1. Specificities and Testing Requirements of Photovoltaic Transformers
As a new energy systems technician, I recognize photovoltaic transformers' unique design and application traits: Inverter - output AC carries abundant 5th/7th - order odd harmonics, with PCC harmonic current distortion reaching 1.8% (higher voltage distortion under low load), causing winding overheating and accelerated insulation aging. Photovoltaic systems use TN - S grounding, requiring reliable N - phase output from the secondary side to avoid short circuits. Environmentally, they must withstand 60°C desert heat, coastal salt spray, and industrial EMI.
These specifics dictate testing uniqueness: Beyond conventional DC resistance, voltage ratio, insulation, and withstand voltage tests, add harmonic detection (Fluke F435 for THD), temperature rise monitoring (infrared imagers), grounding system checks (four - terminal method for ≤0.1Ω contact resistance), and short - circuit impedance testing. The core aim is ensuring safe operation in power electronic environments while preventing harmonic, thermal, and grounding - related risks.
2. Conventional Testing Items and Tool Selection for Photovoltaic Transformers
2.1 DC Resistance Test
This key test identifies inter - turn short circuits or loose connections in windings. The four - terminal method is used to eliminate line resistance interference, with procedures including power-off discharge, winding cleaning, temperature measurement, current selection (1A/10A), and temperature correction. The ZSCZ - 8900 DC resistance tester (accuracy: 0.2%±2μΩ, resolution: 0.1μΩ) meets high - precision requirements. Measured values must be compared with standards/historical data; significant deviations may indicate faults - as seen in a case where poor winding contact was detected via DC resistance testing and later repaired.
2.2 Voltage Ratio Test
This verifies whether winding turns ratios align with design specifications to ensure stable voltage output under load. The dual - voltmeter method calculates ratios by measuring primary/secondary voltages under no - load conditions, while the voltage ratio bridge method offers higher precision. For instance, a voltage imbalance in the low - voltage output of an 800V/400V transformer, caused by a high - voltage side open circuit, was identified through voltage ratio testing.
2.3 Insulation Performance Test
  • Insulation Resistance Test: Using an MI - 2094H megohmmeter, measure insulation resistance between windings and between windings and the core (required ≥300MΩ).
  • Withstand Voltage Test: Apply 2× rated voltage for 60 minutes to check for breakdown. Ensure power is off, disconnected from live equipment, and surfaces are clean before testing.
2.4 Short - Circuit Impedance Test
The volt - ampere method evaluates short - circuit tolerance: one side is shorted, and a test voltage is applied to the other side to drive rated current through windings, measured by a CS - 8 impedance tester. A change >±2% from the factory value may indicate winding deformation. Note: Test current should be controlled at 0.5% - 1% of rated current to avoid waveform distortion.
2.5 Temperature Rise Test
After full - load operation, measure temperatures of windings, core, and casing using thermometers or infrared thermometers. Temperature rises should be ≤60K for oil - immersed transformers and ≤75K for dry - type transformers. A dry - type transformer operating in a 60°C environment that maintained a temperature rise within 65K extended its service life effectively.
2.6 Grounding System Test
The four - terminal method measures grounding continuity to avoid misjudgments from the two - terminal method. Common faults include rusted connections or plastic washer misuse, requiring regular inspection. Four - terminal ground resistance testers ensure measurements meet the 0.1Ω standard.
2.7 Harmonic Detection
A unique test for photovoltaic systems, using Fluke F435 at the PCC to detect harmonics up to the 50th order (focusing on 5th/7th orders). Results must comply with GB/T 14549 - 93, providing data for equipment optimization.
3. On - site Testing Procedures and Safety Specifications for Photovoltaic Transformers
3.1 Pre - testing Preparation
Develop detailed plans specifying project information, testing items, and equipment lists (including high - precision power analyzers, power quality testers, infrared thermal imagers, etc.). Check equipment integrity and power voltage (220V±10%), and monitor environmental conditions - such as irradiance ≥700W/m², irradiance variation <2% in the preceding 5 minutes, no strong winds or clouds - to ensure test accuracy.
