generator or transformer outlet to provide top-level protection for downstream switchgear, enhancing overall system security. |
IV. Technical Implementation and Selection Guide
Technical Parameter |
Unit |
12kV / 17.5kV System |
24kV System |
36kV / 40.5kV System |
Rated Voltage |
kV |
12 / 17.5 |
24 |
36 / 40.5 |
Rated Current |
A |
1250 - 5000¹ |
2500 - 4000¹ |
1250 - 3000¹ |
Maximum Breaking Capacity |
kA (RMS) |
210 |
210 |
140 |
Note ¹: Forced air cooling is required for rated currents exceeding 2000A. |
V. Summary
The Ultra-Fast Current Limiter (FCL) is not merely a simple alternative device but represents a revolutionary approach to system protection. Through its millisecond-level breaking speed, it redefines the benchmark for short-circuit protection, delivering unprecedented safety and economic benefits to customers. When facing the widespread challenge of excessive short-circuit currents, the FCL provides a top-tier solution that is mature, reliable, and validated by thousands of projects globally. It is a strategic choice for ensuring the future reliability and economical operation of critical power systems.