Commissioning Test Procedures for Oil-Immersed Power Transformers
Transformer Commissioning Tests Procedures 1. Non-Porcelain Bushing Tests 1.1 Insulation Resistance Suspend the bushing vertically using a crane or support frame. Measure the insulation resistance between the terminal and the tap/flange using a 2500V insulation resistance meter. The measured values