Vziman Oil-Immersed Transformer Leakage Management: Complete Response and Control Guide

Vziman oil-immersed transformer leak management: complete response and control guide for reliable power system operation.

Vziman
Field: Manufacturing
10Year<
China
Add us on Google
Oil leakage in oil-immersed transformers is a major risk affecting equipment reliability and environmental compliance. Drawing on years of operational experience and industry practice, Rockwill has developed a complete management system covering emergency response through long-term prevention.
iee-business

1. Leakage Classification and Emergency Response

1.1 Leakage Rating and Response

Level Characteristics Response
Seepage Oil stain only, no dripping Place drip tray; continuously monitor oil level, temperature, and Buchholz alarm; no immediate shutdown required
Moderate leakage Continuous dripping Transfer non-critical loads within the substation; prepare for oil top-up; schedule shutdown for repair
Severe gushing Heavy oil loss Immediately isolate HV/LV switches, earth and tag the equipment; clear surrounding combustibles; start oil recovery; strictly prohibit any live or pressurized operation

iee-business

Oil Level Abnormality Fault Site Example

1.2 Oil Spill Containment

Use absorbent pads and sealed drums to collect leaked insulating oil. If soil is contaminated, excavate contaminated soil in layers, seal and store it, and dispose of as hazardous waste in accordance with local regulations.

1.3 Oil Level and Equipment Monitoring

Do not continue operation if the conservator oil level falls below the minimum mark. Monitor the Buchholz relay for both gas accumulation (alarm) and oil surge (trip) conditions - if leakage is accompanied by a Buchholz alarm or trip, shut down immediately to prevent winding moisture ingress and consequent insulation failure.

iee-business

1.4 Live Temporary Sealing (Seepage Only)

Clean and dry the leak area, then apply an oil-resistant polymer sealing compound for temporary containment. This measure is a short-term solution only; permanent repair must be carried out during the next planned outage.

2. Permanent Repair by Leak Location

2.1 Flange, Tank Rim, and Radiator Flange Seals (Most Common)

Causes: Aging nitrile rubber (NBR) gaskets, corroded or distorted flange surfaces, uneven bolt tightening, abnormal gasket compression.

Remedial steps:

  • De-energize and drain local oil level; disassemble the flange.
  • Sand the corroded and uneven flange surfaces; degrease thoroughly with cleaning solvent.
  • Replace with OEM oil-resistant NBR gaskets (fluororubber/FKM for high-temperature service); control compression to one-third of the gasket thickness.
  • Tighten bolts evenly in a diagonal sequence; apply oil-resistant sealant to the flange gap as secondary protection.
  • Allow 24 hours settling with no visible leakage before refilling and recommissioning.

2.2 Tank Weld Defects, Shell Porosity, and Radiator Tube Leakage

Type Treatment
Small pinholes / micro-cracks (oil layer thickness above the leak point >= 200 mm) Intermittent tack welding in oil using low current and fast welding to avoid igniting oil vapor (this operation must be performed by a certified welder; in-oil welding carries a risk of combustion and explosion)
Thin-wall radiator tube leak Close radiator isolation butterfly valve, drain oil; repair with composite epoxy wrapping or replace the radiator assembly
Large weld seam fracture Drain oil below the leak point, grind a weld groove, then full-seam weld; perform nitrogen pressure leak test after welding

 2.3 Bushing Base and Tap Changer Oil Compartment Leakage

  • Bushing flange: Replace sealing ring, tighten flange bolts evenly, wrap the base with oil-resistant anti-corrosion composite material.
  • Tap changer: Adjust the oil level difference between the main conservator and the tap-changer conservator to balance oil pressure; if the seal has failed, lift the core to replace the dedicated oil-resistant seal, then re-test insulation resistance.

2.4 Drain Valve, Sampling Butterfly Valve, and Breather Connection Leakage

  • Valve stem seepage: Tighten the stem gland and replenish packing material.
  • Aging valve body with internal leakage: Replace with a double-seal vacuum butterfly valve of the same specification; do not repair old valves.
  • Breather connection: Replace aged rubber connecting hose; seal threaded joints with oil-resistant PTFE tape.

2.5 Conservator and Oil Gauge Leakage

Repair conservator weld seams by re-welding. If the glass oil gauge seal ring has aged, replace the complete oil gauge assembly; avoid applying stress to the glass during installation.

iee-business

3. Post-Repair Verification and Maintenance Testing

3.1 Oil Pressure Leak Test

The leak test may be performed using the 30 kPa air pressure method: for transformers >= 20 MVA / 66 kV, apply 30 kPa air pressure and maintain for >= 24 hours. Pressure fluctuation must remain above 90 % of the set value throughout, with no oil traces at any location. Alternatively, refer to the locally applicable IEC standard method. If using the leak rate detection method, the measurement point vacuum shall be <= 200 Pa.

Note: Testing should be avoided when humidity > 80 %, during rain/snow/fog, or during periods of rapid ambient temperature change.

3.2 Insulating Oil Sampling and Analysis

After oil top-up or oil drainage repair, test the insulating oil for dielectric breakdown voltage, moisture content, acidity, and dissolved gas analysis (DGA). For weld repairs, pay special attention to acetylene content to rule out internal overheating.

3.3 Electrical Preventive Tests

Measure winding insulation resistance and polarization index. For earthing transformers, additionally re-test zero-sequence impedance to confirm the zig-zag winding structure was not damaged during repair.

3.4 Post-Commissioning Inspection

For the first 72 hours after commissioning, inspect all seal points twice daily, record oil level and temperature rise, and confirm no re-leakage.

iee-business

 

4. Long-Term Prevention and Root-Cause Management

4.1 Periodic Seal Replacement

For outdoor oil-immersed earthing transformers, replace all rubber seals on flanges and valves every 3-5 years; reduce to 3 years in coastal salt-spray environments.

4.2 Periodic Bolt Re-Tightening

During each seasonal temperature transition (winter-summer), re-tighten all tank flange bolts in a diagonal sequence to compensate for thermal expansion and contraction.

4.3 Oil Temperature and Quality Control

  • Avoid prolonged overload operation of earthing transformers - elevated temperature accelerates oil expansion and gasket aging.
  • Clean radiator fins regularly to maintain heat dissipation efficiency.
  • Monitor T501 antioxidant content in the oil; replenish when it falls below 0.15 %.
  • Monitor moisture content in oil (attention value: 15 mg/L) to prevent reduction of dielectric breakdown strength.

4.4 Corrosion Protection and Mechanical Stress Management

  • Periodically re-coat the tank and flanges with zinc-rich epoxy anti-corrosion paint to prevent rust pitting and leakage.
  • Long-term vibration can loosen fasteners. For fatigue-prone components such as cooling system bellows, verify whether the number of cycles has reached the design limit (e.g., 2x10^5 cycles); if necessary, install a rigid support or adopt a direct connection fixing method.

4.5 Incident Review and Traceability

Maintain a leakage defect log. Within 30 days of any leakage incident, complete a root-cause review analyzing:

  • Seal material aging (excessive compression set of NBR)
  • Assembly process defects (flange flatness > 0.1 mm/m)
  • Abnormal operating conditions (prolonged overload causing high hot-spot temperature)

Eliminate similar risks at the source and continuously optimize maintenance strategy.

Edited From:Echo

Give a tip and encourage the author!

Comments

Share your question or perspective
WhatsApp
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.
Login
or continue with
New here?
Register