What are the principles of forced re-energization of transmission lines?

Learn the 6 key principles of forced re-energization of transmission lines that ensure grid stability and safety. Get the complete guide now to handle faults effectively.

Edwiin
Field: Power switch
10Year<
China
Add us on Google

Principles of Forced Re-energization of Transmission Lines

Regulations for Forced Re-energization of Transmission Lines

  • Correctly select the forced re-energization end of the line. If necessary, change the connection configuration before forced re-energization, taking into account the reduction of short-circuit capacity and its impact on grid stability.

  • There must be a transformer with its neutral point directly grounded on the busbar at the forced re-energization end.

  • Pay attention to the impact of forced re-energization on the transient stability of adjacent lines. If necessary, first reduce the load on all lines and units within the dynamic stability range before performing forced re-energization.

  • When a line trips or fails to reclose, accompanied by obvious system oscillation, immediate forced re-energization should not be performed. The oscillation must be checked and eliminated before considering whether to perform forced re-energization.

  • The circuit breaker for forced re-energization and its auxiliary equipment must be in good condition, and protection must be complete and functional.

  • During forced re-energization, busbar differential protection should be selectively put into operation and have backup protection for the connection configuration, ensuring that a failure of the circuit breaker to trip will not result in a complete outage of both busbars. When only one busbar is in operation, forced re-energization of lines should be avoided as much as possible.

Principles of forced re-energization of transmission lines.jpg

The Following Cases Prohibit Forced Re-energization After a Line Trip

  • Standby lines in an unloaded charging state;

  • Lines under trial operation;

  • After a line trip, if the load has already been transferred to other lines via automatic backup power switching, and power supply is unaffected;

  • Cable lines;

  • Lines where live-line work is being performed;

  • Line-transformer group circuit breakers that trip and fail to reclose;

  • When operating personnel have already observed obvious fault phenomena;

  • Lines where the circuit breaker has defects or insufficient interrupting capacity;

  • Lines known to have serious defects (e.g., submerged by water, severely tilted towers, severely broken conductor strands, etc.).

In the Following Cases, Forced Re-energization Must Be Performed Only After Contacting and Obtaining Permission from Dispatch

  • Busbar fault, where no obvious fault point is found after inspection;

  • Ring network line fault trip;

  • One circuit of a double-circuit line trips due to fault;

  • Lines that may cause out-of-phase closing;

  • Transformer backup protection trip.

Give a tip and encourage the author!

Comments

Share your question or perspective
WhatsApp
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.
Login
or continue with
New here?
Register