• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


How to analyze and handle typical faults of box-type transformers in photovoltaic power stations?

Felix Spark
Felix Spark
Field: Failure and maintenance
China

To effectively analyze the fault conditions of the pad - mounted transformer, this paper selects a double - secondary - winding pad - mounted transformer (ZGS11 - Z.T - 1000/38.5), which can be connected to 2 centralized inverters. The structure of its power generation unit is shown in Figure 1. This pad - mounted transformer adopts a three - phase three - limb structure design, with 2 windings on the low - voltage side. The overall structure is divided into three major parts: the high - voltage chamber, the low - voltage chamber, and the oil tank. In actual operation, common faults of the pad - mounted transformer include low - voltage winding grounding faults, high - voltage side open - circuit faults, and high - and low - voltage side short - circuit faults. A detailed analysis will be carried out below.

1 Typical Faults of Pad - Mounted Transformers in Photovoltaic Power Stations
1.1 Low - Voltage Winding Ground Faults

Some photovoltaic pad - mounted transformers lack a neutral - point lead. A single - phase ground fault on the low - voltage side damages insulation, with fault manifestations varying by the centralized inverter’s state.

In low - light conditions, the power - generation unit stops, and the inverter disconnects from the grid, drawing power via the transformer. A ground fault here causes the inverter (still at normal voltage) to run, but rising phase voltage damages low - voltage - side insulation long - term, possibly leading to multi - point grounding.

In sufficient light, the inverter switches to grid - connected mode. Its ungrounded neutral makes single - phase ground faults hard to detect—no ground current, unchanged line voltage. The control system, monitoring line voltage, misses the anomaly. The inverter runs but with reduced efficiency, hurting photovoltaic benefits.

1.2 High - Voltage Side Open - Circuit Faults

Open - circuit faults split into high - voltage lead and winding disconnection. A high - voltage lead disconnection trips the inverter and shuts down the generator set. Testing reveals abnormal noises, smells, and infinite resistance in the fault - phase winding (normal for others), indicating the fault.

For high - voltage winding disconnection, DC resistance is twice the normal inter - phase value (not infinite). On the high - voltage side, fault and adjacent phases’ line voltage drops to 50% of rated; on the low - voltage side, the corresponding phase’s line voltage falls (not to zero, due to induced voltage).

1.3 High - and Low - Voltage Side Short - Circuit Faults

Inter - phase short - circuit faults often occur, tripping the corresponding circuit breaker and causing noises, oil spraying, and smells.

To handle faults: first, grasp the situation from protection actions, then move the transformer to maintenance, take safety measures, and disassemble the unit to check. Initial faults may be inter - phase; if worsening, winding damage and core replacement follow.

An actual fault started as a low - voltage inter - phase short circuit, leading to high - low winding breakdown under impulse discharge. This caused severe discharge, core damage, oil tank issues. The root cause was inherent insulation weaknesses.

2 Fault Prevention for Pad - Mounted Transformers in Photovoltaic Power Stations
2.1 Insulation Monitoring Devices

The monitored transformer uses a three - phase three - wire star connection. Single - phase ground faults (no neutral point) barely change line voltage, making detection hard and risking fault worsening. Add an insulation monitoring device to alarm and enable timely faulty unit disassembly. Use a neutral - point - connected inverter (preferably yyn11 type) for better ground fault handling.

2.2 Routine Insulation Monitoring

Strict regular inspections (focus on insulation) detect defects early, reducing internal equipment failures. Increase pad - mounted transformer insulation monitoring frequency in operation and maintenance.

2.3 Oil Sample Testing

Internal insulation defects cause failures. Regular oil sample testing catches heat/discharge - related component changes during deterioration. Strengthen oil temperature monitoring and testing to avoid overheating - induced faults.

2.4 Technical Selection in Construction

Ensure long - term safety by doing good site selection, electrical design, and equipment selection in the construction phase—guaranteeing product quality and compliance with station design.

3 Conclusion

This paper analyzes common ground, disconnection, and short - circuit faults of a typical pad - mounted transformer in photovoltaic stations. To avoid faults, strengthen routine insulation monitoring, emphasize oil tank testing, and add insulation devices when possible—ensuring safe operation.

Give a tip and encourage the author!
Recommended
10kV RMU Common Faults & Solutions Guide
10kV RMU Common Faults & Solutions Guide
Application Issues and Handling Measures for 10kV Ring Main Units (RMUs)The 10kV ring main unit (RMU) is a common electrical distribution device in urban power distribution networks, primarily used for medium-voltage power supply and distribution. During actual operation, various issues may arise. Below are common problems and corresponding corrective measures.I. Electrical Faults Internal Short Circuit or Poor WiringA short circuit or loose connection inside the RMU can lead to abnormal operati
Echo
10/20/2025
High-Voltage Circuit Breaker Types & Fault Guide
High-Voltage Circuit Breaker Types & Fault Guide
High-Voltage Circuit Breakers: Classification and Fault DiagnosisHigh-voltage circuit breakers are critical protective devices in power systems. They rapidly interrupt current when a fault occurs, preventing damage to equipment from overloads or short circuits. However, due to long-term operation and other factors, circuit breakers may develop faults that require timely diagnosis and troubleshooting.I. Classification of High-Voltage Circuit Breakers1. By Installation Location: Indoor-type: Insta
Felix Spark
10/20/2025
10 Prohibitions for Transformer Installation and Operation!
10 Prohibitions for Transformer Installation and Operation!
10 Prohibitions for Transformer Installation and Operation! Never install the transformer too far away—avoid placing it in remote mountains or wilderness. Excessive distance not only wastes cables and increases line losses, but also makes management and maintenance difficult. Never choose transformer capacity arbitrarily. Selecting the right capacity is essential. If the capacity is too small, the transformer may be overloaded and easily damaged—overloading beyond 30% should not exceed two hours
James
10/20/2025
How to Maintain Dry-Type Transformers Safely?
How to Maintain Dry-Type Transformers Safely?
Maintenance Procedures for Dry-Type Transformers Put the standby transformer into operation, open the low-voltage side circuit breaker of the transformer to be maintained, remove the control power fuse, and hang a "DO NOT CLOSE" sign on the switch handle. Open the high-voltage side circuit breaker of the transformer under maintenance, close the grounding switch, fully discharge the transformer, lock the high-voltage cabinet, and hang a "DO NOT CLOSE" sign on the switch handle. For dry-type trans
Felix Spark
10/20/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.