• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Induced Voltage Test Issues and Solutions for HKSSPZ-6300/110 Arc Furnace Transformer

Oliver Watts
Field: Inspection and testing
China

A HKSSPZ-6300/110 electric arc furnace transformer has the following basic parameters:

Rated capacity S = 6300 kVA, primary voltage U₁ = 110 kV, secondary voltage U₂ = 110–160 V, vector group YNd11, with both low-voltage winding ends (start and finish) brought out, and equipped with 13-step on-load tap changing. Insulation levels: HV/HV neutral/LV, LI480AC200 / LI325AC140 / AC5.

The transformer uses a dual-core series voltage regulation design, with an "8"-shaped low-voltage winding configuration. The schematic for the induced voltage test is shown in Figure 1.

Test conditions: tap changer set at position 13; 10 kV applied to tertiary windings Am, Bm, Cm; with K = 2, only phase A is illustrated (phases B and C are identical). Calculated values: UZA = K × 10 = 20 kV, UG₀ = K × 110 / √3 ≈ 63.509 kV, UGA = 3 × 63.509 = 190.5 kV (95% of rated), UAB = 190.5 kV, frequency = 200 Hz.

After completing the test connections per the diagram, the induced voltage test began. When UZA was raised to 4000–5000 V, distinct "crackling" corona discharge sounds were observed near the low-voltage terminal bushings, accompanied by the odor of ozone. Simultaneously, the partial discharge (PD) detector indicated PD levels exceeding 1400 pC. However, the measured voltage between low-voltage terminals remained correct. Initially, we suspected potential issues with the low-voltage terminal material or the effect of the 200 Hz test frequency on the resin terminal. In a second test using a 50 Hz power source at the same voltage (4000–5000 V), the same phenomena were observed, thereby ruling out the influence of the 200 Hz frequency.

We then carefully reviewed the test circuit diagram and actual connections. It was noted that the low-voltage winding ends (start and finish) are both externally brought out and are normally connected externally into delta or star configuration when connected to the furnace. During the induced voltage test, however, the low-voltage terminals were neither connected in star nor in delta, nor grounded—leaving them in a floating potential state. Could this floating potential be the cause?

To test this hypothesis, we temporarily connected the x, y, and z terminals together and reliably grounded them before re-running the test. The aforementioned discharge phenomena disappeared completely. When the voltage was increased to 1.5 times the level, PD was only about 20 pC. The test voltage was further increased to 2 times, and the transformer successfully passed the induced voltage withstand test.

Conclusion: For this type of dual-core series voltage-regulated furnace transformer with both low-voltage winding ends brought out, although the voltage between terminals (e.g., a and x) is low, the absence of a reliable ground connection can create a floating potential, leading to the observed partial discharge. Therefore, during induced voltage testing, the x, y, and z terminals should be shorted together and reliably grounded to eliminate such anomalies.

Give a tip and encourage the author!

Recommended

Transformer Noise Control Solutions for Different Installations
1.Noise Mitigation for Ground-Level Independent Transformer RoomsMitigation Strategy:First, conduct a power-off inspection and maintenance of the transformer, including replacing aged insulating oil, checking and tightening all fasteners, and cleaning dust from the unit.Second, reinforce the transformer foundation or install vibration isolation devices—such as rubber pads or spring isolators—selected based on the severity of vibration.Finally, strengthen sound insulation at weak points of the ro
12/25/2025
What Are the Basic Requirements for Outdoor Installation of Distribution Transformers?
1. General Requirements for Pole-Mounted Transformer Platforms Location Selection:Pole-mounted transformers should be installed near the load center to minimize power losses and voltage drop in low-voltage distribution lines. Typically, they are placed close to facilities with high electricity demand, while ensuring that the voltage drop at the farthest connected equipment remains within allowable limits. The installation site should allow easy access for maintenance and avoid complex pole struc
12/25/2025
Regulations for Primary Wiring of Distribution Transformers
The primary wiring of transformers shall comply with the following regulations: Supports and Cable Protection Conduits: The construction of supports and cable protection conduits for transformer incoming and outgoing lines shall conform to design document requirements. Supports must be firmly installed with elevation and horizontal deviations within ±5mm. Both supports and protection conduits shall have reliable grounding connections. Rectangular Busbar Bending: When rectangular busbars are used
12/23/2025
Power transformers Insulation Resistance & Dielectric Loss Analysis
1 IntroductionPower transformers are among the most critical equipment in power systems, and it is essential to maximize prevention and minimize the occurrence of transformer failures and accidents. Insulation failures of various types account for more than 85% of all transformer accidents. Therefore, to ensure safe transformer operation, regular insulation testing of transformers is necessary to detect insulation defects in advance and promptly address potential accident hazards. Throughout my
12/22/2025
Send inquiry
+86
Click to upload file

IEE Business will not sell or share your personal information.

Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.