• Product
  • Suppliers
  • Manufacturers
  • Solutions
  • Free tools
  • Knowledges
  • Experts
  • Communities
Search


Optimisation SF6 handling procedures during on-site testing and commissioning for GIS

Edwiin
Field: Power switch
China

Gas Compartment Design and Optimization

Pre-filled SF6 Gas Compartments

Gas compartments are pre-filled with sulfur hexafluoride (SF6) at a pressure slightly above atmospheric pressure for transportation. This ensures that the equipment remains stable during transit and reduces the workload required for on-site installation.

Optimization to Minimize SF6 Usage

Gas compartments are optimized to use the minimum amount of SF6 necessary for a given functionality. Since the lowest achievable SF6 recovery pressure is defined, the mass of SF6 released into the atmosphere is directly proportional to the size of the gas compartment. Through this optimization, the usage of SF6 can be minimized, thereby reducing environmental impact.

Use of Cable Plugs for Connecting High-Voltage Cables

Cable plugs are used to connect high-voltage cables, eliminating the need for complete SF6 recovery or opening the gas compartment when connecting the cables to the GIS. The cable compartment includes a socket, and the cables are simply plugged in. This method simplifies the connection process while maintaining the system's seal and safety.

Utilizing Power Voltage Transformers (VT) for High-Voltage Testing

During high-voltage testing, power voltage transformers (VT) can energize from the low-voltage side, thus avoiding the need to handle SF6 to connect the high-voltage source for testing. After the high-voltage test, the power VT can continue to function as a standard instrument transformer. This approach not only enhances testing efficiency but also reduces the need for SF6 handling.

Use of Bushing Connections for High-Voltage Testing

Bushing connections can be used to connect the high-voltage source for testing without the need to handle SF6. However, this method may introduce some limitations related to on-site partial discharge tests. Despite these limitations, it still provides a convenient and environmentally friendly way to perform high-voltage tests.

Give a tip and encourage the author!

Recommended

Rockwill Powers Cambodia’s Battambang Solar-Storage Project
The Battambang Conch PV + Energy Storage Power Station in Cambodia has successfully completed its grid-connected trial operation. The project utilized medium-voltage switchgear supplied by Rockwill Intelligent Electric Co., Ltd. Despite numerous challenges—including an extremely tight delivery schedule—Rockwill Intelligent delivered high-quality products and exceptional service throughout project execution, earning consistent praise from the client.Located in Battambang, Cambodia, the Battambang
12/24/2025
Classification of Equipment Defects for Relay Protection and Safety Automatic Devices in Substations
In daily operations, various equipment defects are inevitably encountered. Whether maintenance personnel, operation and maintenance staff, or specialized management personnel, all must understand the defect classification system and adopt appropriate measures according to different situations.According to Q/GDW 11024-2013 "Operation and Management Guide for Relay Protection and Safety Automatic Devices in Smart Substations," equipment defects are classified into three levels based on severity an
12/15/2025
Under What Conditions Will the Line Circuit Breaker Auto-Reclosing Signal Be Locked Out?
The line circuit breaker auto-reclosing signal will be locked out if any of the following conditions occur:(1) Low SF6 gas pressure in circuit breaker chamber at 0.5MPa(2) Insufficient energy storage in circuit breaker operating mechanism or low oil pressure at 30MPa(3) Busbar protection operation(4) Circuit breaker failure protection operation(5) Line distance protection zone II or zone III operation(6) Short lead protection operation of circuit breaker(7) Presence of remote tripping signal(8)
12/15/2025
Application of Auto-Reclosing Residual Current Protective Devices in Lightning Protection for Communication Power Supplies
1. Power Interruption Problems Caused by RCD False Tripping During Lightning StrikesA typical communication power supply circuit is shown in Figure 1. A residual current device (RCD) is installed at the power supply input terminal. The RCD primarily provides protection against electrical equipment leakage currents to ensure personal safety, while surge protective devices (SPDs) are installed on power supply branches to protect against lightning intrusions. When lightning strikes occur, the senso
12/15/2025
Related Products
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.