Optimisation SF6 handling procedures during on-site testing and commissioning for GIS

Edwiin
03/11/2025

Gas Compartment Design and Optimization

Pre-filled SF6 Gas Compartments

Gas compartments are pre-filled with sulfur hexafluoride (SF6) at a pressure slightly above atmospheric pressure for transportation. This ensures that the equipment remains stable during transit and reduces the workload required for on-site installation.

Optimization to Minimize SF6 Usage

Gas compartments are optimized to use the minimum amount of SF6 necessary for a given functionality. Since the lowest achievable SF6 recovery pressure is defined, the mass of SF6 released into the atmosphere is directly proportional to the size of the gas compartment. Through this optimization, the usage of SF6 can be minimized, thereby reducing environmental impact.

Use of Cable Plugs for Connecting High-Voltage Cables

Cable plugs are used to connect high-voltage cables, eliminating the need for complete SF6 recovery or opening the gas compartment when connecting the cables to the GIS. The cable compartment includes a socket, and the cables are simply plugged in. This method simplifies the connection process while maintaining the system's seal and safety.

Utilizing Power Voltage Transformers (VT) for High-Voltage Testing

During high-voltage testing, power voltage transformers (VT) can energize from the low-voltage side, thus avoiding the need to handle SF6 to connect the high-voltage source for testing. After the high-voltage test, the power VT can continue to function as a standard instrument transformer. This approach not only enhances testing efficiency but also reduces the need for SF6 handling.

Use of Bushing Connections for High-Voltage Testing

Bushing connections can be used to connect the high-voltage source for testing without the need to handle SF6. However, this method may introduce some limitations related to on-site partial discharge tests. Despite these limitations, it still provides a convenient and environmentally friendly way to perform high-voltage tests.

Edwiin

What are the applications of GIS voltage transformers in digital substations?
What are the applications of GIS voltage transformers in digital substations?
Hey everyone, I’m Echo, and I’ve been working with voltage transformers (VTs) for 12 years.From learning how to wire and do error tests under my mentor’s watchful eye, to now participating in all kinds of smart substation projects — I’ve seen the power industry evolve from traditional systems to fully digital ones. Especially in recent years, more and more 220 kV GIS systems are adopting electronic voltage transformers (EVTs), slowly replacing the old-school electro
Echo
07/09/2025
What should be noted when selecting and installing GIS voltage transformers?
What should be noted when selecting and installing GIS voltage transformers?
In power systems, voltage transformers in GIS (Gas Insulated Switchgear) play a crucial role in voltage measurement and relay protection. Selecting the right model and installing it correctly is vital for the stable operation of the equipment. The following points should be noted regarding selection and installation.I. Key Points for Selection(1) Matching Rated ParametersVoltage Level: It must be consistent with the voltage level of the GIS system. For example, 110kV and 220kV GIS systems requir
James
07/08/2025
What are the causes of the breakdown and burning of the 35 kV GIS voltage transformer?
What are the causes of the breakdown and burning of the 35 kV GIS voltage transformer?
1. Accident Overview1.1 Structure and Connection of 35kV GIS Switchgear Voltage TransformerThe ZX2 gas-insulated double-bus switchgear, manufactured in March 2011 and officially put into operation in July 2012, is configured with two groups of bus voltage transformers (PTs) for each bus section. The two PT groups of the same bus section are designed in one switchgear cabinet with a width of 600 mm. The three-phase PTs are arranged in a triangular formation at the bottom of the cabinet.The PTs ar
Felix Spark
07/08/2025
What Are the Steps for Error Testing GIS Voltage Transformers?
What Are the Steps for Error Testing GIS Voltage Transformers?
Hey everyone, I'm Oliver, and I've been working with current transformers (CTs) and voltage transformers (VTs) for 8 years.From assisting my mentor on site to leading high-voltage testing teams and conducting error calibrations independently, I’ve dealt with all kinds of instrument transformers — especially those used in GIS systems. The error test for voltage transformers is something I perform regularly.A few days ago, a friend asked me:“Oliver, how exactly do you perform an
Oliver Watts
07/08/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!