Verification of time quantities in commissioning test for Generator circuit breaker (GCB) according to IEC/IEEE

04/24/2025

Commissioning Tests for Generator Circuit Breakers

Once a Generator circuit breaker has been installed, comprehensive commissioning tests must be conducted. The primary objectives of these tests are to:
  • Ensure that no damage has occurred during transportation and storage.
  • Verify the compatibility of individual components.
  • Confirm that the assembly has been carried out correctly.
  • Validate the proper performance of the fully assembled generator circuit breaker.

Verification of Generator Circuit Breaker Time Quantities

During commissioning, the following time - related parameters of the generator circuit breaker need to be verified:

Closing and Opening Times, Time Spread

Measurements should be taken at the maximum pressure and at the supply voltage of the auxiliary and control circuits. The voltage should be measured at the equipment terminals and under typical load conditions of the supply voltage source. The specific measurements include:
  • Closing Time: For each pole, determine the individual closing time, the time spread among the poles, and, if feasible, the time spread of the breaking units or groups of units within each pole.
  • Opening Time: Similarly, measure the opening time of each pole, the time spread of the poles, and, where possible, the time spread of the breaking units or groups of units per pole.
These measurements should be performed for both separate opening and closing operations, as well as for the opening and closing operations within a CO (close - open) operating cycle. In cases where the circuit breaker is equipped with multiple trip coils, all coils must be tested, and the corresponding times for each coil should be accurately recorded.
It is essential to document the supply voltage both before and during the operations. Additionally, if a three - pole control relay is present, the moment it is energized should be recorded. This information is crucial for calculating the total time in three - pole operation, which is the sum of the relay activation time and either the closing or opening time. When the circuit breaker incorporates resistor closing or opening units, the resistor insertion times must also be carefully recorded.

Operation of Control and Auxiliary Contacts

The timing of the operation of one representative of each type (make and break) of control and auxiliary contacts should be determined relative to the operation of the main contacts during both the closing and opening of the generator circuit breaker. This ensures proper coordination and functionality of the control and monitoring elements associated with the circuit breaker.
Recharging Time of the Operating Mechanism
The relevant recharging times must be verified according to the type of operating mechanism:
  • Fluid - Operated Mechanism:
    • Measure the operation time of the pumping device (such as a pump, compressor, or control valve) in the following scenarios:
      • Between the minimum and maximum pressure levels (corresponding to the cut - in and cut - off points of the pumping device).
      • During specific operations or sequences, each starting from the minimum pressure (cut - in of the pumping device), including:
        • Closing all three poles.
        • Opening all three poles.
        • Performing a CO operation on all three poles.
  • Spring - Operated Mechanism: Measure the recharging time of the motor after a closing operation, ensuring that the measurement is taken at the actual site supply voltage. This helps to confirm that the spring - charging mechanism can quickly and effectively prepare the circuit breaker for subsequent operations.

Hey there! I'm an electrical engineer specializing in Failure and Maintenance. I've dedicated my career to ensuring the seamless operation of electrical systems. I excel at diagnosing complex electrical failures, from malfunctioning industrial motors to glitchy power distribution networks. Using state - of - the - art diagnostic tools and my in - depth knowledge, I pinpoint issues quickly. On this platform, I'm eager to share my insights, exchange ideas, and collaborate with fellow experts. Let's work together to enhance the reliability of electrical setups.

What factors need to be considered when designing a transformer?
What factors need to be considered when designing a transformer?
Transformer design is a complex process that requires consideration of multiple factors to ensure safe and efficient operation. In addition, compliance with international and local regulations is essential to guarantee that transformers meet safety and performance standards. Below are key factors to consider in transformer design and the relevant regulations to follow:Transformer Design Factors: Voltage and Frequency: Determine the input and output voltage levels and the operating frequency. The
Vziman
09/02/2025
What failure modes are possible in a transformer? How to identify and fix these failures?
What failure modes are possible in a transformer? How to identify and fix these failures?
Transformers are critical components in power systems, and various failure modes can affect their operation. Timely identification and resolution of these failure modes are essential to prevent costly downtime and ensure system reliability. Below are some common transformer failure modes, along with methods to identify and address them: Insulation FailureIdentification: Insulation failure leads to decreased insulation resistance, which can be detected through insulation resistance testing (megge
09/02/2025
A hybrid DC circuit breaker
A hybrid DC circuit breaker
Most DC molded-case circuit breakers use natural air arc extinction, and there are typically two arc extinguishing methods: one is conventional opening and closing, where the contacts axially stretch the arc, while the conductive circuit generates a magnetic field that bends and elongates the arc, pulling it lengthwise perpendicular to the arc axis. This not only increases the arc length but also induces lateral motion, enabling air cooling to achieve arc extinction.The other method involves the
09/02/2025
Working Principle and Arc Extinction Mechanism of Magnetic Blowout Device in DC Circuit Breakers
Working Principle and Arc Extinction Mechanism of Magnetic Blowout Device in DC Circuit Breakers
The arc extinguishing system of a DC circuit breaker is crucial for the safe operation of equipment, as the arc generated during current interruption can damage contacts and compromise insulation.In AC systems, the current naturally passes through zero twice per cycle, and AC circuit breakers take full advantage of these zero-crossing points to extinguish the arc.However, DC systems lack natural current zero crossings, making arc extinction significantly more difficult for DC circuit breakers. T
09/02/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!