First trip testing method for circuit breakers

Edwiin
Edwiin
Field: Power switch
China

00.jpg

“First trip” testing is crucial for assessing the condition of the coil operating mechanism and providing insights into how the circuit breaker will perform in an actual fault scenario. Thus, capturing the first trip operation is fundamental for effective circuit breaker condition monitoring.

A circuit breaker spends the majority of its lifespan conducting current without any operation. Once the protective relay detects an issue, a circuit breaker that may have been idle for a year or even longer must operate as swiftly as possible. However, if a circuit breaker has not been actuated for an extended period, latch friction may increase. Information regarding latch friction can be gleaned from the coil current waveform recorded during the first trip operation.

The most significant advantage of first trip testing lies in its ability to simulate “real - world” operating conditions. If a circuit breaker has not been operational for a year, first trip testing can reveal whether it has become slower due to issues such as corrosion in the mechanism linkages. In contrast, traditional testing methods are carried out after the circuit breaker has been taken out of service and has been operated one or even two times.

When a fault occurs, proper operation of the circuit breaker (CB) is expected. Regrettably, environmental contaminants, hardened grease, vibration, and other factors can negatively impact the circuit breaker's operating time. Often, this problem resolves after the breaker's first operation, making it impossible to detect the root cause in subsequent tests.

Modern CB analyzers offer an online testing mode that can record the first on - line trip time without being isolated from the grid. Online first trip testing provides three key advantages:

  • Time and resource savings: It reduces the need for extensive offline testing procedures, saving both time and resources.

  • Diagnostic determination: It helps determine whether a CB requires offline diagnostic testing.

  • Slow operation capture: It can capture instances of slow CB operation during the first trip test.

  • The first online testing measurements typically include the following aspects:

  • Trip and Close Coil Current: Measuring the current in the trip and close coils.

  • Main Contact Timing: Determining the timing of the main contacts' opening and closing.

  • Battery Voltage graph: Monitoring the battery voltage over time.

  • Auxiliary Contact Inputs: Recording the status of auxiliary contact inputs.

In the figure, a typical connection diagram for an online test from Vanguard Instruments Company is shown. Three non - contact AC current probes, connected to the CB bushing CT secondary winding, are used to detect the main contact current. Since the timer can detect when the trip or close operation is initiated, the contact time can be determined based on the presence or absence of the bushing current.

Give a tip and encourage the author!
Recommended
 Causes and Preventive Measures of Fire and Explosion in Oil Circuit Breakers
Causes and Preventive Measures of Fire and Explosion in Oil Circuit Breakers
Causes of Fire and Explosion in Oil Circuit Breakers When the oil level in an oil circuit breaker is too low, the oil layer covering the contacts becomes too thin. Under the effect of the electric arc, the oil decomposes and releases flammable gases. These gases accumulate in the space beneath the top cover, mixing with air to form an explosive mixture, which can ignite or explode under high temperature. If the oil level inside the tank is too high, the released gases have limited space to expan
Felix Spark
11/06/2025
THD Measurement Error Standards for Power Systems
THD Measurement Error Standards for Power Systems
Error Tolerance of Total Harmonic Distortion (THD): A Comprehensive Analysis Based on Application Scenarios, Equipment Accuracy, and Industry StandardsThe acceptable error range for Total Harmonic Distortion (THD) must be evaluated based on specific application contexts, measurement equipment accuracy, and applicable industry standards. Below is a detailed analysis of key performance indicators in power systems, industrial equipment, and general measurement applications.1. Harmonic Error Standar
Edwiin
11/03/2025
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
How Vacuum Tech Replaces SF6 in Modern Ring Main Units
Ring main units (RMUs) are used in secondary power distribution, directly connecting to end-users such as residential communities, construction sites, commercial buildings, highways, etc.In a residential substation, the RMU introduces 12 kV medium voltage, which is then stepped down to 380 V low voltage through transformers. The low-voltage switchgear distributes electrical energy to various user units. For a 1250 kVA distribution transformer in a residential community, the medium-voltage ring m
James
11/03/2025
Why Monitoring Accuracy Matters in Power Quality Systems
Why Monitoring Accuracy Matters in Power Quality Systems
The Critical Role of Monitoring Accuracy in Power Quality Online DevicesThe measurement accuracy of online power quality monitoring devices is the core of the power system’s “perception capability,” directly determining the safety, economy, stability, and reliability of power supply to users. Inadequate accuracy leads to misjudgment, incorrect control, and flawed decision-making—potentially causing equipment damage, economic losses, or even grid failures. Conversely, high accuracy enables precis
Oliver Watts
10/30/2025
Send inquiry
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.