Verification of time quantities in commissioning test for Generator circuit breaker (GCB) according to IEC/IEEE

Edwiin
04/24/2025

Commissioning Tests for Generator Circuit Breakers

Once a Generator circuit breaker has been installed, comprehensive commissioning tests must be conducted. The primary objectives of these tests are to:
  • Ensure that no damage has occurred during transportation and storage.
  • Verify the compatibility of individual components.
  • Confirm that the assembly has been carried out correctly.
  • Validate the proper performance of the fully assembled generator circuit breaker.

Verification of Generator Circuit Breaker Time Quantities

During commissioning, the following time - related parameters of the generator circuit breaker need to be verified:

Closing and Opening Times, Time Spread

Measurements should be taken at the maximum pressure and at the supply voltage of the auxiliary and control circuits. The voltage should be measured at the equipment terminals and under typical load conditions of the supply voltage source. The specific measurements include:
  • Closing Time: For each pole, determine the individual closing time, the time spread among the poles, and, if feasible, the time spread of the breaking units or groups of units within each pole.
  • Opening Time: Similarly, measure the opening time of each pole, the time spread of the poles, and, where possible, the time spread of the breaking units or groups of units per pole.
These measurements should be performed for both separate opening and closing operations, as well as for the opening and closing operations within a CO (close - open) operating cycle. In cases where the circuit breaker is equipped with multiple trip coils, all coils must be tested, and the corresponding times for each coil should be accurately recorded.
It is essential to document the supply voltage both before and during the operations. Additionally, if a three - pole control relay is present, the moment it is energized should be recorded. This information is crucial for calculating the total time in three - pole operation, which is the sum of the relay activation time and either the closing or opening time. When the circuit breaker incorporates resistor closing or opening units, the resistor insertion times must also be carefully recorded.

Operation of Control and Auxiliary Contacts

The timing of the operation of one representative of each type (make and break) of control and auxiliary contacts should be determined relative to the operation of the main contacts during both the closing and opening of the generator circuit breaker. This ensures proper coordination and functionality of the control and monitoring elements associated with the circuit breaker.
Recharging Time of the Operating Mechanism
The relevant recharging times must be verified according to the type of operating mechanism:
  • Fluid - Operated Mechanism:
    • Measure the operation time of the pumping device (such as a pump, compressor, or control valve) in the following scenarios:
      • Between the minimum and maximum pressure levels (corresponding to the cut - in and cut - off points of the pumping device).
      • During specific operations or sequences, each starting from the minimum pressure (cut - in of the pumping device), including:
        • Closing all three poles.
        • Opening all three poles.
        • Performing a CO operation on all three poles.
  • Spring - Operated Mechanism: Measure the recharging time of the motor after a closing operation, ensuring that the measurement is taken at the actual site supply voltage. This helps to confirm that the spring - charging mechanism can quickly and effectively prepare the circuit breaker for subsequent operations.
Edwiin

Analysis of Transformer Capacity, Load Rate and Number of Units Selection Issues
Analysis of Transformer Capacity, Load Rate and Number of Units Selection Issues
The safe and economical operation of power transformers is related to the safety, economy, stability, and reliability of the operations of various industries. The limitations of conditions such as the investment economic indicators for its selection, the economic benefits of maintenance and operation, and the adaptability in the new environment (access of distributed power sources, configuration of energy storage, etc.) make it impossible to include comprehensive factors in other aspects.The cap
Leon
07/17/2025
What should be noted when using indoor vacuum circuit breakers?
What should be noted when using indoor vacuum circuit breakers?
I. Overvoltage PreventionVacuum circuit breakers excel in interrupting performance, but high overvoltage may occur across inductors during the switching of inductive loads due to abrupt changes in loop current, which requires special attention. When switching small-capacity motors, starting currents are large, so measures like step-down starting should be adopted to limit the current.Transformers with different structures show distinct characteristics: oil-immersed transformers have high impulse
Echo
06/10/2025
The application of indoor high-voltage vacuum circuit breakers
The application of indoor high-voltage vacuum circuit breakers
In the first half of 2007, as project participants from the Electromechanical Equipment Company of Huaibei Mining Group, we carried out a technical transformation of the 10kV substation in the East Factory Area. Our primary task was to replace the original 10kV disconnector - oil - immersed circuit breaker units with ZN20 indoor high - voltage vacuum circuit breakers.Previously, the SN10 - 10 oil - immersed circuit breakers had been in operation for an extended period, leading to severe oil leak
Echo
06/09/2025
What are the common faults and corresponding solutions for indoor drawer-type high-voltage vacuum circuit breakers?
What are the common faults and corresponding solutions for indoor drawer-type high-voltage vacuum circuit breakers?
Inability to Push In or Withdraw the Draw-out CarriageThe main manifestation is difficulty in inserting the carriage, which may cause equipment damage and threaten production when severe. The causes and countermeasures are shown in Table 1.The circuit - breaker fails to close. It manifests as the closing core actuating but the circuit - breaker not closing successfully; or the closing core not actuating, which shows that the control circuit of the circuit - breaker is open - circuited or the mec
Felix Spark
06/09/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!