• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Hydro Power Plant | Construction Working and History of Hydro power plant

electricity-today
Field: Electrical Operations
0
Canada

WechatIMG1769.jpeg

In hydroelectric power station the kinetic energy developed due to gravity in a falling water from higher to lower head is utilised to rotate a turbine to produce electricity. The potential energy stored in the water at upper water level will release as kinetic energy when it falls to the lower water level. This turbine rotates when the following water strikes the turbine blades. To achieve a head difference of water hydroelectric electric power station are generally constructed in hilly areas. In the way of the river in hilly areas, an artificial dam is constructed to create required water head. From this dam water is allowed to fall toward downstream in a controlled way to turbine blades. As a result, the turbine rotates due to the water force applied to its blades and hence the alternator rotates since the turbine shaft is coupled with alternator shaft.
The main advantage of an
electric power plant is that it does not require any fuel. It only requires water head which is naturally available after the construction of the required dam.

No fuel means no fuel cost, no combustion, no generation of flue gases, and no pollution in the atmosphere. Due to the absence of fuel combustion, the hydroelectric power plant itself is very neat and clean. In addition to that, it does not produce any pollution to the atmosphere. Also from constructional point of view, it is simpler than any thermal and nuclear power plant.
The constructional cost of a hydroelectric power plant maybe higher than that of other conventional
thermal power plants because of construction of a huge dam across the flowing river. The engineering cost in addition to the constructional cost is also high in a hydroelectric power plant. Another disadvantage of this plant is that it cannot be constructed anywhere according to the load centres.
So,
long transmission lines are required to transmit the generated power to the load centres.
Thus the transmission cost may be high enough.

In spite of that, the stored water in the dam can also be utilised for irrigation and any other similar purposes. Sometimes by creating such dam in the way of the river, occasional floods in the downstream of the river can be controlled significantly.

hydro power plant
There are only six primary components required to construct a hydroelectric power plant. These are dam, pressure tunnel, surge tank, valve house, penstock, and powerhouse.

The dam is an artificial concrete barrier constructed across the way of the river. The catchment area behind the dam creates a huge water reservoir.
The pressure tunnel takes water from the dam to the valve house.
In the valve house, there are two types of valves available. The first one is main sluicing valve and the second one is an automatic isolating valve. The sluicing valves control the water flowing to the downstream and automatic isolating valves stop the water flow when the electrical load is suddenly thrown off from the plant. Automatic isolating valve is a protecting valve does not play any direct role control the flow of water to the turbine. It only operates during emergency to protect the system from burst out.

The penstock is a steel pipeline of suitable diameter connected between the valve house and powerhouse. The water flows down from upper valve house to lower powerhouse through this penstock only.
In the powerhouse there are water turbines and
alternators with associated step up transformers and switchgear systems to generate and then facilitate transmission of electricity.
At last, we will come to the surge tank. The surge tank is also a protective accessory associated with hydroelectric power plant. It is situated just before the valve house. The height of the tank must be greater than the head of the water stored in the water reservoir behind the dam. This is an open top water tank.

The purpose of this tank is to protect the penstock from bursting out when suddenly turbine refuses to take water. At the entry point of turbines, there are turbine gates control by governors. The governor opens or closes the turbine gates according to the fluctuation of the electrical load. If the electrical load is suddenly thrown off from the plant, the governor closes the turbine gates and water is blocked in the penstock. Sudden stopping of water can cause a serious burst of penstock pipeline. The surge tank absorbs this back pressure by swing the level water in this tank.

Statement: Respect the original, good articles worth sharing, if there is infringement please contact delete.

Give a tip and encourage the author!

Recommended

HECI GCB for Generators – Fast SF6 Circuit Breaker
1.Definition and Function1.1 Role of the Generator Circuit BreakerThe Generator Circuit Breaker (GCB) is a controllable disconnect point located between the generator and the step-up transformer, serving as an interface between the generator and the power grid. Its primary functions include isolating generator-side faults and enabling operational control during generator synchronization and grid connection. The operating principle of a GCB is not significantly different from that of a standard c
01/06/2026
Design Principles for Pole-Mounted Distribution Transformers
Design Principles for Pole-Mounted Distribution Transformers(1) Location and Layout PrinciplesPole-mounted transformer platforms should be located near the load center or close to critical loads, following the principle of “small capacity, multiple locations” to facilitate equipment replacement and maintenance. For residential power supply, three-phase transformers may be installed nearby based on current demand and future growth projections.(2) Capacity Selection for Three-Phase Pole-Mounted Tr
12/25/2025
Transformer Noise Control Solutions for Different Installations
1.Noise Mitigation for Ground-Level Independent Transformer RoomsMitigation Strategy:First, conduct a power-off inspection and maintenance of the transformer, including replacing aged insulating oil, checking and tightening all fasteners, and cleaning dust from the unit.Second, reinforce the transformer foundation or install vibration isolation devices—such as rubber pads or spring isolators—selected based on the severity of vibration.Finally, strengthen sound insulation at weak points of the ro
12/25/2025
Rockwill Passes Single-Phase Ground Fault Test for Smart Feeder Terminal
Rockwill Electric Co., Ltd. has successfully passed the real-scenario single-phase-to-ground fault test conducted by the Wenzhou of China Electric Power Research Institute for its DA-F200-302 hood-type feeder terminal and integrated primary-secondary pole-mounted circuit breakers—ZW20-12/T630-20 and ZW68-12/T630-20—receiving an official qualified test report. This achievement marks Rockwill Electric as a leader in single-phase ground fault detection technology within distribution networks.The DA
12/25/2025
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.