How Often Should Transformers Be Overhauled?

Felix Spark
Felix Spark
Field: Failure and maintenance
China

1. Transformer Major Overhaul Cycle

  • The main transformer shall undergo a core-lifting inspection before being put into service, and thereafter a core-lifting overhaul shall be performed every 5 to 10 years. Core-lifting overhaul shall also be carried out if a fault occurs during operation or if issues are identified during preventive tests.

  • Distribution transformers operating continuously under normal load conditions may be overhauled once every 10 years.

  • For on-load tap-changing transformers, the tap changer mechanism shall be removed for maintenance after reaching the number of operations specified by the manufacturer.

  • Transformers installed in polluted areas shall have their overhaul intervals determined based on accumulated operational experience, test data, and technical records.

2. Steps and Items for Transformer Major Overhaul

  • Pre-overhaul preparation: Review and extract known defects from operation records, verify them on-site, and formulate corrective measures. If major defects require special repair techniques, dedicated technical and organizational safety measures must be developed. Prepare a list of required equipment, materials, and tools in advance, and inspect the overhaul site to ensure all necessary items and environmental conditions are ready.

  • Drain oil, remove the transformer top cover, lift out the core assembly, and inspect windings and core.

  • Overhaul the core, windings, tap changer, and lead wires.

  • Overhaul the top cover, conservator tank, explosion-proof pipe, radiators, oil valves, breather, and bushings.

  • Overhaul the cooling system and oil reclamation unit.

  • Clean the tank shell and repaint if necessary.

  • Overhaul control, measuring instruments, signaling, and protective devices.

  • Filter or replace insulating oil.

  • Dry the insulation if necessary.

  • Reassemble the transformer.

  • Perform measurements and tests according to the prescribed test procedures.

  • After passing all tests, return the transformer to service.

3. Requirements for Transformer Major Overhaul Items

  • To prevent moisture ingress into windings due to prolonged exposure of the core assembly to air, core lifting should be avoided on rainy or humid days. The maximum allowable exposure time of the lifted core in air is as follows:

    • In dry air (relative humidity ≤65%): 16 hours

    • In humid air (relative humidity ≤75%): 12 hours
      Before core lifting, measure ambient temperature and transformer oil temperature. Core lifting may proceed only when the core temperature is approximately 10°C higher than the ambient temperature.

  • For transformers with long service life (e.g., over 20 years), special attention shall be paid during core lifting to check for winding insulation aging. Typically, this is done by pressing the insulation surface with a finger:

    • Good insulation is elastic; it deforms temporarily under finger pressure and recovers its shape upon release, with a light-colored surface.

    • Moderately aged insulation becomes harder and more brittle; finger pressure causes small cracks and the color darkens. In such cases, insulation should be replaced or reinforced as needed.

    • Severely aged insulation cracks easily under finger pressure and flakes off in carbonized particles, requiring complete insulation replacement.

  • Insulating spacers between transformer windings shall be secure; windings must show no looseness, deformation, or displacement. High- and low-voltage windings shall be symmetrical and free of oil-adhered contaminants.

  • Tap changer contacts shall be firm; insulating pressboard and insulating tubing shall be intact and undamaged.

  • Verify that the contact positions, tightening screws, rotating shafts, and markings on the voltage selector switch align correctly with the labels on the cover.

  • The core shall not be loose; oil ducts (cooling channels) between the core and windings must remain unobstructed.

  • The insulation resistance of core-through bolts shall be measured using a 1000 V megohmmeter. The minimum acceptable values are:

    • ≥2 MΩ for 3 kV, 6 kV, and 10 kV transformers

    • ≥5 MΩ for 35 kV transformers

  • The insulation resistance of the secondary circuit of the Buchholz relay shall meet requirements, wiring shall be correct, and the internal float and mercury contacts shall be intact.

  • Oil level in oil-filled bushings shall be maintained at the designated mark.

Give a tip and encourage the author!
Recommended
Adjustment and Precautions for H61 Oil Power 26kV Electric Transformer Tap Changers
Adjustment and Precautions for H61 Oil Power 26kV Electric Transformer Tap Changers
Preparatory Work Before Adjusting the Tap Changer of H61 Oil Power 26kV Electric Transformer Apply for and issue a work permit; carefully fill out the operation ticket; conduct a simulation board operation test to ensure the operation is error-free; confirm the personnel who will carry out and supervise the operation; if load reduction is required, notify affected users in advance. Before construction, power must be disconnected to take the transformer out of service, and voltage testing must be
James
12/08/2025
H59/H61 Transformer Failure Analysis and Protection Measures
H59/H61 Transformer Failure Analysis and Protection Measures
1.Causes of Damage to Agricultural H59/H61 Oil-Immersed Distribution Transformers1.1 Insulation DamageRural power supply commonly uses a 380/220V mixed system. Due to the high proportion of single-phase loads, H59/H61 oil-immersed distribution transformers often operate under significant three-phase load imbalance. In many cases, the degree of three-phase load imbalance far exceeds the limits permitted by operational regulations, causing premature aging, deterioration, and eventual failure of th
Felix Spark
12/08/2025
What Is an H61 Distribution Transformer? Uses & Setup
What Is an H61 Distribution Transformer? Uses & Setup
H61 distribution transformers refer to transformers used in power distribution systems. In a distribution system, high-voltage electricity must be converted into low-voltage electricity via transformers to supply electrical equipment in residential, commercial, and industrial facilities. The H61 distribution transformer is a type of infrastructure equipment primarily used in the following scenarios: Supplying power from high-voltage grids to low-voltage grids: During power delivery, high-voltage
James
12/08/2025
How to Diagnose Faults in H59 Distribution Transformers by Listening to Their Sounds
How to Diagnose Faults in H59 Distribution Transformers by Listening to Their Sounds
In recent years, the accident rate of H59 distribution transformers has shown an upward trend. This article analyzes the causes of failures in H59 distribution transformers and proposes a series of preventive measures to ensure their normal operation and provide effective assurance for power supply.H59 distribution transformers play a vital role in power systems. With the continuous expansion of power system scale and the increasing single-unit capacity of transformers, any transformer failure n