Load Factor: What is it? (And How To Calculate It)

Electrical4u
Field: Basic Electrical
0
China
What Is Load Factor

What is Load Factor?

In electrical engineering, the Load Factor is defined as a ratio of the average load divided by the maximum (or peak) load in a given time of period. In other words, the Load Factor is the ratio of total energy (kWh) used over a specific period of time to the total possible energy available within that period (i.e. peak demand over that specific time period). Load Factor can be calculated on a daily, monthly, or yearly basis. The equation of Load Factor is;

  \[ Load \, Factor = \frac{Average \, Load}{Maximum \, demand \, over \, specific \, time \, of \, period} \]

The Load Factor is used to measure the utilization rate (means the efficiency of usage of electrical energy). The value of the Load Factor is always less than one. Because the average load will always less than the maximum demand.

The high value of Load Factor means the load is using electrical energy more efficiently. High Load Factor gives more saving of electrical energy. And low Load Factor means the electricity used insufficiently compared to your maximum demand.

Improved load factor means to reduce the peak load demand. This will increase the value of the Load Factor and saves electrical energy. It will also reduce the average cost per unit (kWh). This procedure is also known as load balancing or peak saving.

Improved load factor means to reduce the peak load demand. This will increase the value of the Load Factor and saves electrical energy. It will also reduce the average cost per unit (kWh). This procedure is also known as load balancing or peak saving.

A low load factor means high maximum demand and low utilization rate. If the Load factor is very low as high peak demand, the capacity of electrical energy remains inactive for a long time. And this will increase the per-unit cost of electrical energy to the consumer. To reduce the peak demand, shift some load from peak time to non-peak time.  

For generators or power plants, the Load Factor is an important factor to find the efficiency of the power plant. For power plants, the Load Factor is defined as a ratio of energy generated in a given time of period to the product of maximum load and number of hours of operation.

  \[ Load \, Factor =\frac{ Energy \, Generated \, in \,  a \, Given \, Period \,  }{ Maximum \, Load \times Hours \, of \, Operation} \]

How to Calculate Load Factor?

The Load Factor is calculated by dividing the total consumption of electrical energy (kWh) for a given specific time of period to the product of maximum demand (kW) and the number of hours in that period.

The Load Factor can be calculated over any time of period. Generally, it is calculated based on a daily, weekly, monthly, or annual basis. The below equations show the Load Factor for a different time.

  \[ Load \, Factor \, (daily) = \frac{Total \, kWh \, throughout \, 24 Hr \, of \, the \, day}{Peak \, Load \,  in \, kW \times 24 Hr} \]

  \[ Load \, Factor \, (Monthly) = \frac{Total \, kWh \, throughout \, the \, Month}{Peak \, Load \,  in \, kW \times 720 Hr} \]

  \[ Load \, Factor \, (Annual) = \frac{Total \, kWh \, throughout \, the \, Year}{Peak \, Load \,  in \, kW \times 8760 Hr} \]

Load Factor Example Question

Let’s calculate the Load Factor for the below condition. The above equations are multiplied by 100 to calculate the Load Factor in terms of percentage.

Monthly energy consumption is 36000 kWh and maximum demand of 100 kW.

  \[ Load \, Factor = \frac{Total kWh \times 100}{Peak \, demand \times No. \, of \, days \times 24 \, Hours} \]


  \[ Load \, Factor = \frac{36000 \, kWh \times 100}{100\, kW \times 30 \, days \times 24 \, Hours} \]


  \[  Load \, Factor = 50 \% \]

Let’s take the same example but the maximum demand is reduced from 100 kW to 70 kW.

  \[ Load \, Factor = \frac{36000 \, kWh \times 100}{70 \, kW \times 30 \, days \times 24 \, Hours} \]

  \[  Load \, Factor = 71.43 \% \]

So, the Load Factor is improved by reducing the maximum demand.

How to Improve Load Factor?

The load factor is a ratio of average load to the maximum demand. Hence, it depends on the value of the average load and maximum demand. The consumer tries to keep the load factor as high as possible. Load Factor cannot be more than one as the average load is always less than the maximum demand.

The meaning of improving Load Factor means to increase the value of Load Factor. If the consumer tries to keep average load near the maximum demand, then the Load Factor will increase.

But instead of varying the average load, it is easy for consumers to reduce the maximum demand. The maximum demand can be reduced by shifting peak load to below-average load. The below figure shows the load curve for a day.

Load Curve
Load Curve

From the above figure, we can conclude that the load demand is very high during the period 8-16. If we shift some load during below average load period like 4-8 or 20-24. Then the maximum demand will be reduced and it helps to improve the Load Factor. And this will helps to reduce the amount to pay for per unit charge of electricity to consumers.

Statement: Respect the original, good articles worth sharing, if there is infringement please contact delete.

Give a tip and encourage the author!

Recommended

Main Transformer Accidents and Light Gas Operation Issues
1. Accident Record (March 19, 2019)At 16:13 on March 19, 2019, the monitoring background reported a light gas action of No. 3 main transformer. In accordance with the Code for Operation of Power Transformers (DL/T572-2010), operation and maintenance (O&M) personnel inspected the on-site condition of No. 3 main transformer.On-site confirmation: The WBH non-electrical protection panel of No. 3 main transformer reported a Phase B light gas action of the transformer body, and the reset was ineff
02/05/2026
Faults and Handling of Single-phase Grounding in 10kV Distribution Lines
Characteristics and Detection Devices for Single-Phase Ground Faults1. Characteristics of Single-Phase Ground FaultsCentral Alarm Signals:The warning bell rings, and the indicator lamp labeled “Ground Fault on [X] kV Bus Section [Y]” illuminates. In systems with a Petersen coil (arc suppression coil) grounding the neutral point, the “Petersen Coil Operated” indicator also lights up.Insulation Monitoring Voltmeter Indications:The voltage of the faulted phase decreases (in
01/30/2026
Neutral point grounding operation mode for 110kV~220kV power grid transformers
The arrangement of neutral point grounding operation modes for 110kV~220kV power grid transformers shall meet the insulation withstand requirements of transformer neutral points, and shall also strive to keep the zero-sequence impedance of substations basically unchanged, while ensuring that the zero-sequence comprehensive impedance at any short-circuit point in the system does not exceed three times the positive-sequence comprehensive impedance.For 220kV and 110kV transformers in new constructi
01/29/2026
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?
Why Do Substations Use Stones, Gravel, Pebbles, and Crushed Rock?In substations, equipment such as power and distribution transformers, transmission lines, voltage transformers, current transformers, and disconnect switches all require grounding. Beyond grounding, we will now explore in depth why gravel and crushed stone are commonly used in substations. Though they appear ordinary, these stones play a critical safety and functional role.In substation grounding design—especially when multiple gr
01/29/2026
Related Products
Send inquiry
+86
Click to upload file
Download
Get the IEE Business Application
Use the IEE-Business app to find equipment, obtain solutions, connect with experts, and participate in industry collaboration anytime, anywhere—fully supporting the development of your power projects and business.