3.2 Electrical Connection Inspection
Use a phase volt - ampere meter to verify inverter output polarity matches the transformer's primary corresponding terminal, preventing circulating current losses. Inspect cable connections for tightness. For oil - immersed transformers, check oil level and color; for dry - type transformers, verify cooling fans operate normally.
3.3 Insulation Resistance Test
With power off, use a megohmmeter to test high/low - voltage windings and grounding, recording 1 - minute stable values. A sudden resistance drop indicates insulation issues. Detailed test reports must be compiled post - testing.
3.4 AC Withstand Voltage Test
Connect the withstand voltage device's output to test points, set parameters to 2× rated voltage, gradually increase voltage while monitoring for breakdown, and maintain for 60 minutes before reducing voltage.
3.5 Load Test
Measure output voltage, current, and power under full - load operation to calculate efficiency and voltage regulation rate, while monitoring temperature rise. Increase load current gradually and record parameter changes for analysis.
3.6 Short - Circuit Impedance Test
Apply voltage to the high - voltage side with the low - voltage side shorted (using wires with sufficient cross - section). Control test current at 0.5% - 1% of rated value and correct results for temperature (75°C for oil - immersed, 120°C for dry - type) to avoid misjudging winding deformation.
3.7 Harmonic Detection
Use a power quality analyzer at the PCC to monitor odd - order harmonic content and calculate THD, ensuring compliance with national standards for safe operation in harmonic environments.
Oliver Watts

Hey! I'm Oliver Watts, an electrical engineer in Inspection and Testing. With years of hands - on experience, I ensure electrical systems meet top safety and performance standards. Using advanced gear, I conduct diverse tests, easily spotting issues in both large - scale industrial and small - scale commercial setups. I love teaming up, sharing knowledge, and keeping up with industry regs. Also, I'm skilled at data analysis with software. If you're into electrical inspection or just want to chat engineering, reach out. Let's connect and explore!

A Quick Verification Method for Low-Voltage Current Transformers
A Quick Verification Method for Low-Voltage Current Transformers
To ensure safe operation of the power system, power equipment operation must be monitored/measured. General devices can’t connect to primary high - voltage equipment directly; instead, large primary currents are scaled down for current transformation, electrical isolation, and use by measurement/protection devices. For AC large - current measurement, conversion to a unified current eases secondary instrument use.Current transformers split into measurement - and protection - type, with accu
Oliver Watts
07/16/2025
What Tests Are Required for a Qualified AIS Voltage Transformer?
What Tests Are Required for a Qualified AIS Voltage Transformer?
Hey everyone! I’m Oliver, an experienced electrician with over a decade in the power system industry. Today, we’re diving into a practical topic — what tests are required to ensure an Air Insulated Switchgear (AIS) voltage transformer is qualified? These tests are crucial not only for ensuring the device operates correctly but also for maintaining the safety and stability of the power grid. Let’s get started!1. Visual InspectionFirst Look MattersThe very first step is a v
Oliver Watts
07/14/2025
What Tests Must a Qualified AIS Current Transformer Undergo?
What Tests Must a Qualified AIS Current Transformer Undergo?
Hey everyone, I’m Oliver, a 10-year veteran in the power system industry. Today we’re going to talk about a very practical topic — how do you know if a current transformer (CT) used in Air Insulated Switchgear (AIS) is truly qualified? This isn’t just about meeting technical specs; it’s directly tied to equipment safety, grid stability, and accurate metering.Let’s dive in — based on my real-world experience.IntroductionIn substations or distribution syst
Oliver Watts
07/12/2025
What are the routine tests for outdoor voltage transformers?
What are the routine tests for outdoor voltage transformers?
1. IntroductionOutdoor voltage transformers are key equipment for ensuring the safety of electrical apparatus. Scientific and comprehensive test analysis is required to avoid hazards and property losses caused by improper operation. Test analysis can guide the formulation of operation strategies and precautions, ensure the stable operation of equipment, and maximize economic and social benefits.2. Concept of Outdoor Voltage TransformersAn outdoor voltage transformer is essentially an outdoor ste
Oliver Watts
07/10/2025
Inquiry
Download
IEE-Business is dedicated to serving the personnel in the global power industry.
Join IEE-Business, not only can you discover power equipment and power knowledge, but also canhnd like - minded friends!